FORMULAE Flashcards

1
Q

New Completion Date

A

New Date: Original Time Estimate/SPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule Performance Index

A

SPI = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Variance

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost Performance Index

A

CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Estimate at Completion

A

EAC = BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Variance

A

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate to Complete

A

ETC = EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

ROI

A

(Benefits-costs)/costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

To-Complete Cost Performance

A

TCPI = (BAC-EV)/(BAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Number of Communications Channels

A

Channels = n(n-1)/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly