Earned Value Flashcards
what is earned value?
earned value, as a quantity,represents the amount of work achieved at any given point in time
- every task in the project has an earned value associated with it at any given time
- earned value of each task is zero at the start
- when a task is complete, its earned value is declared to be the amount equal to the amount allocated to the task
how do you calculate earned value?
earned value = total budget x %complete
earned value (task) = total budget (task) x %complete (task)
PC =
planned cost the amount that is planned to have spent at any particular time
AC =
actual costs of the work
How is EV used?
- record is made of each task and progress made (% complete)
- EVs are calculated and added up
- ACs are recorded and added up
- Plotted against Planned cost (PC) on S-curve)
- This can show whether project is on time/on budget
what three variances can be calculated from EV data
CV = cost variance SV (cost) = schedule variance SV (time) = schedule variance
what is CV
the difference between the value of the work performed and the money spent on it CV = earned value - actual costs
SV (cost)
difference between what was planned to have been achieved in terms of value delivered and what has actually been achieved
SV (cost) = earned value - planned cost
SV (time)
shows how far behind (or ahead) the project or activity is, compared to what was planned SV (time) = original duration - time now
what are performance indicies?
- when quantities used to calculate variances are combined to give performance indicies
- e.g. CPI - cost performance
- SPI (cost-based) -schedule performance
- value close to 1.0 represents planned situation
- value < 1 is a problem
- value > 1 is desirable (better than planned)
CPI =
CPI = earned value/ actual cost
SPI (cost based)
SPI (cost-based) = earned value/ planned budget
SPI (time)
SPI (time) = original duration/actual time achieved
what is forecasting ?
To predict the state of the project at completion using baseline plan and earned value data, principally one of the variances or performance indicies
advantages of EVA
- shows time and cost on one report
- trends can be identified and corrective action taken
- cost and schedule variances can used for forecasting
- enables calculation of overall % completion of project which is of interest to senior managers