the digging and removal of earth from its natural position
excavation
ecavation characterized as having independent and hollow block wall footing
minor excavation
an excavation which requires wide or total extraction of the soil
major excavation
the process of providing temporary supports to the structure or ground during excavation
shoring
the process of rebuilding, strengthening or stabilising the foundation of an existing building
underpinning
these consist of steel cables or tendons that are inserted into holes pre-drilled through the sheet piling and into the rock or a suitable stratum of soil, grouted under pressure to anchor them to the rock soil, and post-tensioned with a hydraulic jack
tieback
part of the foundation system which provides support for the superstructure above to resist active earth pressure and anchor the superstructure against wind and seismic forces
foundation wall
serves as a sheeting and often used as a permanent foundation wall
slurry wall
a method of foundation system protection applied to a foundation wall when a subsoil conditions indicate that hydrostatic pressure will not occur
dampproffing
a system of temporary boarding, sheathing or pans used to produce the desired shape and size of concrete mass
formworks
boarding or sheeting of wood, metal, plastic, fiber glass for containing and giving a desired shape
form
a system of temporary platform to support workers and materials on the face of a structure and to provide access to work areas above ground
scaffoldings
temporary bracing for supporting work under construction which cannot yet support itself
falsework
a temporary platform for workers and the materials that the use in building structures
staging
a piece of timber to support a wall, usually set in a diagonal or oblique position to hold the wall in place temporarily
shore