FOPR 2 Flashcards

1
Q

Explain the meaning of the ratios for the angle of repose of a cut or fill slope.

2:1 and 3/4:1.

A

indicates the angle of the slope. order of the ratio is sometimes reversed but 1 is always the verticle (rise)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Construction phases of building a road include:

A
  1. Falling and clearing R/W
  2. Stripping (clearing material unsuitable as construction soil)
  3. Sub-grade construction: cut and fills
  4. Drilling and blasting
  5. Drainage structures: bridges and culverts
  6. Ballasting and surfacing: fortifying subgrade if not able to support load
  7. Stabalization: fortifying slope stabiliy risks