EVM Formulae Flashcards
Budget at completion (BAC)
Original budget of the project
Formula:
-
(purna budget)
Planned Value (PV)
Amount of money worth of work that should have been done on the project.
Formula:
PV = Planned % of completion X BAC
(Atta paryant kiti takke kaam vhayla pahije hota X Purna budget)
Earned Value (EV)
Amount of money worth of work you actually did on the project.
Formula:
EV = Actual % of completion X BAC
(Atta paryant kiti takke kaam jhalay X Purna budget)
Actual Cost (AC)
Amount of money you already spent on the project
Formula:
-
(Atta paryant kiti paise kharcha jhale)
Cost Variance (CV)
The difference between the work done and money spent.
Formula:
CV = EV - AC
(+ve CV mhanje under budget… -ve CV mhanje over budget)
Cost Performance Index (CPI)
The rate of how we are spending to actually earning on the project.
Formula:
CPI = EV / AC
(index > 1 mhanje under budget, index < 1 mhanje over budget)
Schedule Variance (SV)
The difference between the amount of work we should have done vs. the amount actually done.
Formula:
SV = EV - PV
(+ve SV mhanje ahead of schedule, -ve mhanje behind schedule )
Schedule performance Index (SPI)
The rate of how we are meeting the project schedule.
Formula:
SPI = EV / PV
(Index > 1 mhanje ahead of schedule, index < 1 mhanje behind schedule)
Estimate at completion (EAC)
Forecasting the total cost of the project at the end based on the current spending rate of the project.
Formula:
EAC = BAC / CPI
(hyach rate ni kaam chalau rahila (CPI) tar end la kiti paise lagtil)
Estimate to complete (ETC)
Forecasting the amount that will be needed to complete the current project based on the current performance
Formula:
ETC = EAC - AC
(hyach rate ni kaam chalu rahila tar ‘AJUN’ kiti paise lagtil)
Variance at completion (VAC)
The difference between the original budget and new forecasted budget
Formula:
VAC = BAC - EAC
(total budget madhe farak kiti padla)
(+ve is good, mhanje plan kele jast paise pan vaparnar kami aahe)
To-Complete performance index
The performance that needs to be met to finish the project within the budget.
Formula:
TCPI = (BAC - EV) / (BAC - AC)
(same initial budget madhe kaam sampvaycha asel tar aata kiti speed ni kaam kela pahije.. HE 1 PEKSHA KAMI ASLA PAHIJE.. ONLY INDEX / RATIO WHICH SHOULD BE BELOW 1)
EXAM Tip
In CV, CPI, SV, SPI 1st term is always EV
if its Variance –> its difference i.e. subtraction
if its index –> its the ratio i.e. division
if its about ‘cost’ —> use actual value (AC)
if its about ‘schedule’ —> use planned value (PV)