(DS) Progress Reports Typical to Architectural Firms Flashcards
1
Q
Cash Flow Statement
A
Depicts inflows and outflows or cash
Necessary in order to ensure payroll can be paid
2
Q
Project Progress Report
A
Shows the sum of direct LABOR HOURS and LABOR COST for each phase of a project for the current reporting period and total cost to date in order to compare with estimated project labor costs
3
Q
Office Earnings Report
A
Summarize each firms projects with respect to revenue generated, expenses incurred, percent complete, and profit or lost to date
4
Q
Time Analysis
A
Lists each employee with number of hours spent on direct labor, indirect labor, vacation time, sick leave, and holidays. Used to calculate an employee’s Utilization Rate