Evacuation Sector MP 201.05E Flashcards

1
Q

What is the key to an organized evacuation?

A

Develop an ICS early, initiate/update a plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 3 levels of evacuation?

A

Site Evac: small # of people, evac of less than an hour or two
Intermediate evac: larger area, less than 100 people, coordinate with PD
Large Scale evac: out of homes for many hours or days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who is responsible for developing an evacuation plan?

A

Planning Sector, along with PD.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who should be evacuated?

A

Residents living/working in the area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What happens when a resident refuses to leave?

A

Inform of risk. If they still won’t leave, notify Evacuation Branch with the citizens address for follow-up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

For On-Site Notification to Evacuate (notifying a large residential street or area), what is best method?

A

Use of Sirens, PA system, and air horns will speed alert process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Where immediate evac makes door to door impossible, what can be done?

A
  • use (3) 5 second siren blasts on yelp setting

- start siren blasts at start of each block, every 50 yards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly