Formulas Flashcards
tM
Duration that is most likely to happen
tO
Best-case scenario
tP
Worst-case scenario
Triangular Distribution
tE = (tO + tM + tP)/3
tE
Time Estimate
Beta Distribution
tE - (tO + 4*tM +tP)/6
EV
Earned Value
PV
Planned Value
AC
Actual Cost
Schedule Variance (SV)
EV - PV
Cost Variance (CV)
EV - AC
Schedule Performance Index (SPI)
EV/PV
Cost Performance Index (CPI)
EV/AC
Estimate At Completion (EAC)
AC + Bottom-Up ETC
ETC
Estimate To Complete
Estimate At Completion (EAC) #2
AC + (BAC - EV)
Estimate At Completion (EAC) #3
BAC/CPI
BAC
Budget At Completion
Estimate At Completion (EAC) #4
AC+ [(BAC - EV) / (CPI * SPI)]
Estimate to Complete (ETC)
EAC - AC
To Complete Performance Index (TCPI) #1
(BAC - EV)/(BAC - AC)
To Complete Performance Index (TCPI) #2
(BAC - EV)/(EAC-AC)
Earned Value Analysis
Check PMBOK for a chart
Communication Channels
n*(n-1)/2
n
number of stakeholders