Dirt Cratering (Chapter 12) Flashcards

1
Q
  1. What is explosive requirement for Dead stumps?
A

1lb of explosive is used per 1’ of diameter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. What is the spacing between deliberate crater boreholes?
A

Same as hasty crater

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. An expedient cratering charge should prime with what
A

Prime with 1lb of TNT (dual priming is recommended)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. What is formula to calculate relieved face crater?
A

N= (L-10/7)+1

* calculate number of charges for friendly row of boreholes*

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. What is characteristics of deliberate crater?
A

V shaped, 7-8 feet deep & 25-30 wide with 37 degree slope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. What is measurement requirement for end of deliberate crater?
A

End boreholes are 7’ deep

No two 5’ holes sides by sides

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. What is explosive requirement for live stumps?
A

2bls of explosive is used per 1’ of diameter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. What is measurement and explosive requirement of enemy row?
A

4’ deep with 30lbs explosive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. How to measure stump removal?
A

Stumps are measured 12-18” above ground level then diameter is rounded to next higher ½ foot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. What is the spacing between hasty crater boreholes?
A

From center to center 5’ between boreholes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. An effective craters takes _______ allowing time to employ AT weapon
A

4 or more passes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. How to improve craters?
A

By digging face vertically on friendly side, mining, and any other means to further delay the ENY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. What is characteristics of hasty crater?
A

V shaped, 6-7 feet deep & 20-25 wide with 25-35 degree side slope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. What is fuel oil requirement for fertilizer?
A

1 quart per 25lbs of fertilizer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. What is minimum weight of explosive used in hasty craters?
A

At minimum 50lbs of explosive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. To construct deliberate crater, which row will be fired first?
17
Q
  1. For breaching hard surface pavement, use how many pound of explosives for pavement?
A

1 pound for every 2 inches of pavement and tamp charge twice the thickness of the pavement

18
Q
  1. What is measurement of deliberate crater boreholes?
A

A combination of 5’ and 7’ deep

19
Q
  1. What is the placement of row when constructing relieved face crater?
A

On Dirt or Gravel roads: 8’ apart

On Hard surface road: 12’ apart

20
Q
  1. What is explosive requirement for complete tree?
A

3lbs of explosive is used per 1’ of diameter

21
Q
  1. How much nitrogen must be contained in Ammonium nitrate fertilizer?
A

33 1/3% of nitrogen

22
Q
  1. What is hasty crater blowout distance?
A

Approximately 8’

23
Q
  1. What are the three method of boulder removal?
A

Snake-hole, mudcapping, and block-hole method

24
Q
  1. What is the characteristics of relieved face crater?
A

Trapezoidal shape, 7-8 deep and 25-30 feet wide with unequal side slopes

25
7. For hasty crater, what is average traverse attempts of modern tanks?
Average of 4 attempts
26
37. What is taproot hole depth equivalent to?
Equal to breaching radius
27
20. What is measurement and explosive requirement of friendly row?
5’ deep with 40lbs explosive
28
25. For relieved face crater, how would you place first borehole?
First borehole placed 5’ in from desired edge of crater
29
23. What is the spacing between relieved face crater boreholes?
From center to center 7’ between boreholes
30
38. What is lateral hole depth equivalent to?
Equal to breaching radius, place long side of root
31
16. What is minimum explosive requirement of deliberate crater boreholes?
5’ holes will have 40 lbs of explosive | 7’ holes will have 80 lbs of explosive
32
18. What is formula of deliberate crater?
N = (L-16/5) +1
33
4. For hasty crater, what is minimum depth of boreholes?
At least 5’ deep
34
1. What is the requirement of effective craters?
Must be too wide for track vehicles to span & too steepsided for vehicles to pass
35
12. For deliberate crater, what is average traverse attempts of modern tanks?
Average of 8 attempts
36
10. What is the formula for hasty crater?
N= (L-16 / 5)+1 | Round up any fractional number of holes to next higher number
37
19. What are the two types of row requires to construct relieved face crater?
Friendly row and Enemy row
38
28. How to calculate number of enemy row boreholes?
Number of friendly row borehole – 1 hole
39
11. What is deliberate crater blowout distance?
Approximately 8’