Develop Schedule Flashcards
0
Q
What are the tools in the develop schedule process?
A
Schedule network analysis Critical path method Critical chain method Resource optimization techniques -Resource leveling -Resource smoothing
Modeling techniques
- What if analysis (monte Carlo analysis)
- Alternate Critical path performed by a computer
Applying leads and lags
Schedule compression
-Crash it
-Fast tracking
Scheduling tool
1
Q
How many tool, inputs and outputs are there in the develop schedule process?
A
27
2
Q
What are the 7 outputs to the develop schedule process?
A
Project schedule Project network diagrams Schedule baseline Schedule data Project management plan updates Project calendar Project document updates
3
Q
What are the inputs to the develop schedule process?
A
T