Final Revision Flashcards
Name some other programming software other than MS Project?
- ProjectLibre
- Asta Power Project
What was on the critical path in the pre-planning programme?
VP formed the critical path due to the inability to do some of the required surveys such as R&D Asbestos
Bat surveys - requirement to conduct over time (Must have 1 survey in May to August date range) Multiple required overall
Design & Access statement was required prior to submission of some of the architects design
What is the difference between valuation certificate and payment certificate?
Valuation cert is the precursory QS valuation
Pay cert is issued by the EA/CA
Pay cert can be amended to include deductions for LDs or works not in accordance.
What does RAAC stand for?
Reinforced airated autoclaved concrete
How might you improve structural load of an existing building?
Underpinning.
Efficient W2F ratio?
0.4 to 0.5
4 risk headings in NRM1?
Design Development
Construction Risks Estimate
Employer Change Risks
Employer Other Risks
Final account timelines in JCT D&B?
Contractor submit = 2 months post PC
Recommendation issued = 3 months (by EA)
Final account timelines in JCT SBC?
Contractor submit = 6 months post PC
Recommendation issued = 3 months (by CA)
How much was the civils package on the DC project?
£58m final B5.
£38m budget!
Price per KW on London?
£7500/kW
How much was the steels package on the DC project?
£64m final B5.
£55m budget.
Name 10 RICS Black Books?
- Acceleration
- Cashflow
- Change ctrl and management
- Commercial mngmnt
- Conflict avoidance & Dispute Resolution
- Construction Security & Performance Documents
- Cost Reporting
- Defining completion
- EA D&B
- E-Tendering
- EOT’s
- Final Accounts
- Fluctuations
- Interim Valuations & Payment
- Life Cycle Costing
- Management of Risk
- Surveying Safely
- Retention
- Tendering Strategies
- Termination/Corporate Recovery
- Value Management & VE
- Valuing Change
6 bribery prevention things?
P - Proportionate Procedures
T - Top Level Commitment
R - Risk Assessments
D - Due Diligence
C - Communication
M - Monitoring and Review
What is the currently anticipated final cost for the DC build?
Currently excluding all fees, indirects, and contingency pot: £780m
PTE budget = £760m