EO 1 Block 1 Flashcards
Which ONE of the following combinations describes the TWO purposes of the 345 KV distribution system?
- Provide a normal power source for the Circulating Water Pumps and the
Reactor Coolant Pump’s at 100 % power. - Distribute power generated at the station for commercial use.
- Provide an emergency source of power to essential 4160 VAC buses.
- Provide a source of alternate power to station loads at 100 % power.
A. 1, 3
B. 1, 4
C. 2, 3
D. 2, 4
D
ONE purpose of the 345 KV Distribution System is to provide input to the grid for financial income for First Energy.
Which ONE of the following is another purpose of the system at 100 % power?
A. Provide a source of EMERGENCY power to station DC loads.
B. Provide a source of EMERGENCY power to emergency lighting panels.
C. Provide a source of ALTERNATE power to station AC loads.
D. Provide a source of ALTERNATE power to the security diesel.
C
Which ONE of the following combinations describes TWO purposes of the 345 KV distribution system?
- Distribute power generated at the station for commercial use.
- Provide an emergency source of power to essential 4160 VAC buses.
- Provide offsite power via the startup transformers to the 13.8 KV buses during startup and shutdown.
- Provide the normal power source for the Circulating Water Pumps and the Reactor Coolant Pumps at 100% power.
A. 1 and 2
B. 1 and 3
C. 1 and 4
D. 2 and 3
B
Which one of the following substations tie directly to Davis-Besse’s 345 kV System switchyard?
A. Acme
B. Beaver Valley
C. Lindsey
D. Ohio Edison
D
The Plant is being Shut Down per DB-OP-06902 Power Operations.
Current Reactor Power is 28% and stable at Low Level Limits.
The following breakers open:
ACB 34560
ACB 34564
What is the source of power to Startup Transformer 01?
A. Lemoyne Line
B. Bayshore Line
C. Main Generator
D. Ohio Edison Line
A
During refueling outages, the Main Generator output breakers (ACB 34560 & 34561) are normally _____ and the Main Generator air break
switch (ABS 34620) is normally _______ .
A. open to prevent powering the Main Generator; open to prevent powering the Main Generator
B. closed to allow ring bus continuity; open to prevent powering the Main Generator
C. open to prevent powering the Main Generator; closed to allow Main Generator relaying to function
D. closed to allow ring bus continuity; closed to allow Main Generator relaying to function
B
During EXTENDED shutdown operations with the main generator shutdown, which ONE of the following represents the condition of the generator output breakers, ACB 34560 and ACB 34561?
A. OPEN to prevent motoring the generator.
B. OPEN to ensure ring bus continuity.
C. CLOSED to ensure protective relay availability.
D. CLOSED to ensure ring bus continuity.
D
During extended SHUTDOWN operations with the main generator shutdown, ACBs’ 34560 and 34561 are normally __________, ABS 34620 is normally __________, and Ground Switch 34645 is normally __________.
A. OPEN; OPEN; CLOSED
B. OPEN; CLOSED; OPEN
C. CLOSED; OPEN; CLOSED
D. CLOSED; CLOSED; CLOSED
C
During normal 100 % power operations, ACB’s 34560 and 34561 are normally __________, ABS 34620 is normally __________, Ground Switch 34645 is normally __________.
A. CLOSED; CLOSED; CLOSED
B. CLOSED; OPEN; OPEN
C. OPEN; CLOSED; CLOSED
D. CLOSED; CLOSED; OPEN
D
Which of the following combinations are all substations with DIRECT tie-in to Davis-Besse’s 345 KV switchyard?
- Oak Harbor Feeder
- Bayshore
- Eastlake
- Lemoyne
- Ohio Edison-Beaver Substation
A. 1, 2, 4
B. 1, 3, 4
C. 2, 4, 5
D. 3, 4, 5
C
What action would be required if the only source of power after a reactor/turbine trip caused by inclement weather is by backfeeding through the Main Transformer?
A. Disconnects at the Isophase system would have to be removed locally to prevent motoring the main generator when ACB34561 and ACB34560 are closed.
B. Ground switch 34645 must be close to prevent shock danger to plant personnel prior to closing ACB 34560 and ACB 34561
C. Main Generator must be taken off the turning gear and the rotor must be locked in order to prevent shaft from rotating when breakers ACB34560 and ACB34560 are closed.
D. Contact the dispatcher to have the Isophase disconnects open remotely prior to closing ACB34560 and ACB34561.
A
Generator output breakers ACB 34560 and 34561 can be OPENED and can be CLOSED .
A. by the Load Dispatcher and, from the Control Room by the Load Dispatcher and from the Control Room
B. by the Load Dispatcher and, from the Control Room from the Control Room ONLY
C. from the Control Room ONLY by the Load Dispatcher and, from the Control Room
D. from the Control Room ONLY, from the Control Room ONLY
B
Which ONE of the following identifies the purpose of SF6
gas in an Air Circuit Breaker?
A. Provides a backup supply to the operating air system.
B. Provides moisture absorption to keep operating air system dry.
C. Quenches the arc during OPENING and CLOSING operations.
D. Provides insulation at the phase interrupter and phase current transformers.
D
Which ONE of the following indicates the location from which ALL air break switches and motor operated disconnects can be OPENED AND CLOSED?
A. Control Room
B. Relay House
C. System Dispatchers Office
D. Switchyard, at the components
D
When CLOSING a 345 KV Air Circuit Breaker from the Control Room.
The synchroscope should be at the 12 o’clock position, rotating __________ and the synchronizing lamps should be ___________.
A. SLOW in the FAST direction; OFF
B. SLOW in the SLOW direction; ON
C. SLOW in the SLOW direction; OFF
D. SLOW in the FAST direction; ON
A
Which ONE of the following describes the purpose of a RECLOSER switch in the relay house?
A. Allows for AUTOMATIC reclosure of an ACB.
B. Used to relay TRIP signals between breakers.
C. Prevents RECLOSURE of designated breakers during fault conditions.
D. Used to RECLOSE motor-operated disconnects in the event of a fault.
A
When in the AUTO position, the RECLOSER switch in the relay house allows for AUTOMATIC reclosure of an ACB ____________________ following ____________________.
A. IMMEDIATELY, a TEMPORARY line fault.
B. after a set time delay, only a DIFFERENTIAL fault.
C. IMMEDIATELY, a PERMANENT line fault.
D. after a set time delay, ANY line fault.
D
The Relay House switches that permit AUTOMATIC TRIP signals to be received from the Remote Line Relays or to be transmitted to the Remote Line Relays if required to TRIP the breaker are ___________ switches.
A. reclosure
B. carrier
C. transfer trip
D. control
C
The Relay House switches that permit LINE-FAULT-TRIP blocking signals to be transmitted or received via coupling capacitor potential devices are __________ switches.
A. reclosure
B. carrier
C. transfer-trip
D. syncroscope
B
Which ONE of the following conditions will result in annunciator 1-1-E, SU XFMR 01 LOCKOUT?
A. LOSS of DC annunciator power to Startup Transformer 01 cabinet.
B. LOW oil flow in the #1 oil cooler group for Startup Transformer 01.
C. Sudden pressure RISE inside Startup Transformer 01.
D. LOW Nitrogen pressure in Startup Transformer 01 Inertaire cylinder.
C
Determine which ONE of the following control room annunciators will alarm if power is lost to MCC E22A.
A. SU XFMR 01 TRBL
B. SU XFMR 02 TRBL
C. XFMR CE1-2 TRBL
D. BUS E1 TRBL
B
The following plant conditions exist:
* Reactor power is 70 % power
* Annunciator 1-1-F, AUX XFMER 11 LOCKOUT just alarmed coincident with numerous others.
* An EO reports that a fork lift has tipped over and its load has slammed into Auxiliary Transformer 11.
The expected plant response is for ACB 34560 & 34561 to be <>
and for the 13.8 Kv buses to be powered from <> .
A. open; Aux. 11 Xfmer with a load rejection in progress.
B. closed; the Startup Xfmers with the plant stabilizing at 70 % power.
C. closed; Aux. 11 Xfmer with a reactor/turbine trip present
D. open; Startup Xfmers with a reactor/turbine trip present
B
The following plant conditions exist:
- 100% Normal Power Operation
- A Bus Reserve Source Selector Switch is in the 01 position.
- A Lockout has occurred on the “J” Bus.
- The plant has tripped due to Main Transformer Fault.
Which ONE of the following describes the status of “A” Bus?
A. “A” Bus is De-energized.
B. “A” Bus is powered from the 01 Transformer.
C. “A” Bus is powered from the 02 Transformer.
D. “A” Bus is powered from the Aux 11 Transformer.
A
The following plant conditions exist:
- Plant at 100% power
- Normal 100% electrical lineup
A lockout on the J Bus occurs.
Which ONE of the following describes the status of A Bus?
A. A Bus is de-energized.
B. A Bus is powered from 02 Startup Transformer.
C. A Bus is powered form 01 Startup Transformer.
D. A Bus is powered from the Auxiliary 11 transformer.
D
The following plant conditions exist:
· Reactor power is 100%.
· The station electrical line-up is normal for 100% power.
If 345 kV ACB 34560 develops a ground fault, but fails to open, which ONE of the following correctly describes the AUTOMATIC response of the 13.8 kV distribution system?
A. · 13.8 kV bus A is deenergized
· All 13.8 kV bus A Load Breakers are TRIPPED OPEN
· 13.8 kV bus B transfers its power supply to Startup Transformer X02
B. · 13.8 kV bus B is deenergized
· All 13.8 kV bus B Load Breakers are TRIPPED OPEN
· 13.8 kV bus A transfers its power supply to Startup Transformer X01
C. · 13.8 kV bus A is deenergized
· The associated RCP and circ. water pump breakers are TRIPPED OPEN
· 13.8 kV bus B transfers its power supply to Startup Transformer X02
D. · 13.8 kV bus B is deenergized
· The associated RCP and circ. water pump breakers are TRIPPED OPEN
· 13.8 kV bus A transfers its power supply to Startup Transformer X01
C
Which ONE of the following will cause a LOCKOUT of startup transformer 02?
A. LOW oil level
B. HIGH winding temperature
C. A differential relay operation cause by a fault
D. Loss of 480V AC power to the cooling fans and pumps
C
Which ONE of the following is the purpose of the Kirk Key interlock between the generator field breaker and the generator output ground switch (34645)?
A. Ensures ONLY qualified personnel operate the equipment.
B. Prevents UNAUTHORIZED personnel from operating the devices.
C. Prevents operation of EITHER component without the Shift Manager’s permission.
D. Prevents SIMULTANEOUS operation which would result in shorting the generator output to ground.
D
The plant is operating at 100% power when annunciator 1-1-F, AUX XFMR 11 LOCKOUT, alarms. Which ONE of the following represents the effects on plant equipment?
A. * ACB 34560 and 34561 OPEN
* The turbine and main generator TRIP
* A and B busses fast dead transfer to startup transformers
B. * ACB 34560 and 34563 OPEN
* The main generator stays on line
* A and B busses fast dead transfer to startup transformers
C. * The ring bus remains intact (ACB 34560 and ACB 34561 remain closed)
* ABS 34620 (generator output) OPENS
* A and B busses deenergize.
D. * ACB 34561 and 34564 OPEN
* ABS 34620 (generator output) OPENS
* A and B busses deenergize
A
If Air Circuit Breaker (ACB) 34560 received a TRIP signal but FAILED to OPEN, which ONE of the following sets of breakers would OPEN?
A. ABS 34620 and ACB 34561
B. ACB 34561 and ACB 34563
C. ACB 34562 and ACB 34564
D. ACB 34563 and ACB 34562
B
If ACB 34560 received a trip signal but failed to open, which ONE of the following sets of devices would open?
A. ACB 34562 and ACB 34564
B. ACB 34563 and ACB 34562
C. ABS 34620 and ACB 34561
D. ACB 34561 and ACB 34563
D
If ACB 34560 received a trip signal but failed to open, which ONE of the following sets of breakers would open?
A. ACB 34561 and ACB 34564
B. ACB 34562 and ACB 34563
C. ACB 34562 and ACB 34564
D. ACB 34561 and ACB 34563
D
If ACB 34560, GENERATOR OUTPUT BREAKER, received a trip signal but failed to open, which one of the following sets of breakers would open?
A. ACB 34561 and ACB 34564
B. ACB 34562 and ACB 34563
C. ACB 34562 and ACB 34564
D. ACB 34561 and ACB 34563
D
The plant is operating at 100% power. Due to improper maintenance on 345 kV switchyard breaker 34561, the “B” phase operating mechanism linkage on this breaker broke after the last breaker closure (closure successful), and will NOT respond to further electrical control signals. If the LOW air pressure system on this breaker develops a leak in excess of compressor makeup capacity, which ONE of the following describes the AUTOMATIC response of the plant?
A. Main generator TRIP, ACB 34560 TRIPS open, Bayshore line TRIP (TT), ACB 34562 TRIPS open, A & B Bus fast dead transfer to selected startup transformers.
B. NO AUTOMATIC actions occur, but an alarm annunciates in the CTRM.
C. ACB 34561 TRIPS open, along with its associated disconnect switches.
D. Main generator TRIP, ACB 34560 TRIPS open, LOCKOUT of SU XFMR 02, A bus fast dead transfers to SU XFMR 01, B bus is de-energized.
A
The following plant conditions exist:
* The plant is operating at 100% power.
* All systems are in a normal lineup.
The following conditions occur:
* ACB 34562 tripped
* ACB 34564 tripped
* HX02A tripped
* HX02B tripped
A fault has occurred on __________.
A. J Bus
B. Main Transformer
C. Lemoyne Transmission Line
D. Ohio Edison Transmission Line
D
The following plant conditions exist:
* 100% Power
* All systems are in a normal lineup
* B Bus Reserve Source Selector Switch is in the “X02” position
Due to a fire, a lockout occurs on the 02 Startup Transformer
Which ONE of the following describes the status of B Bus?
B Bus will <>.
A. be de-energized
B. transfer to the 01 Startup Transformer
C. transfer to the 02 Startup Transformer
D. remain powered from the Aux 11 Transformer
D
Which ONE of the following identifies the correct location where the temperature in the switchyard is read for the switchyard rounds?
A. At the base of ACB 34564.
B. At the base of ABS 34620.
C. At the base of DCS 34560A.
D. At the south wall of the relay house.
A
With the plant in Mode 1, which ONE (1) of the following conditions would NOT require entry into TS LCO 3.8.1, AC Sources-Operating?
A. DG 1 is declared INOPERABLE
B. Startup Transformer 01 locks out
C. Ring Bus Feeder from Lemoyne line is lost
D. 4KV Bus C locks out
C
Match the conditions in the left column with the appropriate setpoint in the right column which will cause Annunciator 1-3-E, SU XFMR 01 TRBL, to alarm in the
Conrol Room.
____ 1. Hi Oil Temperature
____ 2. Hi Winding Temperature
____ 3. Pressure Relief Device
____ 4. Nitrogen Pressure Hi/Lo
A. 8.5 psig/-3 psig
B. 165°C
C. 117°C
D. 5.5 psig/-2 psig
E. 90°C
F. 8 psig
- E.
- C.
- F.
- A.
The Main Transformer primary cooling group AUTOMATICALLY starts when__________ and AUTOMATICALLY stops when __________.
A. the exciter breaker CLOSES; the exciter breaker OPENS
B. the generator field breaker CLOSES; the generator field breaker OPENS
C. the FIRST generator output breaker CLOSES; the SECOND generator output breaker OPENS
D. the SECOND generator output breaker CLOSES; the SECOND generator output breaker OPENS
B
Which ONE of the following statements describes an interlock between the Main Generator Field Breaker and the Main Transformer Cooling Groups?
A. Secondary Group must be MANUALLY stopped if it started on high winding temperature
B. Primary Group oil pumps AUTO START sequentially when the Generator Field Breaker is CLOSED
C. Secondary Group must be MANUALLY stopped if it started on high top oil temperature
D. Primary Group oil pumps AUTO START simultaneously when the Generator Field Breaker is CLOSED
B
Which one of the following describes what occurs on a loss of NORMAL power to Aux 11 transformer auxiliaries?
A. Aux 11 LOCKS OUT/TRIPS.
B. Auxiliaries AUTO transfer to ALTERNATE supply of power.
C. The transformer REMAINS as is.
D. Actuation of a 13.8 KV bus fast dead transfer.
B
Annunciator 16-3-C, MN XFMR 1 DNGR, will alarm in the Control Room if oil temperature INCREASES to _____°C or winding temperature INCREASES to _____°C.
A. 180, 90
B. 180, 135
C. 90, 180
D. 90, 135
D
Which of the following identifies the Auxiliary 11 Transformer Nitrogen cylinder alarm pressure setpoint that will cause annunciator 1-3-F, AUX XFMR 11 TRBL, to alarm in the Control Room?
A. 200 psig
B. 300 psig
C. 400 psig
D. 500 psig
A
Which ONE of the following conditions will result in Control Room annunciator 1-3-F, AUX XFMR 11 TRBL, being LIT?
A. Undervoltage
B. Pressure relief lifts
C. High oil temperature
D. Low oil level
A
The following plant conditions exist:
* Reactor power is 100%.
* Alarm 16-3-C, MN XFMR 1 DNGR, actuates.
* An EO sent to the Main Transformer reports that the IDD Alert - Action is in alarm.
Which one of the following is the appropriate response to this situation?
A. Immediately trip the reactor and go to DB-OP-02000.
B. Reduce power to less than 40% power and trip the Turbine.
C. Contact the Electricians for verification and follow-up actions.
D. Preform a rapid shutdown to Low Level Limits, trip the reactor and go to DB-OP-02000.
C
Which of the following combinations will lead to the greatest possibility of static electrification in the main transformer?
A. High oil flow rate at high oil temperatures.
B. High oil flow rate at low oil temperatures.
C. Low oil flow rate at low oil temperatures.
D. Low oil flow rate at high oil temperatures.
B
Determine which ONE of the following annunciators would be received in the Control Room as a result of failure of Startup Transformer 01 due to static electrification.
A. SU XFMR 01 DNGR
B. SU XFMR 01 TRBL
C. BUS A LOCKOUT
D. J BUS DIFF
A
EACH of the generator output breakers, ACB 34560 and 34561 has THREE (3) Control Room indicating lights at its respective Hand Indicating Switch.The green indicating light, when LIT, indicates that the breaker is __________ and the 2 red lights, when LIT, indicate that the breaker is __________
A. TRIPPED and power is available to the CLOSE coil;
CLOSED and power is available to BOTH TRIP coils.
B. TRIPPED and power is available to BOTH TRIP coils;
CLOSED and power is available to the CLOSE coil.
C. CLOSED and power is available to the TRIP coil;
TRIPPED and power is available to BOTH CLOSE coils.
D. CLOSED and power is available to BOTH TRIP coils;
TRIPPED and power is available to the CLOSE coil.
A
Which ONE of the following sets of locations allows for opening ACB 34560 from EACH location within the set?
A. - System Dispatcher’s office
- Control Room
- Relay House
B. - Control Room
- Relay House
- Breaker Control Cabinet in the switchyard
C. - Relay House
- Breaker Control Cabinet in the switchyard
- System Dispatcher’s office
D. - Breaker Control Cabinet in the switchyard
- System Dispatcher’s office
- Control Room
D
The ________________ allows for automatic reestablishment of the ring bus via closure of its associated breaker in the event of a momentary fault such as a lightning strike.
A. Carrier switch
B. Recloser switch
C. Feeder Line relaying
D. Transfer Trip switch
B
The system is the DIRECT source of reliable electrical power to the 480 VAC nonessential distribution system.
A. 345 kV
B. 13.8 kV
C. 4160 VAC
D. 480 VAC essential
B
With the plant in Mode 5, which of the following describes the normal source of power to 13.8 kV Bus B?
A. Main Transformer
B. Startup Transformer 1
C. Startup Transformer 2
D. Auxiliary Transformer 11
B
The plant has been operating at full power for 9 months when annunciator 1-4-E, BUS A LOCKOUT goes into ALARM.
Which ONE of the following combinations of LIT alarms can be expected to be received coincident with a valid ground fault on A Bus?
A. · XFMR AC LOCKOUT, 1-1-D
· BUS C1 BKRS NTNM, 1-5-D
· BUS D1 BKRS NTNM, 1-5-H
B. · XFMR AC LOCKOUT, 1-1-D
· BUS C1 BKRS NTNM, 1-5-D
· BUS A BKRS NTNM, 1-5-E
C. · BUS C1 BKRS NTNM, 1-5-D
· BUS A BKRS NTNM, 1-5-E
· BUS B BKRS NTNM, 1-5-G
D. · BUS A BKRS NTNM, 1-5-E
· BUS B BKRS NTNM, 1-5-G
· BUS D1 BKRS NTNM, 1-5-H
B
Which ONE of the following describes the purpose of HS9828, Bus C1 Undervoltage Trip Bypass?
A. DEFEAT the Loss of Voltage Relay (59% UV) TRIP for AC Transformer.
B. BYPASS the Degraded Voltage Relay (90% UV) TRIP feature on C1 Bus.
C. OVERRIDE the Loss of Voltage Relay (59% UV) TRIP for C1 Bus lockout circuitry.
D. INSERT a Degraded Voltage Relay (90% UV) TRIP setpoint into the C1 Bus control scheme.
B
A LOCKOUT has occurred on A Bus.
Which ONE of the following describes the status of the “A” Bus breakers?
A. All load breakers and supply breakers open.
B. Load breakers and supply breakers are NOT affected.
C. Load breakers open, supply breakers are NOT affected.
D. Load breakers are NOT affected, supply breakers open.
A
The plant is in Mode 3 with all electrical systems in a normal lineup.
Which ONE of the following will cause A Bus to automatically transfer to Startup Transformer 02?
A. Low oil level on Transformer 02.
B. A current differential on Transformer 01.
C. High winding temperature on Transformer Aux 11.
D. Loss of 480 VAC power to the cooling fans and pumps for Transformer Auxiliary 11.
B
A ground fault has occurred on B bus. Which ONE of the following annunciators will NOT be received as a result of the event?
A. XFMR BD LOCKOUT (1-1-H)
B. BUS B LOCKOUT (1-4-G)
C. BUS B BKRS NTNM (1-5-G)
D. BUS F7 TRBL (1-5-J)
D
Bus A is inadvertently deenergized due to a switching error during a plant shutdown. Which ONE of the following buses will be deenergized as a result of manually deenergizing A Bus?
A. C1 Bus
B. C2 Bus
C. F7 Bus
D. E1 Bus
B
The plant is at 100% power. All systems are in a normal lineup.
A LOCKOUT of A Bus has occurred. Which ONE of the following describes the impact on the Electrical Distribution System?
A. - C1 fast transfers to BD transformer
- C2 is fed power from C1 bus
- Power is lost to E2 and E3 buses
- E5 continues to receive power from its normal source
B. - EDG-1 starts to supply power to C1 bus
- Power is lost to C2 bus
- E2 and E3 transfer to the alternate B bus supply
- Power is lost to E5
C. - C1 fast transfers to BD transformer
- Power is lost to C2 bus
- Power is lost to E2 and E3 buses
- E5 continues to receive power from its normal source
D. - EDG-1 starts to supply power to C1
- C2 is fed power from C1
- E2 and E3 transfer to the alternate B bus supply
- Power is lost to E5
A
Which ONE of the following is the function of the undervoltage (UV) bypass pushbuttons?
A. Temporarily locks out the Emergency Diesel Generator.
B. Allows the Degraded Voltage Relay (90 % UV) Essential Bus load shed to be bypassed.
C. Allows the Loss of Voltage Relay (59 % UV) Essential Bus load shed to be bypassed.
D. Bypasses the Safety Features Actuation System start signal for the Emergency Diesel
Generator.
B
Which ONE of the following describes the purpose of the 13.8 kV Distribution System?
A. Distribute generator output to the switchyard and to the station.
B. Directly provide power for 480 VAC non-essential distribution and to Emergency Core Cooling System components.
C. Directly provide an alternate source of power to the essential busses on a loss of the Emergency Diesel Generators.
D. Directly provide reliable power for 480 volt non-essential distribution, Reactor Coolant Pumps and the Circulating Water Pumps.
D
The system is the DIRECT source of reliable electrical power to the 480 VAC nonessential distribution system.
A. 345 kV
B. 13.8 kV
C. 4160 VAC
D. 480 VAC essential
B
The following plant conditions exist:
* The plant is operating at 100% power.
* Equipment is in a normal alignment.
The following actions automatically occur:
* HX11A opens
* HAAC opens
* AACC2 opens
* ABDC1 closes
This would occur as a result of which ONE of the following?
A. Ground on A Bus
B. Ground on B Bus
C. Overpressure on AC Transformer
D. Overpressure on BD Transformer
A
Which ONE of the following Buses receives its source of power DIRECTLY from 13.8 kV Bus A?
A. 4160V Bus C1
B. 4160V Bus C2
C. 480V Bus F1
D. 480V Bus F2
B
Which ONE of the following Buses receives its source of power DIRECTLY from 13.8 kV Bus B?
A. 4160V Bus C2
B. 4160V Bus D1
C. 480V Bus F1
D. 480V Bus F4
D
With the plant at 100% power, which ONE of the following describes the NORMAL electrical power flowpath to 13.8 kV Bus A?
A. Main Generator Output via Auxiliary Transformer 11
B. 345 kV Bus J via Auxiliary Transformer 11
C. 345 kV Bus J via Startup Transformer 01
D. 345 kV Bus K via Startup Transformer 02
A
With the plant in Mode 6, which ONE of the following is the NORMAL electrical power flowpath to 13.8 KV Bus B?
A. 345 kV Bus J via Auxiliary Transformer 11
B. 345 kV Bus K via Auxiliary Transformer 11
C. 345 kV Bus J via Startup Transformer 01
D. 345 kV Bus K via Startup Transformer 02
D
Due to a fire in the #1 High Voltage Switchgear Room, it is decided to completely de-energize 13.8kV Bus A (Remove AC & DC Voltage sources). Which ONE of the following would accomplish this objective while minimizing the impact on the remaining plant equipment? Open HX01A, HX02A and HX11A. Open ____________
A. DAP02 and DAN02. Place ALL “A” Bus emergency control transfer switches in local.
B. the control power knife switch. Place the A Bus Reserve Source Selector switch in the 02 position.
C. DAP02, DAN02, HAAC, HAAE4, HAAE3 and HAAE2.
D. D1P02, D1N02, HAAC, HAAE4, HAAE3 and HAAE2.
C
Which ONE of the following 13.8 kV breakers WILL trip due to an A Bus lockout; but WILL NOT trip due to an A Bus undervoltage?
A. 1-1 Reactor Coolant Pump Breaker (HA03)
B. Bus Tie Transformer AC Breaker (HAAC)
C. 1-3 Circ Water Pump Breaker (HA12)
D. Bus Tie Transformer BD Breaker (HBBD)
B
Which ONE of the following local switches is still functional on A Bus with all of the Emergency Disconnect Switches in the REMOTE position?
A. Reserve Source Selector Switch
B. Breaker Hand Switch for HX01A
C. Synchronizing Switch for HX02A
D. Synchronizing Switch for HX11A
B
Which ONE of the following describes the NORMAL source of power to A Bus during NORMAL operation at FULL power?
A. Auxiliary 11 Transformer
B. Startup Transformer 01
C. Startup Transformer 02
D. Main Transformer
A
Match the source of DC control power in the right column with its associated load in the left column.
____ 1. A Bus Normal (source breakers)
____ 2. A Bus Alt (source breakers)
____ 3. A Bus Normal (load breakers)
____ 4. A Bus Alt (load breakers)
____ 5. B Bus Normal (source breakers)
____ 6. B Bus Alt (source breakers)
____ 7. B Bus Normal (load breakers)
____ 8. B Bus Alt (load breakers)
A. DAN
B. DBN
C. DBP
D. DAP
- A.
- D.
- D.
- A.
- B.
- C.
- C.
- B.
Which ONE of the following explains the use of potential transformers in the 13.8 kV System?
A. Step down bus voltage to a value usable for metering and relaying.
B. Step down bus voltage to a value usable for a backup source of breaker control power.
C. Provide signal isolation to prevent a ground on one meter from affecting other indicators.
D. Provide a means of reducing system current to a value that allows easier transmission of power to system loads.
A
Which ONE of the following is the NORMAL source of DC control power for 13.8 kV Bus A source breakers?
A. DAN
B. DBN
C. DBP
D. DAP
A
Annunciator Alarm (1-4-G) BUS B LOCKOUT has just illuminated.
Which ONE of the following describes the status of the B Bus breakers?
A. All load and supply breakers open
B. Load and supply breakers are not affected
C. Load breakers open, supply breakers are not affected
D. Load breakers are not affected, supply breakers open
A
Which ONE of the following conditions will cause Annunciator (1-4-E) BUS A LOCKOUT to alarm?
A. Bus A Overcurrent
B. Bus A Undervoltage
C. Bus A Underfrequency
D. Bus A High Temperature
A
Which ONE of the following sets of pumps would stop running on an A Bus undervoltage?
- RCP 1-1
- RCP 1-2
- RCP 2-1
- RCP 2-2
- Circ Water Pump 1
- Circ Water Pump 2
- Circ Water Pump 3
- Circ Water Pump 4
A. 1, 3, 5, 8
B. 1, 4, 5, 7
C. 2, 3, 6, 7
D. 2, 4, 6, 8
B
Which ONE of the following describes the function of the Undervoltage Bypass pushbuttons (HIS9828 and HIS9829)?
A. Bypasses the 90% undervoltage relays.
B. Bypasses the 59% undervoltage relays.
C. Temporarily locks out the Emergency Diesel Generator.
D. Bypasses the SFAS start signal to the Emergency Diesel Generator.
A
The following plant conditions exist:
The plant is operating at 100% power.
What happens to the 13.8 kV buses on a degraded 345 kV grid frequency?
A. The bus locks out.
B. The bus automatically load sheds.
C. 13.8 KV bus automatically transfers to the source selected on the reserve source selector switch.
D. Tech. Spec. 3.8.1.1 requires frequency to be restored with four (4) hours or begin plant shutdown in the next six (6) hours.
B
The following plant conditions exist:
* The plant is at 100% power.
* All systems are in a normal lineup.
The following event occurs:
* Lockout of A bus.
Which one of the following describes the impact on buses that are NORMALLY powered from A bus?
A. C1 fast transfers to BD transformer
C2 is fed power from C1
Power is lost to E2 and E3 buses
E5 continues to receive power from its normal source
B. EDG 1 starts to supply power to C1
Power is lost to C2
E2 and E3 transfer to the alternate B bus power supply
Power is lost to E5
C. C1 fast transfers to BD transformer
Power is lost to C2
Power is lost to E2 and E3 buses
E5 continues to receive power from its normal source
D. EDG 1 starts to supply power to C1
C2 is fed power from C1
E2 and E3 transfer to the alternate B bus power supply
Power is lost to E5
A
The following plant conditions exist:
* The plant is at 100% power.
* All systems are in a normal lineup.
* Subsequently, a lockout of A bus occurs.
Which one of the following describes the impact on buses that are NORMALLY powered from A Bus?
A. C1 fast transfers to BD transformer
C2 is fed power from C1 bus
Power is lost to E2 and E3 buses
E5 continues to receive power from its normal source
B. EDG 1 starts to supply power to C1 bus
Power is lost to C2 bus
E2 and E3 fast transfer to the alternate B bus supply
Power is lost to E5
C. C1 fast transfers to BD transformer
Power is lost to C2 bus
Power is lost to E2 and E3 buses
E5 continues to receive power from its normal source
D. EDG 1 starts to supply power to C1
C2 is fed power from C1
E2 and E3 fast transfer to the alternate B bus supply
Power is lost to E5
A
The 13.8 KV Bus synchro check relays ensure proper phasing for live transfers by looking at both sources of power and preventing breaker closure if ______________________.
A. current difference between them is greater than 5 amps
B. voltage difference between them is greater than 100 volts
C. phase difference between them is greater than 35 degrees
D. frequency difference between them is greater than 0.5 cycles
C
Which ONE of the following describes the function of the Bus C1 and D1 Undervoltage Trip Bypass pushbuttons (HIS9828 and HIS9829)?
A. Bypasses the Degraded Voltage relays
B. Bypasses the Loss of Voltage relays
C. Temporarily locks out the Emergency Diesel Generator
D. Bypasses the SFAS start signal to the Emergency Diesel Generator
A
During MODE 1, full power operations, the NORMAL source of electrical power to essential 480 VAC substations E1 and F1 is ____________.
A. 13.8 KV Buses A and B via DIRECT feed to substation transformers for E1 and F1.
B. 13.8 KV Buses A and B which are fed from Startup Transformers 01 and 02.
C. 4160 VAC via C2 Bus and D2 Bus which are fed from C1 Bus and D1 Bus, respectively.
D. 4160 VAC via C1 Bus and D1 Bus which are fed from C2 Bus and D2 Bus, respectively.
D
The purpose of a circuit breaker is: A fuse like device__
A. with no control features
B. that is reusable
C. that is reusable after repair.
D. only operated in emergencies.
B
What is the purpose of a circuit breaker; A protective device_____
A. used to verify instrumentation is correctly functioning.
B. capable of making, carrying, and breaking currents by automatic means only.
C. that can only be closed, following a fault trip, manually.
D. used to provide quick connections and disconnections.
D
Which ONE of the following sets contains components which are ALL fed directly from 4160 VAC bus C1?
- Component Cooling Water Pump 1
- Decay Heat Pump 1
- Emergency Instrument Air Compressor
- Makeup Pump 1
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
B
Which ONE of the following sets contains components which are ALL fed directly from 4160 VAC bus C2?
- Motor Driven Feed Pump
- Startup Feed Pump
- Switchyard Feeder #1
- Backup Service Water Pump
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
D
Which ONE of the following sets contains components which are ALL fed directly from 4160 VAC bus D1?
- HPI pump 2
- CTMT spray pump 2
- DHR pump 2
- Service Water pump 2
A. 1, 2, 3
B. 1, 3, 4
C. 1, 2, 4
D. 2, 3, 4
B
Which ONE of the following sets contains components which are ALL fed directly from 4160 VAC bus D2?
- Backup Service Water Pump
- Motor Driven Feed Pump
- Station Air Compressor #2
- Aux. Boiler Forced Draft Fan
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
D
Which ONE of the following is the normal power lineup for bus D1?
A. Bus D2 supplies bus D1 via AD110.
B. Bus C2 supplies bus D1 via AACD1.
C. Bus tie transformer BD supplies D1 via ABDC1.
D. Bus tie transformer AC supplies D1 via AACD1.
A
Which of the below statements describe a condition for the use of the cross-tie breakers for the 4160 VAC essential buses (supplying both C1 & D1 from one Bus Tie Transformer)?
A. Both SU Transformers must be OPERABLE or declare one Offsite AC Source INOPERABLE.
B. Both SU Transformers must be OPERABLE or declare Onsite AC Distribution System INOPERABLE.
C. Operation in this configuration is not allowed at power (Modes 1-4) due to ETAP concerns with bus and transformer voltage drop.
D. There are no restrictions to this configuation based upon ETAP analysis of bus and transformer voltage drops.
A
Which ONE of the following will occur on a Bus C1 lockout?
A. ALTERNATE supply breaker (ABDC1) CLOSES to energize the bus.
B. NORMAL supply breaker (AC110) remains CLOSED to keep the bus energized.
C. Emergency Diesel Generator 1 STARTS, but its output breaker (AC101) DOES NOT CLOSE.
D. Emergency Diesel Generator 1 STARTS, and its output breaker (AC101) CLOSES to reenergize the bus.
C