EVM Formulae Flashcards

1
Q

Budget at completion (BAC)

A

Original budget of the project
Formula:
-
(purna budget)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Planned Value (PV)

A

Amount of money worth of work that should have been done on the project.
Formula:
PV = Planned % of completion X BAC
(Atta paryant kiti takke kaam vhayla pahije hota X Purna budget)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value (EV)

A

Amount of money worth of work you actually did on the project.
Formula:
EV = Actual % of completion X BAC
(Atta paryant kiti takke kaam jhalay X Purna budget)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Actual Cost (AC)

A

Amount of money you already spent on the project
Formula:
-
(Atta paryant kiti paise kharcha jhale)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance (CV)

A

The difference between the work done and money spent.
Formula:
CV = EV - AC
(+ve CV mhanje under budget… -ve CV mhanje over budget)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Performance Index (CPI)

A

The rate of how we are spending to actually earning on the project.
Formula:
CPI = EV / AC
(index > 1 mhanje under budget, index < 1 mhanje over budget)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Variance (SV)

A

The difference between the amount of work we should have done vs. the amount actually done.
Formula:
SV = EV - PV
(+ve SV mhanje ahead of schedule, -ve mhanje behind schedule )

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule performance Index (SPI)

A

The rate of how we are meeting the project schedule.
Formula:
SPI = EV / PV
(Index > 1 mhanje ahead of schedule, index < 1 mhanje behind schedule)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at completion (EAC)

A

Forecasting the total cost of the project at the end based on the current spending rate of the project.
Formula:
EAC = BAC / CPI
(hyach rate ni kaam chalau rahila (CPI) tar end la kiti paise lagtil)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate to complete (ETC)

A

Forecasting the amount that will be needed to complete the current project based on the current performance
Formula:
ETC = EAC - AC
(hyach rate ni kaam chalu rahila tar ‘AJUN’ kiti paise lagtil)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Variance at completion (VAC)

A

The difference between the original budget and new forecasted budget
Formula:
VAC = BAC - EAC
(total budget madhe farak kiti padla)
(+ve is good, mhanje plan kele jast paise pan vaparnar kami aahe)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-Complete performance index

A

The performance that needs to be met to finish the project within the budget.
Formula:
TCPI = (BAC - EV) / (BAC - AC)

(same initial budget madhe kaam sampvaycha asel tar aata kiti speed ni kaam kela pahije.. HE 1 PEKSHA KAMI ASLA PAHIJE.. ONLY INDEX / RATIO WHICH SHOULD BE BELOW 1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EXAM Tip

A

In CV, CPI, SV, SPI 1st term is always EV
if its Variance –> its difference i.e. subtraction
if its index –> its the ratio i.e. division

if its about ‘cost’ —> use actual value (AC)
if its about ‘schedule’ —> use planned value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly