Estimating cost Flashcards
Name 3 types of top down cost estimates
Analogy, expert opinion and parametric.
Name one bottom down cost estimate
Cost engineering
-Detailed breakdown of labour or materials at the work package or task level.
Name 7 sources of cost overruns.
- Uncertainty and lack of information
- Changes in requirements or design
- Economic/Social Factors
- Inefficiency, Poor communication and lack of control
- Ego of the estimator
- Project contract
- Bias and ambition
Whats are life cycle costs?
All costs of a system incurred during each phase of the project life cycle from the conception phase to the operations phase
What is an estimate?
A realistic assessment based upon facts about the work, required resources, constraints and the
environment, derived from estimating methods.
What is the difference between accuracy and precision.
Accuracy is the closeness of the estimated value to the actual value.
Precision is how many decimal places are used in the estimate.
Name 4 types of costs
Direct costs
Direct Overhead Costs
General & Admin overhead costs
Profits