What are the Sub-systems of non-rad ventilation?
- Aux building non-rad ventilation
- Low voltage switchgear room ventilation
- Battery room ventilation
- Main steam line room ventilation
- CCW room
- EDG rooms
- Aux Feed Pump room
What is Non-rad ventilation purpose?
Provide conditioned air or local heating for areas to maintain temperature, prevent freezing, and provide a suitable environment for personnel
The Auxiliary Building Nonradioactive Areas HV System shall maintain the space temperature between what?
104F - 60F
The Auxiliary Building Nonradioactive Areas HV System shall maintain the space temperature , unless otherwise noted, during all modes of operation under the following two outside ambient conditions
Summer 95°F (dry bulb)/76°F (wet bulb)
Winter –10°F (dry bulb
The basis for 104°F maximum temperature of the Auxiliary Building Non-Rad Ventilation is to meet what?
The equipment qualification requirements.
CCW room fan cycles between __ and ___
99F - 80F
CCW room dampers modulate when fan running maintains what temperature?
85F
EDG rooms maintain between what temperatures?
90F - 60F
What EDG rpm does the EDG room ventilation turn on?
40rpm
AFP room auto cycles between what temperatures?
104F and 80F
i
i
List five (5) lube oil tanks that are part of the lube oil purification, transfer, and storage system.
New lube oil storage tank
Used lube oil storage tank
T-G lube oil tank
MFPT lube oil tank 1 and 2
MFPT used lube oil tank
Why are accumulated water vapors in the TGLO tank an operational concern?
Formation of rust in the tank
The Vapor Extractor on the Turbine Generator Lube Oil Tank ________________.
A. is used primarily to remove water vapor.
B. is used primarily to remove accumulated nitrogen gas.
C. causes excessive dirt and water to be drawn into the oil.
D. is used primarily to prevent cavitation of the motor suction pump.
A
Where is the Main Turbine Lube Oil Tank LEVEL normally read and what is the normal operating level?
TG Lube Oil Tank room - normal 5 ft.
Normal level in the T-G Lube Oil Tank should be _____ inches from the bottom of the tank.
A. 60”
B. 50”
C. 40”
D. 32”
A
All objects must be removed from the Turbine Generator Lube Oil tank hatches prior to starting the system to ensure _____________.
A. the hatches function as an explosion - relief device
B. class “A” housekeeping requirements are maintained
C. a slight positive pressure is maintained by the vapor extractor
D. accessibility for performance of level alarm float switch maintenance
A
Choose the correct value for the high differential pressure setpoint on the Kadon Lube Oil purification skid.
A. 5 psid
B. 15 psid
C. 25 psid
D. 100 psid
C
Which ONE (1) of the following describes the operation of the Air Detraining Section within the Turbine Generator Lube Oil Tank?
A. Reduces turbulence of oil in high flow areas of the tank by use of a vertical baffle
B. Promotes evaporation of water by use of a vapor extractor
C. Removes air from the tank atmosphere by use of a vapor extractor
D. Reduces turbulence of oil in high flow areas of the tank by use of 2 fine mesh screens
A
Who must approve any lube oil transfer to the Main Feed Pump Turbine Lube Oil Tank?
A. The Test/Performance Engineer
B. The Maintenance Manager
C. The Lube Room Supervisor
D. The Fire Protection Engineer
A
State the purpose of the Kaydon Lube Oil Conditioner
The conditioner removes particulate impurities and a coalescing
filter to remove water. An acceptable answer to include both particulate and water.
New Lube Oil should be transferred to the Main Feed Pump Turbine Lube Oil Tank via the?
A. Used Lube Oil Tank
B. Main Lube Oil Reservoir
C. Kaydon Lube Oil Conditioner
D. Portable Lube Oil Transfer Pump
C
State the purpose of the 480 Volt Electrical Distribution System.
Receives power from the 13.8kV and 4160 V (.5) buses through unit substations to provide power to motor control centers
The ____________ system receives power from the 4160 VAC and
____________ system via unit substations to provide power to motor control centers.
A. 120 VAC; 480 VAC
B. 480 VAC; 345 Kv
C. 240 VAC; 13.8 Kv
D. 480 VAC; 13.8 Kv
D
A lockout on __________ will cause the Emergency Instrument Air compressor to shut down.
A. Bus A
B. Bus D1
C. Bus D2
D. Bus Tie Transformer AC
C
The following conditions have been noted:
* HIS 6227, control switch for essential 480 VAC transformer AC1CE12 green and red lights are OFF.
* BOTH light bulbs have been verified as operational.
* II 6227, BUS C1 TO XFMR CE1-2 current indicates 5 AMPS.
* II 6226, BUS C1 TO XFMR CE1-1 current indicates 40 AMPS.
Which ONE of the following statements explains this set of conditions?
A. Transformer CE1-1 is supplying E1, breaker AC1CE12 is racked out.
B. Transformer CE1-1 is supplying E1, the Emergency Control Transfer Switch for AC1CE12 is in LOCAL.
C. Transformers CE1-1 and CE1-2 are BOTH supplying E1,
BOTH Emergency Control Transfer Switches are in NORMAL.
D. Transformer CE1-2 is supplying E1, breaker AC1CE11 is OPEN
the Emergency Control Transfer Switch for AC1CE12 is in LOCAL.
B
From the Control Room a transfer of Unit Substation E1 from one source to another utilizes __________ and the transfer can __________ transfer.
A. a single switch; be EITHER a live or dead
B. a single switch; ONLY be performed as a dead
C. 2 separate switches; ONLY be performed as a dead
D. 2 separate switches; be EITHER a live or dead
A
Which ONE of the following Motor Control Centers has a Kirk Key interlock associated with it?
A. EF12D
B. E22B
C. F22B
D. F31A
A
Which ONE of the following conditions will NOT cause annunciator 1-3-C, XFMR CE1-1 TRBLE to alarm?
A. Transformer CE1-1 low liquid level
B. Transformer CE1-1 low liquid temperature
C. Transformer CE1-1 pressure relief operation
D. Transformer CE1-1 high tank pressure
B
Which ONE of the following sets of 480 Volt Buses are required to be operable in accordance with Technical Specifications while operating at 100% power?
A. E1 and F1
B. E1 and F2
C. E2 and F1
D. E2 and F2
A
The green light being OFF above the Control Room control switch for a 480V Unit Substation Breaker indicates _____.
A. The breaker is racked in to the TEST position
B. The breaker is racked in to the OPERATE position
C. DC voltage is NOT available to the breaker TRIP coil
D. DC voltage is NOT available to the breaker CLOSE coil
C
Which ONE of the following choices represents the correct flowpath order from HIGH voltage to LOW voltage of the listed components?
1. BD Transformer
2. 480 VAC Motor Control Center F12B
3. 4160 VAC Bus D2
4. Unit Substation F1
A. 1, 2, 4, 3
B. 1, 3, 4, 2
C. 3, 1, 2, 4
D. 4, 1, 3, 2
B
How many transformers will be energized as a result of CLOSING a 13.8 KV breaker to energize a non-essential substation?
A. 1
B. 2
C. 3
D. 4
B
Which ONE of the following choices represents the correct flowpath order from HIGH voltage to LOW voltage of the listed components?
1. AC Transformer
2. Motor Control Center E12B
3. Bus C2
4. Unit Substation E1
A. 1, 2, 4, 3
B. 1, 3, 4, 2
C. 3, 1, 2, 4
D. 4, 1, 3, 2
B
The following conditions have been noted:
* HIS 6227, control switch for essential 480 VAC transformer AC1CE12 green and red lights are OFF.
* BOTH light bulbs have been verified as operational.
* II 6227, BUS C1 TO XFMR CE1-2 current indicates 5 AMPS.
* II 6226, BUS C1 TO XFMR CE1-1 current indicates 40 AMPS.
Which ONE of the following statements explains this set of conditions?
A. Transformer CE1-1 is supplying E1,breaker AC1CE12 is racked out.
B. Transformer CE1-1 is supplying E1, the Emergency Control Transfer Switch for AC1CE12 is in LOCAL.
C. Transformers CE1-1 and CE1-2 are BOTH supplying E1,
BOTH Emergency Control Transfer Switches are in NORMAL.
D. Transformer CE1-2 is supplying E1, breaker AC1CE11 is OPEN the Emergency Control Transfer Switch for AC1CE12 is in LOCAL.
B
Which ONE of the following is NOT an automatic shutdown of the Miscellaneous Diesel Generator?
A. Lube Oil pressure reads 8 psi.
B. Engine speed reads 2000 RPM
C. Coolant Temperature reads 210 F
D. Overcrank - engine cranks for 90-100 seconds without starting
B
Which ONE of the following is NOT an automatic shutdown of the Miscellaneous Diesel Generator?
A. High crank case pressure ( 5 psig)
B. Unloaded in auto ( 5 minutes)
C. Overspeed (2070 RPM)
D. High coolant temperature (205 F.)
A
During a loss of offsite power the Miscellaneous Diesel Generator will start and supply electrical power to security systems via Motor Control Center:
A. E43
B. F71
C. E11C
D. E23A
A
There are ____ Emergency Lighting Panels in the plant which NORMALLY are powered from E5 and F5 and receive EMERGENCY backup power from ____ .
A. 4, the DC MCC 250 VDC buses.
B. 4, battery BA and BB.
C. 6, the DC MCC 125 VDC buses.
D. 6, individual 8-hour battery packs.
A
A typical emergency lighting panel can be supplied from 2 separate sources, with one being ____________ and the other being _______________ via an automatic bus transfer device.
A. 120 VAC bus; 250VDC MCC
B. internal batteries; 480 VAC bus
C. substation E5 or F5; 250VDC MCC
D. substation E5 or F5; internal batteries
C
A lockout on __________ will cause the Emergency Instrument Air compressor to shut down.
A. Bus A
B. Bus D1
C. Bus D2
D. Bus Tie Transformer AC
C
When transferring from the Normal to Alternate Transformer for non essential bus E2 using the Control Room switch,
The normal breaker will open:
A. as soon as the alternate source breaker closes.
B. when the synchro check relays energize for the alternate source.
C. after the control switch is held in the “Alternate” position for 5 seconds.
D. when the breaker control switch is released and returns to it’s mid position.
D
Which ONE of the following conditions will NOT cause annunciator 1-4-C XFMR CE1-2 TRBLE to alarm?
A. Transformer CE1-2 pressure relief operation
B. Transformer CE1-2 tank pressure <5.5 psig vacuum
C. Transformer CE1-2 liquid temperature <90 degrees C
D. Transformer CE1-2 liquid level 17.5” below handhole
C
Which ONE of the following conditions will result in annunciator 1-2-I XFMR DF1-2 FAULT going into alarm?
A. F1 Bus overcurrent
B. Loss of DC control power for F1 Bus
C. Transformer DF 1-2 High liquid temperature
D. Ground fault as sensed on ground detection panel C4621A
A
From the Control Room a transfer of Unit Substation E1 from one source to another utilizes __________ and the transfer can _________ transfer.
A. a single switch; be EITHER a live or dead
B. a single switch; ONLY be performed as a dead
C. 2 separate switches; ONLY be performed as a dead
D. 2 separate switches; be EITHER a live or dead
A
A lockout on __________ will cause the Emergency Instrument Air compressor to shut down.
A. Bus A
B. Bus D1
C. Bus D2
D. Bus Tie Transformer AC
C
Which ONE of the following Motor Control Center’s (MCC) has a Kirk Key interlock associated with it?
A. EF15
B. E22A
C. F23B
D. F61
A
The emergency lighting panels powered from E5 & F5 get their alternate power from _________.
A. 480 VAC Essential bus E1
B. 250 VDC Motor Control Center’s
C. 480 VAC Essential bus F1
D. 120 VAC Essential panel YE1
B
Which ONE of the following is NOT an automatic shutdown of the Miscellaneous Diesel Generator?
A. Lube Oil pressure reads 8 psi.
B. Engine speed reads 2000 RPM
C. Coolant Temperature reads 210 F
D. Overcrank - engine cranks for 90-100 seconds without starting
B
Which ONE of the following is NOT an automatic shutdown of the Miscellaneous Diesel Generator?
A. High crank case pressure ( 5 psig)
B. Unloaded in auto ( 5 minutes)
C. Overspeed (2070 RPM)
D. High coolant temperature (205 F.)
A
The emergency lighting panels powered from E5 & F5 get their alternate power from _________.
A. 480 VAC Essential bus E1
B. 250 VDC Motor Control Center’s
C. 480 VAC Essential bus F1
D. 120 VAC Essential panel YE1
B
There are ____ Emergency Lighting Panels in the plant which NORMALLY are powered from E5 and F5 and receive EMERGENCY backup power from ____
A. 4, the DC MCC 250 VDC buses.
B. 4, battery BA and BB.
C. 6, the DC MCC 125 VDC buses.
D. 6, individual 8-hour battery packs.
A
The function of the Switchyard DC Network is ___________.
A. to provide a source of power for starting the Miscellaneous Diesel Generator
B. to provide power for various metering and relay circuits in the switchyard
C. to provide control power for operation of the switchyard breakers
D. to provide power to the alarm panel in the Relay House
B
Which of the following Relay House Loads is supplied by an automatic bus transfer device?
A. Switchyard Air Compressors, Relay House HVAC Unit
B. Switchyard Air Compressors, L3 Distribution Panel
C. Battery Charger CA, Relay House HVAC Unit
D. L3 Distribution Panel and Battery Charger CA
A
Which ONE of the following choices represents the correct flowpath order from HIGH voltage to LOW voltage of the listed components?
1. BD Transformer
2. 480 VAC Motor Control Center F12B
3. 4160 VAC Bus D2
4. Unit Substation F1
A. 1, 2, 4, 3
B. 1, 3, 4, 2
C. 3, 1, 2, 4
D. 4, 1, 3, 2
B
Which ONE (1) of the following 480 volt MCCs is energized by depressing a rocker arm switch that energizes an internal contactor?
A. F13
B. EF12C
C. EF12D
D. EF15
B
When placing the local disconnect switch for a 480 VAC essential component in the “local” position. The Control Room:
A. will have no remote control of the component.
B. will be able to only OPEN the components breaker.
C. will be able to place the component in it’s Safe Shutdown position if it has one.
D. will be able to operate the component only if it is a support system required to be operable during accident conditions.
A
The emergency lighting panels powered from E5 & F5 get their alternate power from _________.
A. 480 VAC Essential bus E1
B. 250 VDC Motor Control Center’s
C. 480 VAC Essential bus F1
D. 120 VAC Essential panel YE1
B
There are ____ Emergency Lighting Panels in the plant which NORMALLY are powered from E5 and F5 and receive EMERGENCY backup power from ____ .
A. 4, the DC MCC 250 VDC buses.
B. 4, battery BA and BB.
C. 6, the DC MCC 125 VDC buses.
D. 6, individual 8-hour battery packs.
A
A typical emergency lighting panel can be supplied from 2 separate sources, with one being ____________ and the other being _______________ via an automatic bus transfer device.
A. 120 VAC bus; 250VDC MCC
B. internal batteries; 480 VAC bus
C. substation E5 or F5; 250VDC MCC
D. substation E5 or F5; internal batteries
C
Which ONE of the following could be a common cause for the BUS E1 TRBL and BUS C1 BKRS NTNM annunciators in alarm?
A. 480 VAC Breaker BCE11 spuriously tripped open.
B. Ground fault on 4160/480 VAC transformer CE1-1.
C. Bus fault on 4160 VAC Bus C1.
D. 4160 VAC Breaker AC1CE11 spuriously tripped open.
D
Which ONE of the following statements is correct concerning the Station Lighting System?
A. A transfer of Unit substation F5 from NORMAL to ALTERNATE is usually a live transfer.
B. A transfer of Unit substation E5 from ALTERNATE to NORMAL is always a dead transfer because of a kirk key interlock.
C. The normal method of transferring Unit substation E5 will not result in any momentary loss of lighting in any areas of the plant.
D. All transfers of Unit substations E5 and F5 are designed to be live transfers to prevent loss of lighting to any essential areas of the plant.
B
There are ____ Emergency Lighting Panels in the plant which NORMALLY are powered from E5 and F5 and receive EMERGENCY backup power from ____
.
A. 4, the DC MCC 250 VDC buses.
B. 4, battery BA and BB.
C. 6, the DC MCC 125 VDC buses.
D. 6, individual 8-hour battery packs
A
Which ONE of the following specifies how long the Updated Safety Analysis Report assumes that control room instrumentation is designed to continue to operate during a loss of all AC power?
A. 30 minutes
B. 60 minutes
C. 120 minutes
D. 180 minutes
B
The purpose of the Instrument AC System is to provide reliable, __________.
A. BACKUP redundant 120 VDC power to NORMAL DC instrumentation
B. BACKUP redundant 120 VAC power to 125 VDC instrumentation
C. Redundant 120 VAC power to NORMAL AC instrumentation
D. Redundant 120 VAC power to 125 VDC instrumentation
C
Which ONE of the following completes the following statement concerning instrument AC loads and their respective power supplies? The normal feed to __________ is __________, and an alternate feed is ______________.
A. SFAS Channel 1; Y1 from inverter YV1; Y1 from voltage regulator XY1.
B. Post Accident Channel 2; Y1 from inverter YV1; Y1 from voltage regulator XY1.
C. ARTS Channel 3; Y1 from inverter YV1; Y1 from voltage regulator XY1.
D. SFRCS Channel 4; Y4 from inverter YV4; Y4 from voltage regulator XY4.
A
The Post Accident Monitoring instruments are powered from which ONE of the following?
A. Non-Nuclear Instrumentation
B. Essential Instrument AC
C. Uninterruptable Instrument AC
D. Nonessential DC
B
Which ONE of the following completes the following statement concerning instrument AC loads and their respective power supplies? The normal feed to __________ is __________.
A. RPS Channel 2; Y1
B. RPS Channel 4; Y3
C. SFRCS Channel 1; Y1
D. SFRCS Channel 3; Y3
C
Alternate AC power to the Essential Instrument Buses Y1 through Y4 is provided from _____.
A. Essential Powered Rectifiers
B. Non-Essential Powered Rectifiers
C. Essential Powered Constant Voltage Transformers
D. Non-Essential Powered Constant Voltage Transformers
C
Inverter YVA is NORMALLY powered by __________, but will
AUTOMATICALLY transfer to __________ via action of a static transfer switch.
A. non-essential 480 VAC; non-essential 120 VAC
B. non-essential 480 VAC; essential 120 VAC
C. 250 VDC; non-essential 120 VAC
D. 250 VDC; essential 120 VAC
C
The __________ is provided to allow automatic live transfer of Inverters YV1 through YV4 to alternate.
A. out of phase device
B. synchronizing reference signal
C. synchrocheck relay
D. automatic bus transfer device
B
Which ONE of the following correctly describes Instrument AC System essential power supplies?
A. Y1 is normally powered from inverter YV1, with alternate power supplied to YV1 automatically from voltage regulator XY1.
B. Y2 is normally powered from inverter YV2, with alternate power supplied to YV2 automatically from voltage regulator XY4.
C. Y3 is normally powered from inverter YV3, with alternate power supplied to YV3 manually from uninterruptable bus YAU.
D. Y4 is normally powered from inverter YV4, with alternate power supplied to YV4 manually from uninterruptable bus YBU.
A
Which ONE of the following is NOT correct concerning Instrument AC loads and their respective power supplies?
The NORMAL feed to _______ is _________ and an ALTERNATE feed is _______________.
A. SFAS Channel 1; Y1 from inverter YV1; Y1 from voltage regulator XY1.
B. Post Accident Channel 2; Y1 from inverter YV1; Y1 from voltage regulator XY1.
C. ARTS Channel 3; Y3 from inverter YV3; Y3 from voltage regulator XY3.
D. RPS Channel 4; Y4 from inverter YV4; Y4 from voltage regulator XY4.
B
The following plant conditions exist:
* The plant is operating at 85% power.
* 4.16 KV Bus C1 is de-energized due to a bus lockout.
* No operator actions have been taken.
Which one of the following describes the electrical supply to Essential Instrument Distribution Panel Y1?
A. Rectified power from E12A through Inverter YV1.
B. E16A through a constant voltage transformer via the Static Transfer Switch on Inverter YV1.
C. DC Distribution Panel D1P supplied from Battery Charger DBC1P through Inverter YV1.
D. DC Distribution Panel D1P supplied from the Station Battery 1P through Inverter YV1.
D
Which ONE of the following conditions will result in Control Room annunciator 1-6-A, INV YV1-YV3 TRBL being LIT?
A. LOW AC Output Current
B. Inverter Cabinet fans OPERATING
C. LOW Inverter Cabinet Temperature
D. LOW AC Output Voltage
D
Which ONE of the following conditions will NOT result in Control Room annunciator 1-6-A, INV YV1-YV3 TRBL being LIT?
A. HIGH DC Current
B. HIGH AC Output Current
C. LOW DC Voltage
D. LOW AC Output Voltage
A