AIA B101 Flashcards

1
Q

What is AIA B101

A

Contract between Owner and Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

State the exact verbiage from Standard of Care

A

The Architect shall perform its services with the professional skill and care ordinarily provided by architects practicing in the same or similar locality under the same or similar circumstances. The Architect shall perform its services as is consistent with such professional skill and care and the orderly progress of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the first task under basic services that architect must provide?

A

Creating a schedule of when Architect’s services are to be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the first design task?

A

To review the program the owner provided during schematic design phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What’s the difference between Supplemental and Additional Services

A

Supplemental services is work written in the contract

Additional Services is work added after the project starts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are two obligations the Architect has to the owner that are the same in SD/DD/CD phases?

A

Architect owes owner cost estimate and provide Design Documents at owner’s request.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the owner’s responsibilities when it comes to coordinating the work of Owner’s consultants with the work of the architect?

A

-Owner is to coordinate the work of their consultant with the work of the architect; example GEOTECH AND CIVIL
-the architect is responsible for coordinating work of own consultants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Supplemental Services

A

-Programming
- Multiple Preliminary Designs
- Development of BIM Modeling for Post-construction use
- As-Constructed Record Drawings
-Coordination of Owner’s Consultant
-Measured Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

T/F
You can use this contract with a Stipulated Sum or a Percentage of Construction Cost

A

T

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What’s included in the cost of construction?

A

-All elements of the project specified or designed by Architect.
INCLUDES:
-Contractor Overhead and profit (typically not listed in design-bid-build) so cannot be exluded as it relates to architect’s compensation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is not included in the Cost of the Work?

A

-Land Costs
-Financing
-Contingencies
-Other things owner pays for directly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What if the owner want to save money on Lumber for a project?

A

If owner brings own materials, lumber, etc. that stuff does NOT count toward cost of work, a reasonable value must be assigned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What happens if all bid receieved are higher than the owner’s budget?

A

Owner can:
-Increase Budget
-Rebid or renegotiate
- End project
-Revise the program or scope
- Anything else that owner and Architect agree on

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Is the architect entitled to any compensation if they are required to change construction documents at this point?

A

The architect is required to provide services for all options that owner decides to readjust budget.

Eating into the design fee
-If bids come in too high due to “market” conditions the architect couldn’t have reasonable anticipated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the arch8itect’s requirement to inspect the work during the construction Phase? If B101 is not clear what is the other document that clarifies this?

A

-Inspection of work twice
1. Substantial Completion
2. Final Completion
A201 also refers to architect role

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Time Question:
How frequent are architect site visits during construction?

A

Intervals appropriate to the stage of construction

17
Q

Time Question:
How many day are you required to give notice of termination?

A

9 days

18
Q

Time Question
How much time does owner need to provide information about liens?

A

15 days

19
Q

Time Question
What time frame can an architect terminate agreement if owner suspends project?

A

90 Days

20
Q

List out items included in the base of services

A