When water or wind detaches soil and rock particles from the land surface, it is called
Erosion
The process that occurs when flowing water slows down enough to allow suspended soil particles to settle is called
Sedimentation
What year did NC legislation establish a statewide program to control soil erosion and sedimentation?
1973
An erosion and sedimentation control plan must be submitted at least ____ before land disturbance begins
30 days
During construction, the person who is responsible for maintaining the erosion and sedimentation control devices and practices is the _____
Site developer and/or land owner
What does DENHR stand for
Department of Environment, Health, and Natural Resources
Graded slopes must be planted with vegetation or or otherwise stabilized within how many working days?
30 working days
Some erosion is unavoidable and the resulting erosion must be
Trapped on site
When possible, you should schedule construction projects that cause soil disturbance during which seasons?
Summer, Fall
When planning a project consider the maintenance and repair costs of each erosion control practice ______ construction.
Before
Erosion and sediment control structures should be _______ and ______.
Inspected and maintained