Budgeting Formulas Flashcards
1
Q
BAC = ?
A
Total project budget
2
Q
EV = ?
A
EV= BAC X APC
3
Q
PV = ?
A
PV= BAC X PPC
4
Q
VAC= ?
A
VAC= BAC - EAC
5
Q
SPI = ?
A
EV
SPI = PV
Schedule Performance Index (SPI) is a measure of schedule efficiency on a project. It is the ratio of earned value (EV) to planned value (PV). The SPI = EV divided by PV.
6
Q
SV = ?
A
SV= EV - PV
Schedule Variance (SV) Is a measure of schedule performance on a project. It is the difference between the earned value (EV) and the planned value (PV).
7
Q
AC= ?
A
Total money spent to date.
8
Q
CPI= ?
A
_ EV_
CPI= AC
9
Q
TCPI= ?
A
(BAC-EV)
TCPI= (BAC-AC)
10
Q
CV= ?
A
CV= EV - AC
11
Q
ETC= ?
A
ETC= EAC - AC
12
Q
EAC= ?
A
BAC
EAC= CPI
13
Q
What does BAC stand for?
A
Budget at completion.
14
Q
What does EV stand for?
A
Earned value.
15
Q
What does PV stand for?
A
Planned value.