On completion of a new installation who is required to sign the completion certificate?
The designer, the installer and the tester.
The Wiring Regulations, BS7671 are published by which engineering institution?
The Institution of Engineering and Technology, formerly the Institution of Electrical Engineers.
Generally how frequently should an electrical installation in office premises be inspected and tested to check it is in safe condition?
Fixed Wire testing or condition surveys should be undertaken every 5 years.
What is the test and inspection frequency of electrical installations in Leisure Centres?
The longest period between re-inspection and re-testing is 3 years.
What is the re-inspection frequency to be applied to wiring installed in a swimming pool area?
Every 12 months
Defects found during electrical fixed wire testing are prioritised as Cat1; Cat 2 and Cat3. What do these categories indicate?
Cat 1 defects are immediately dangerous and should be repaired or isolated during the inspection/test
Cat 2 defects
Cat 3 defects
How much of an installation must be inspected during the periodic inspection and test of an installation?
All of the inspection which is accessible MUST be inspected.
The Electricity at Work Regulations specifies the minimum frequency of testing Residual Current Devices (RCDs). What is that frequency?
12 months
Who can issue a Permit to Work on LV or HV systems?
Only an Authorised Person - an AP, can issue a Permit to Work.
AP appointments are system specific, so only an AP for the system can issue a Permit on the system.