All Flashcards
What are some examples of unconscious bias?
- Halo effect
- Horns effect
- Authority bias
- Gender bias
- Recency bias
- Beuaty bias
What are the fines under GDPR?
Major breach = £17 million or 4% of turnover
Minor = £8 million or 2% of turnover
(Whichever is higher!)
What are the sections under a JCT D&B?
- Definition and interpretation
- Carrying out of the works
- Control of works
- Payment
- Change
- Injury, damage, insurance
- Assignment, TPR, Collateral warranties
- Termination
- Disputes
If a contractor applied for materials offsite, what are the criteria to do so?
- Proof of ownership transfer
- Insurances
- Labelled clearly with ownership stated
- Offsite material bond (if req. by Client)
If a contractor applied for materials onsite, what are the criteria to do so?
- Be for the works
- Be adequately protected
- Delivered to programme
- Reasonable quantity
What are the standard JCT payment terms?
Interim valuation once a month
Due date 7 days after val. date
Payment notice due 5 days from Due Date
Final Payment Date (21 days from val date or 14 from DD)
21 days total. Can be amended in contract amendments. Typical in industry to go to 28.
What are the two alternative payment types in JCT?
A - Stage.
B - Periodic/interim.
What is your understanding of the HGCRA (1996)?
The amendments seek to provide increased certainty regarding construction payments and to provide a fairer payment regime, improve rights for contractors to suspend works in non-payment circumstances and make adjudication more accessible for the resolution of disputes.
What is the RICS motto?
Est Modus in Rebus - There is measure in all things.
When was RICS founded?
1868
What is the RICS mission statement?
Promote quality and equip members to offer highest standard of services
Promote standards
Lead solutions to major challenges through expertise
What are the PI levels required for a firm?
Based on turnover in preceeding year:
<£100k = £250k
>£100k to 200k = £500k
>£200k+ = £1m
What are the max levels of uninsured excess?
£10m or less = 2.5% of sum insured or £10k
£10m+ = No limit!
What are the 7 obligations firms have to the RICS?
- Have a CPH
- PI cover
- Locum cover
- Co-operate with RICS
- Provide info promptly to standards + regs.
- Display RICS on literature
- Report all matters req. under rules.
What are an RICS members individual CPD requirements?
Applying member = 96 hours. 48 per year. 50/50 split formal/informal.
Member = 20 per year. 50/50 split.
What is the equality act 2010 and what importance does it have?
The act means workplaces must ensure all employees treated fairly and without discrimination.
Some examples:
- Adjustments of accommodation for disabled
- Elimination of discriminatory practices
- Promote diversity in recruitment
- Equal pay between gender
How does change work in FIDIC?
Change can be either via instruction (by client) or proposal (by contractor)
Once instructed, the contractor has 28 days to submit particulars.
Engineer then has 42 days upon receipt to review.
How do rates within valuations work in FIDIC?
Appropriate price as specified in the BOQ/SOW (contract pricing document)
New rate allowed if:
1. Item not identified/non-similar
2. Quantity change of +/- 10%
3. Works are instructed under clause 13 (change)
What is the Bichard Review?
A follow on review from the Levett report reviewing the RICS governance and strategy. It aimed to create new purpose & direction for the RICS and to also prevent previous recurrence of wrongs.
The report gave 36 recommendations, namely:
1. More oversight to governing council, specifically the president.
2. New leadership roles created to simplify governance.
3. Increased importance within leadership on specialisms and geographies.
4. D&I panel
5. Public interest panel.
What is RLBs strategy?
- Have fun - Create great business culture
- Feel valued - Create value for employees
- Make money - 2030 target = £150m turnover, £30m profit.
- Forever - Future proof and sustainable.
What is an RLB goal?
30 by 30!
To have £150m turnover by 2030, of which £30m profit.
What are the adv/disadv of D&B?
Adv:
1. Client bares no risk. The contractor is the single point of responsibility.
2. Early start onsite. (Overlap design/construction)
3. Early price certainty.
4. Buildability advice from contractor. (Technically complex projects may req this)
Disadv:
1. Hard to prepare sufficient brief.
2. Comittment at early design stage.
3. Variations from concept design COSTLY!
4. Difficult to compare tenders.
What is vacant possession?
Must be provided to signify property is physically and legally fit for occupation. It’s a way to ensure that the property is completely empty and ready for the new occupant.
- Must be empty of people & furniture.
- No party holds rights to enter/possess
What is a collateral warranty?
A contract a party in the works warrants to a third party beneficiary that it has fulfilled obligations under the contract.
Collateral warranties provide a bridge between clients and subbies in case of main contractor insolvency.
Differences between JCT & NEC?
JCT is preferred in the private sector for its familiarity and risk transfer.
NEC is chosen for complex, large projects by proactive clients like public bodies and corporations.
JCT tends to allocate risk to contractor.
NEC tends to distribute risks more equitably. Encourages proactive management of risks through early warnings.
JCT allows provisional sums - NEC does not.
Programme a contract doc in NEC - not in JCT.
JCT leaves agreement of FINAL cost till very end.
Whats the difference between value engineering and value management?
Value Engineering:
Focus: Cost reduction.
Timing: Typically during the design phase.
Goal: Identify cost-saving opportunities.
Method: Reevaluate materials and methods.
Value Management:
Focus: Overall project objectives.
Timing: Throughout the project lifecycle.
Goal: Enhance project value and performance.
Method: Broader assessment of project goals.
What is NIA:GIA ratio?
In accordance with RICS measuring practice, it is the Net Interanal Area vs Gross Internal Area .
Below 70% is bad.
Above 85% is good.
What is wall to floor ratio?
Relationship between wall and floor area.
Shows cost efficiency for the building.
The lower the ratio the cheaper the building is to construct; this is because less ext. envelope compared to floor area.
What are some different piling types?
Two main types: End Bearing / Friction Transfer.
Bored (CFA/SFA) - Augur into ground.
Driven - Hammered using vibration.
Screw
Sheet - Type of driven.
Difference between EA/CA?
EA can be employed during pre-contract.
EA involves a more PM/decision-making role that includes scope and budget control.
CA considered a more impartial role only focused on administering the contract (pay certs, variations, disputes)
What is contract execution & contract engrossment?
Execution: Signing of engrossed contract
Engrossment: Preparation of contract
In the DC project, how was the agreement formalized after stage one?
A PCSA was entered into.
- Cost Certainty: Provides a more accurate cost estimate, reducing the likelihood of unexpected expenses.
- Detailed Planning: Allows for the development of detailed project plans and specifications.
- Time Investment: While it may add some time to the project’s timeline due to additional planning, it can lead to time and cost savings by preventing issues and changes during the construction phase.
What are the 8 RIBA Plan of Works stages?
- Strategic Definition
- Prep and brief
- Concept Design
- Developed Design
- Technical Design
- Construction
- Hand-over
- In Use
What is the RIBA plan of works?
It organizes the construction project process into EIGHT stages.
These stages detail the outcomes, core tasks, and information exchanges at each stage.
It provides the project team with a road map for promoting standards and consistency from one stage to the next.
What is CDM? When was it released?
CDM 2015 was most recently updated in Sep 2021.
It is in place to ensure H&S issues are managed in order to reduce risk of harm from building use & maintenance.
What are the key roles in CDM?
PD - Principal Designer
Pre-construction design H&S management
Client
Ensure competency, allow time, allow resource.
Note clients are deemed to be the active PD when appointments aren’t yet made.
What is included in a PCI pack?
Description of works
Client considerations - hoarding, welfare, traffic, permits to work.
Previous H&S files
Existing surveys (services, ground conditions, asbestos, contamination)
Design/construction hazards.
What was the MODUS article on Carbon Blindness about?
It centered around a group called Zero Next. ZN are a construction network demanding carbon action in the sector.
ZN argue Net Zero is far too SLOW.
They want carbon to be valued higher than COST.
They believe we have an over-reliance on fossil fuels.
What was the MODUS article on T Levels about?
T Levels are a post 16 qualification that take 2 years to complete
T levels aim to enable young people into trades more easily.
Allows companies to ‘try before they buy’
What is the dispute resolution process in FIDIC?
- Engineer review & decision.
- Review by DAB
- Arbitration or Litigation
What are default payment terms in the FIDIC?
- Pay app (monthly)
- Pay cert/pay notice (28 days)
- Payment release (56 days total (+28 days))
Why is cashflow so important to Microsoft?
Projects are financed via debt.
This creates a fixed obligation that puts pressure on cashflow accuracy.
It is financed this way to provide tax relief, as interest payments on debt can be tax deductible.
What is the Building Safety Act (2022)?
The Act was enacted with the aim of improving the standard of buildings in England and securing the safety of people in or about those buildings, with a particular focus on fire safety.
Applies to: 18 Meters High OR 7 Storeys
Enforces more onerous design, refurb and construction requirements.
How do variations work under JCT?
- Notification - Party requesting change gives notice in writing to other parties.
- Evaluation - Period of time granted to review - duration dependent on scope of change.
- Agreement.
- Implementation.
What is the LDEDA?
LDEDA (2009) was put in place to close loopholes in the HGCRA (1996).
Payment Notices: The LDEDA mandates the issuance of a ‘payment notice’ for every construction contract payment.
Equitable Payment System: The LDEDA establishes a more equitable payment system, ensuring timely and fair payments.
Right to Suspend Work: The LDEDA enhances the right of contractors to suspend work in the event of delayed payments.
Dispute Resolution: The LDEDA streamlines the adjudication process for dispute resolution in construction contracts.
What are the sections in the JCT D&B? (9)
- Definitions
- Carrying out works
- Control of works
- Payment
- Change
- Insurance
- Bonds, TPR, Assignment, Collat. Warranties
- Termination
- Dispute
How can you easily assess a buildings efficiency and VFM?
Gross Internal Area to Net Internal Area rATIO.
A higher ratio indicates more usable area = more rental yield.
1.1 to 1.2 is a strong ratio.
What is a good Wall2Floor ratio?
0.2 to 0.3
Differences between JCT/NEC?
JCT
Client favoured
No programme contract doc
Reactionary to change
Disputes: Adj/Arb/Liti
CA/EA
NEC
Risk sharing / Mutual trust
Programme is contract doc
Early warnings and focus on risk reduction
Disputes: DRB / Adjudication
PM (No CA/EA)
Difference between defined and undefined prov sum?
For a prov sum to be considered defined it must have:
1. Nature and construction of work
2. Fixing
3. Quantity
4. Limitation
How is acceleration done in JCT?
- Contractor proposal: Additional resources / Revised date / Concessions
- Client assessment on VFM
- Agreement: Added to contract as addendum.
What are step in rights?
They grant the funder protection by allowing them to step into another parties shoes allowing them to sell the development on if the project is unachievable.
What is a notional final account?
A final account that is drafted when the GC is deemed insolvent.
It will be of greater value than the original forecast as allowances are required for the appointment of a new GC to finalize works.
When/where was the latest COP? Any key highlights?
Sharm El Sheikh, Egypt (COP 27)
- Loss & damage (of extreme weather) fund established.
- Reinforce 1.5c intentions
-
What should you do if a GC is deemed insolvent?
I would consult the RICS Termination Guidance Note.
- Secure site + offsite materials
- Check contract for termination clauses
- Call in any bonds
- Review collateral warranties & step in rights
- Ensure detailed records are kept
- Draft notional final account
- Revised shedule of works until termination
What are RICS professional statements? Name some?
They are MANDATORY practice for RICS members.
- Rules of conduct
- Conflicts of interest
- Bribery, corruption, money laundering, terrorism financing
- Handling data
What are the JCT guidelines on variations?
- All variations dealt with based on the scope of the variation
- Should be issued ASAP (No later than 2 wks after initially aware)
- 2 wks client review.
- Max 4 wks to agree terms.
What are the adv/disadv of a two-stage tender?
Advantages
Buildability advice
Competitive pricing
Accurate second stage cost
Reduced client risk - contractor manages from early
Disadvantages
Low-cost certainty stage one
Additional pre-con fees
Contractor can take advantage in 2nd stage and ramp up cost
Risk of retender
What might you request in a PQQ? What project details would you send?
Include :
- Contract particulars
- Any bonds/warranties/PCGs required
Request :
- Company turnover
- Experience
- Company accounts
- Org structure
- H&S records
- Quality systems
- Any bonds/warranties/PCGs required
What is a CDM advisor?
A resource employed in addition to a PD to manage both pre-con and/or construction phase CDM requirements.
Roles:
1. Assist PD to identify hazards/risks
2. Advise client of dutys
3. Advise GC on H&S plan
4. Review and advise generally on H&S
5. Site visits/inspections to review H&S
How can you effectively manage a conflict of interest?
- Staff exclusivity.
- Seperate communication lines.
- Seperate locations.
- Seperate data storage.
- NDA
- Regular review.
(All above considered an ‘ethical screen’)
What is a business plan?
A formal statement of a business’ goals containing clear reasons as to why they are attainable and a plan to reach them.
Provides a common focus and culture.
To draft you might use a SWOT
What is litigation?
A dispute resolution method.
Takes place in a public court hearing following civil procedure rules.
High cost.
Most effective for multi-party disputes.
What is arbitration?
Similar to litigation but PRIVATE.
Gives parties more control on how proceedings are handled.
Acceptance of both parties to arbitrate must be given.
Governed by the arbitration act (1996)
What is adjudication?
An independent third party hears claims of both parties resulting in a BINDING decision.
Statutory under HGCRA
Time sensitive - 28 days as default but can be extended to 42.
What is Tuckmans theory?
Team strategy and its evolving nature.
1. Forming
2. Storming
3. Norming
4. Performing
5. Adjourning
Fiber or rebar slab?
In summary, rebar is typically used when high tensile strength and stability are required, while fiber reinforcement is used to prevent shrinkage cracks and handle significant point loads. The choice between the two will depend on the specific needs of your construction project.
Generally fiber can be more cost effective over larger slabs due to the savings associated with labour and plant:
Less Labour Intensive: Fiber reinforced concrete requires less labour and less time spent on-site. This is because the fibers are mixed into the concrete, eliminating the need for the manual placement of rebar.
Reduced Equipment Costs: The use of fiber reinforced concrete can also lead to savings in equipment costs. There’s no need for tying rebar or wire mesh, which can reduce the need for certain equipment.
What are some types of external wall insulation?
Rockwool - Non combustible premium
Kingspan KS - Space saving
EPS - Most popular. Value for money. Lightweight.
XPS - Exstruded polystyrene.
What is permeable paving?
Pavement that allows water to flow through rather than runoff. Promotes drainage and filtration.
Reduces flooding
Improves water quality
Replenishes groundwater supplies
High maintenance costs
What are the HSE powers?
- Visit site without notice
- Issue written or verbal warnings to advise
- Sanctions (stop & improve orders)
- Inspect following complaint.
What is the Building Regs Part L?
Regulations on the conservation of fuel and power.
Gives info on limiting heat gains, air permeability, insulation regs, heating systems etc.
What is NRM1?
RICS published document in 2009
Gives standard set of measurement rules for estimating, cost planning, procurement, whole-life costing.
What is BREEAM?
Best practice standards for environmental performance of buildings.
Focuses on:
- Energy
- Land + ecology
- Water
- Wellbeing
- Pollution
- Material selection
What is a BOQ and when might you use one?
A BOQ is a bill of quantities and is created in accordance with NRM2. A BOQ is produced as a pricing document to be tendered against. If used the risk is retained by the client over the quantities within.
Once procured a BOQ can then be used to assist with variations/changes/valuations/final accounts.
What is NRM3?
Quantification and description of MAINTENANCE WORKS.
Similar to NRM1 (guidance on cost estimates, cost plans) but for use strictly on maintenance projects.
What might you include in an MFR?
- Pertinent commentary on months activity
- Contingency drawdown
- QRA update
- Early warnings
- Change orders
- Cashflow
- Prov sum drawdown
- Retention
- Remaining funding
- Any issues/concerns
What is RICS guidance on complaints handling processes?
Must be TWO stages minimum.
1st stage - Senior Staff review. 21 days to review and respond in writing.
2nd stage - Redress (RICS Dispute Service (ADR by approved provider) or Arbitration)
What are preliminaries?
They define the scope of works. Guidance can be found in NRM2.
Includes:
- Project particulars
- Drawing list
- Scope of works
- Site description
- Items to be priced (gen conditions (items req by contractor to complete works))
- Management arrangements
What is a negotiated tender?
A Negotiated Tender is a procurement method where the buyer approaches a single supplier, usually based on their industry track record or a previous relationship, to deliver the work. The buyer and supplier then negotiate the terms of the contract.
Usually an expensive strategy.
Can accelerate the programme.
Reduces contractor cost of tendering.
When might you use a Tender Price Forecast?
To rebase a cost plan to the midpoint of construction to accurately assess a PTE. Allows client to effectively budget and attain funding.
What is JIT?
Just in Time delivery method. (1970s Japan)
Delivered at exact moment for immediate use.
What is bid levelling?
A process usually carried out to ‘level’ any bids so that a like for like comparison can be made.
Catch errors/omissions
Reduce exclusions
How was COVID dealt with by JCT & NEC?
C19 was considered a force majeure at time of happening.
JCT = Relevant event.
NEC = Compensation event.
CLC launched Future Proofing Guide which gave amendments to contracts catering for COVIDs impact on work delivery.
Issue is when did COVID become FORESEEABLE RISK!
Difference between defined/undefined prov sum?
Undefined prov sums = deemed insufficient detail to effectively programme. This allows contractor to claim cost for prelims and EOT if works can be substantiated.
Defined = Sufficient detail to price prelim costing
Difference between cost plan / cost estimate?
Cost estimates basic in nature. Early stages of design (RIBA 0 to 2). Usually on a cost per functional unit (£/car park space) or cost per m2 (£/m2)
Cost Plan - RIBA Stage 2 onwards.
Elemental breakdown that becomes gradually more detailed as design progresses.
What are dayworks?
Prime (actual) cost of material, labor and plant plus agreed percentage allowance ontop as set out in contract.
Should be calculated in line with RICS guidance note - Definition of prime cost of daywork carried out under building contracts.
Nrm2 gives guidance
What does an interim valuation include?
- Prelims
- Measured work (as pricing doc)
- Variations
- Materials onsite/offsite
- Loss and expense (if applicable)
- Retention
What is a cashflow?
Summary of anticipated outgoing cash on a project over a time period.
How is an EOT judged in JCT?
To be eligible the delay must be caused by events beyond their control (Relevant Event/Relevant matter). Claims must include cause, period and mitigation steps taken.
What are the 9 JCT relevant events?
- Variations
- Weather
- Terrorism
- Failure of client
- Sub-con delays
- Statutory works
- Delay in possession
- Force majeure
- Strikes
What is the H&S At Work Act (HASWA) (1974)?
The primary H&S legislation in the UK.
- Provide safe place of work
- Provide safe equipment
- Ensure staff properly trained
- Carry out risk assessments
- Provide proper facilities
- Appoint competent H&S overseer
What are the 4 main types of asbestos?
- Chrysotile (White)
- Amosite (Brown)
- Crocidolite (Blue)
- Anthophyllite (Green/transparent)
What is a profit and loss sheet?
Shows income & expenditure of a company.
Snapshot of particular period of time.
What is a balance sheet?
Owns (assets) vs Owes (liabilities)
Snapshot of particular period of time.
What is the companies act (2006)?
Legislation that governs all public and private companies in the UK
Mandates financial accounts to be submitted yearly
- Profit and loss
- Cashflow
- Balance sheet
What is the NEC?
New Engineering Contract - Latest Edition 4
Generally for engineering projects - the PM does the CA work
Uses simpler english in comparison to JCT
Considered to be COLLABORATIVE
If a design team is novated, what are the implications?
You may have issues with design responsibility.
As part of innovation the client agrees design level is satisfactory and the contractor is then made responsible for the design.
Disputes then arise due to lack of clarity on WHEN the problems with the design arise. Prior to service transfer of after????
What are the two types of subcontractor under contract?
Domestic or Named
Domestic = Appointed by GC
Named = Client nominated
What are the two types of limitation period in Contracts?
Under hand = 6 years
Deed = 12 years
What is capping and grouting?
- Steel/concrete cap built top of shaft
- Shaft pumped with grout (cement, water, additives)
Name some other methods of measurement?
Highways method (Highways, roads, bridges)
CESSM4 (2012) (Civil Engineering Method of Measurement)
What was the tender process in the Microsoft scheme? Why were RLB not involved?
It was entirely handled inhouse.
- Allowed client ownership of contractors
- No risk of contractor collusion (400m contract!)
- Uninfluenced decision
Why do RLB not have sight of the DC contract?
- RLB not appointed on contractual issues
- Dedicated contracts team with MSFT
- Allows CT honed focus on cost
How would you conduct a valuation?
- Visit site in person to assess works complete
- Create markups of works complete showing progress from month to month
- Review all materials onsite/offsite
- Review preliminary costs (assess both fixed and time)
- Value any changes/claims against contract rates
GROSS - Prev. Payments - Retention = Valuation!
CA/EA issues pay cert.
What does a BOQ contain?
Lists and quants all materials, labour, and any other costs.
In accordance with NRM2.
RIBA Stage 4 typical.
What is a schedule of rates?
Lists the rates and prices for specific con. activities.
Typically produced by contractor - perhaps during first stage of tender.
What does a client brief contain?
F - Function - Purpose of building.
A - Aesthetics - Design requirements
C - Cost - Budget
T - Timeframe
S - Sustainability targets
What does an MFR contain? (8)
- Budget vs actual
- Cashflow
- Forecasting (estimate to completion)
- Change orders
- Prov sums
- Contingency drawdown
- Risk
- Schedule
What are the BREEAM scores?
Pass - 30 to 44%
Good - 45 to 54%
V Good - 55 - 69%
Excellent - 70 - 84%
Outstanding - 85 to 100%
If a complaint is unresolved by RLB what happens?
Negotiation
Mediation (with RICS)
Arbitration
At its core what is a conlfict of interest?
When personal or financial interests comprise integrity - can be at odds with professional obligations.
What is a PD?
S - Safety Management
A - Assistance
F - File management (H&S file up to date and available)
E - Emergency procedures (F10 HSE Notification with emergency instructions provided)
Decarbonising Steel - what is it?
Looking at reducing the carbon production of steel through the whole life cycle
In 2018 1 tonne steel = 1.85 tonne co2
- Blast furnace efficiency
- Biomass reductions
- Carbon capture + usage
- Electronic arc furnaces
Can you tell me a little about the RICS Interim Payments guidance note?
Advice on best practice in interim valuations/payments.
Details on good practice in the form of valuation method, payment criteria, administrative rules.
How do you effectively assess cost?
Advice on how to consider the WHOLE LIFE IMPACT of costs and the consequential impact of cost.
- Operating cost
- End of life cost
- Statutory compliance
- Programme impact
- Funding conditions
- Maintenance costs
Do NOT JEOPARIDSE other costs without proper holistic consideration.
What are the 3 Models in the Cost Reporting guidance note?
- Construction Cost Report
Costs under a specific contract/project - Project Cost Report
Developer specific report on multiple sites/whole project - Programme Cost Report
Programme management specifics
What clause is key for subcontractors under HGCRA?
The pay when paid clause.
Disallows people paying only when they have been paid.
Takes strain off subcontractors.
Under JCT what grants an EOT?
Relevant event = Time only
Relevant matter = Time and L&E
When might you use minor works?
Sub 200k value
Simple in nature works
Design complete
Short duration
What is CDP?
Contractors design portion
Contractor responsible for design of specific elements/components.
CDP elements clearly captured within contract documents with clear delineation of responsibilities.
How might you advise a client on how to select a JCT contract?
Utilise the JCT Deciding tendering strategy guidance note (2016)
As a CA how do you effectively manage a contract?
Ensure parties aware of payment/valuation dates
Transparent communications facilitated between all parties
Good payment practice
Detailed considered review of change/variations ensuring fair outcome
Clear record keeping - auditable
What must be in place for liquidated damages to be billed?
1- Non-Comp cert
2- Withholding notice
Substantiation of fair and genuine pre estimate from client.
What are liquidated damages?
A fair and genuine pre-estimate of likely loss incurred by completion date not being met.
As QS we cannot advise - they must be set by client.
Two types of liability?
Liability
Loss
When does a CA role begin?
When contract is executed
What are some CA qualities?
- Knowledge and skill to understand contract
- Independent, impartial
- Indepth construction knowledge
- Clear record keeping
- Routine awareness of critical path and programme
What is a Section 73?
A condition attached to a planning application.
E.g. Additional approvals for colour of materials etc.
What does the RICS Cost Reporting guidance note cover?
Purpose of cost reports
Factors affecting costs
Cost report models
Format of cost reports
Treatment of variable costs
What does RLB do for equality?
Great maternity leave policy
Bring yourself to work
D&I steering group
General advantages of using JCT?
Industry standard so lots of familiarity in industry
Established case law
Covers majority of different procurement types
Beneficial to client for risk transfer
General disadvantages of using JCT?
Compromises conditions to satisfy parties
Very long
Uses legal ‘speak’ so difficult to understand
What is the purpose of a first stage in a two stage tender?
Gain buildability advice
Fixing of prelims/OHP/schedule of rates
Speeds up procurement by overlapping design and tender
Whitewall or blockwork?
If you need a cost-effective, load-bearing solution and aesthetics are not a primary concern, blockwork walls may be more appropriate.
If you require a clean and hygienic environment, with a modern appearance and ease of maintenance, whitewalls may be preferred. Also, it is quicker to install and grants savings on prelims with limited requirement for scaffolding.
In some cases, a combination of both materials might be used, such as using blockwork for structural elements and whitewalls for areas requiring a clean, bright finish.
.
.
How do photovoltaic windows work?
A thin film of solar cells is applied to the window. Additional layers can be appled but the window will darken.
How does PV work?
Photovoltaic Cells: Solar slate is made up of small photovoltaic (PV) cells, which are the key components that capture sunlight and convert it into electricity. These PV cells are typically made from materials like silicon.
Sunlight Absorption: When sunlight hits the solar slate, the PV cells absorb the energy from the sun’s rays. This energy excites electrons within the cells.
Electricity Generation: As the electrons become energized, they create an electrical current. This current is in the form of direct current (DC) electricity.
Inverter: The DC electricity generated by the solar slate is then sent to an inverter, which converts it into alternating current (AC) electricity. Most household appliances and the electrical grid use AC electricity.
What is run off cover?
Must be in place for ALL previous employees for min. 6 years.
Precedent set by Merritt vs Babb Case Law (2001)
What insurances do you need to start a firm?
- Professional indemnity
- Employers liability
- Public liability
- Building Insurance
What are the RICS PII reqs?
Each and every claim basis
Run off cover min 6 years
Why did the RICS create new rules of conduct?
To give greater clarity to the rules. Simplifies the structure and makes it easier to follow for members.
Increased focus on:
1. Data handling
2. Sustainability
3. D&I
RICS five principles of regulation?
P ropotionality
A ccountability
C onsistency
T argeted
T ransparency
What are the 5 different RICS Membership levels?
Student
AssocRICS
Honorary
Member (MRICS)
Fellow (FRICS)
Difference between Ethics & Rules?
Ethics are a set of moral values.
Rules are a framework we work to.
What are the 5 rules of conduct?
- Be honest, act with integrity and comply with their professional obligations to the RICS.
- Maintain professional competence and ensure services carried out by competent individuals with necessary expertise.
- Provide good quality & diligent service.
- Treat others with respect and encourage D&I.
- Act in public interest, take responsibility for actions and act to prevent harm and maintain public confidence in the profession.
Tell me a little about the RICS Code of Measuring Practice?
Currently in 6th edition released May 2015
Provides direction on how to calculate areas & volumes promoting consistency.
GEA / NIA / GIA
Different types of foundations?
PAD - Bases of reinforced concrete for steel columns. Spreads load to layer below.
STRIP - Continuous perimeter (suitable for light only)
RAFT - Large raft base spreads load evenly to reduce load per m2 (low bearing capacity soils)
Should you ever use an LOI?
If avoidable no you should not.
Case law shows dangers: Ampleforth Abbey Trust v Turner & Townsend Project Management [2012]
The employer successfully sued the project manager for failure to advise on the risks posed by starting the works on the back of a letter of intent, having been unable to claim liquidated damages because no formal contract had been entered into.
ALWAYS outline risks to clients.
How should you approach an LOI?
Contracts bring with them certainty and the ability to manage risk, whereas letters of intent do not.
Before deciding to agree a letter of intent, both parties should stop to ask themselves why they cannot yet enter into a full contract. If the answer is that there are still difficult points of negotiation to be agreed between the parties, then a letter of intent is unlikely to make these issues go away.
Why should contractors and clients not enter into LOI?
From an employer’s perspective, a letter arguably places them in a weaker bargaining position as the contractor is on site and works are under way.
From a contractor’s perspective, meanwhile, there is always a risk that the employer will decide to use someone else – and it is likely to be able to do so if, for example, the letter of intent provides for an express expiry date or a cap on the amount that can be incurred under the contract in question.
Difference between Project Life Cycle & Whole Life Cycle?
Project: Inception -> Completion (specific to construction)
Whole: The above PLUS costs with operating, maintaining, demolishing.
What impact does CDP have on clauses in JCT?
Intermediate - separate CDP agreement.
Minor works - separate contract altogether.
Requirements in others generally are set out in ER’s and are incorporated to main contract.
What is a business statement?
A formal statement of a business’ goals with reasons why they are attainable and the plan to reach them.
Provides a common ground for culture and focus.
What is RLBs business statement?
To be a global leader in the market, through flawless execution, fresh perspective, and independent advice. Create value through skills and passion of RLBs people.
What is retention?
Usually 3 (Other) or 5% (D&B)
Released in 2 stages:
1. PC
2. End of Defects
Retention is a percentage of payment held back typically by a client or main contractor under a construction contract to act as security, or an assurance that the project works will be completed and that defects which may subsequently develop are remedied.
What are the 5 types of certificate on JCT?
- Interim
- PC/Sectional
- Non completion/pay less
- Making good
- Final
What are the 5 stages of project life cycle?
- Initiation
- Planning
- Execution
- Performance + Monitoring
- Closure
What is Part M?
Building regulation on access and use of buildings.
Guidance on facilities for disabled, and the ability for them to move through a building, access to toilets & bathrooms etc.
Ramps, steps, safe degrees of pitch.
Who is RICS President?
Ann Grey
Who is CEO?
Justin Young
Who is President Elect?
Tina Pallet
What happened to Dame Janet Paraskeva?
Dame Janet Paraskeva’s resignation letter to RICS President Ann Gray:
Resignation as Chair of the Standards and Regulation Board due to disagreement over removal.
Denies allegations and believes RICS is trying to terminate her.
Emphasizes commitment to SRB’s independence and offers transition support.
Reserves the right to respond to public comments and provide further details.
What are the 4 main types of FIDIC contract?
Red - Tradoitional
Yellow - Contractor Design
Silver - D&B
Green - Minor work
How does solar PV work?
Converts sunlight to electricity.
Panels capture sunlight.
Inverter converts DC to AC.
Name me 5 items from Black Book?
- Cashflow
- Value management & Engineering
3.Cost Reporting - Commercial management
- Tendering Strategies
How is the RICS structured?
Privy Council
Gov. Council
Standards & Regs Board - Management Board - Audit Comittee
What is the primary H&S legislation in the UK?
H&S at work act 1974
- Gives duty to all employers to provide safe equipment, workplace
- Control of dangerous substances
- 5+ employees = detailed H&S plan/documentation
What is a CPP?
Construction Phase Plan
Contains:
Project description
Management processes of works (inductions, rules, PPE, emergency)
Significant risks (asbestos, working at height, noise pollution, manual handling etc)
Difference between profit and loss & balance sheet?
Profit & Loss (P&L) Statement:
Purpose: Shows if a company made money (profit) or lost money (loss) during a set period.
Timeframe: Covers a specific period, like a movie of financial performance.
Components: Includes income, expenses, and profit (or loss).
Think of it as: A movie showing if a company made money or lost money over time.
Balance Sheet:
Purpose: Reveals what a company owns (assets), owes (liabilities), and its net worth.
Timeframe: Reflects the financial snapshot at a particular date, like a photograph.
Components: Includes assets, liabilities, and shareholders’ equity.
Think of it as: A photograph of what a company owns, owes, and what’s left for the owners at a specific moment.
What is the Companies Act (2006)?
All firms must produce statements for:
1. Turnover
2. Gross profit
3. Net profit
What is GDPR?
General Data Protection Regulation
Governs all EU ensuring data is used fairly, lawfully and transparently.
Difference between Mediation & Conciliation?
Conciliation more active role in discussions. Mediation only facilitates comms.
Under NRM1 how do you measure ext. walls?
Internal perimeter x Height of building. Minus m2 of windows.
Under NRM2 how do you measure ext. walls?
‘Cladding and covering’
Measured m2 on elevations
If less than 1m2 area = Number
Less 600mm wide = Meters
Splits for: Walls, floors, ceilings, roofs, column sides, soffit
Advantages of a fiber slab?
Decrease in surface cracking
Reduced shrinkage
No movement joint req
10-15% more costly than non-reinforced concrete
Name some building regs?
A - Structure
B - Fire Safety
L - Conservation of fuel and power
M - Access
O - Overheating
D - Toxic Substances
What is the ISMSC?
The International Measurement Standards Coalition
Set international standards for:
1. Benchmarking
2. Measuring
3. Reporting of costs