Reasons for placing stage collar inside previous casing
- To avoid jetting effect on the formation
- If stage collar fails, at least OH zone will be cemented
What is a liner
Any string of casing whose top is located below the surface.
What is a tie back
Liner used to cover corroded or damaged zone.
Select the correct plugs used on liner cement jobs
Drill pipe dart & wiper plug
Give the main reason for running tail pipe below a squeeze packer
To avoid cement around the packer
To ensure good placement of slurry across the zone to be squeezed
Squeeze cementing is defined as the process of forcing a cement slurry under pressure
True
What are four reasons you may want to perform a squeeze
- Fix a damaged casing
- Abandon a depleted zone
- Seal off gas zones
- Correct a primary cement job
What is the min compressive strength recommended for drilling
500psi
When performing HP calc for squeeze job the reference point should be
depth of the top perf
In a low pressure sq you do not want to frac the formation the min recommended safety
500psi
Max squeeze volume reached when
The top of cement is at least 1 barrel above top perf, depending on the well configuration.
Main disadvantage of bradenhead head squeeze