Design and Specification Flashcards
What are the U-Values for an existing and new roof?
In Part L2B, the threshold for a refurbished roof is between 0.35 and a new flat roof is 0.18.
For a new pitched roof, a u value is 0.16-0.18 dependent whether the insulation is on the ceiling (0.16) or between rafters (0.18)
Talk me through how you specified the new roof lights?
I determined the size of the aperture and the upstand detail. Was the rooflight going to be flat or would we install a dome.
What would you consider when specifying Roof Lights?
1) Part A - Structure - To install a rooflight, the roof structure will generally need to be altered to create the opening. The roof will have to be able to carry the load (weight) of the new rooflight. If the roof can not do this then it will need to be strengthened.
2) Part L - Energy Efficiency - Any rooflight that is installed will need to prove that it has sufficient insulation against heat loss i.e. is energy efficient.
Part B - Fire Safety - If the rooflight is in close proximity to a boundary, the fire performance of the rooflight will need to be considered.
What does Part L say in relation to Rooflights?
Part L provides a table showing the building type as well as the percentage of windows/doors that can be used on an exposed wall. In the same table is also makes reference to rooflights as a percentage of the area of a roof. 20% apprears to be the maximum opening areas in an extension for a rooflight.
What are some of the standards/code of practice which govern the industry?
British Standards (BS) ,
International Standard (ISO) – Quality management standards,
NHBC (National House Building Council) Standards.
BBA (British Board of Agrement)
How would you go about specifying a new roof?
1) Clients Objectives
2) Carry out research and site inspections
3) Find out more information – site surveys, trial holes etc.
4) Statutory Compliance
5) Approved installer/manufacturers guarantee/Buildability and suitability
6) Design details
What did you specify for a roof deck at Weald of Kent Science Block?
I specified 18mm WBP Ply fixed to the joists with staggered joints with 3mm between joints. Insulation on roof deck – 130mm to achieve 0.18 u value rating for roof using tapered insulation. The roof structure was designed by a Structural Engineer and this was formed from 450mm centres C24 timber joists.
What did you specify for Weald of Kent Roof Replacement?
I specified a 3 layer mineral felt system with 130mm tapered insulation to meet Part L. This required for the flat roof to have a minimum u-value between 018-0.35. This was achieved by installing 120mm tapered insulation. Timbers were installed and unexposed edge to keep insulation in place i.e. perimeter and internal gutters. Metal lined Vapour Control Layer installed to warm side of insulation.
You mentioned you requested a contractor to replace a flashing detail to RBS Bournemouth. What mortar did you specify? What flashing detail was this for? Do you know the recommended flashing heights?
Flashing was the stepped flashing above a soaker and this should be dressed up 75mm from the tiles, tucked in by 25mm and lapped by no less than 100mm.
How far should lead flashing be set into a chase?
25mm.
What is the statutory guidance used when replacing roofs?
Under Part L it states that a Major Renovation is considered to be being undertaken where more than 25% of the surface area of the building envelope undergoes renovation.
The replacement of an existing layer means either stripping down elements to the structure or replacing the waterproof membrane on a flat roof.
What roof repairs did you recommend and why did you recommend them at Merstham?
At Merstham Primary School, the school had damp patches on the lathe and plaster ceilings. I traced the cause to the base of the pitch of the roofs into the lead valleys. I recommended the replacement of the section of lead valley to provide the client for longevity as accessing the valley was quite difficult and could be quite disruptive if the school was occupied. The code of lead used was 4 as recommended by the lead sheet association.
How did you price the costs for roof repairs and prepare budgets?
I use rates from previous projects and assessed the complexities and access arrangements to determine whether the rates need be increased and apply these to the square meterage of the roof.
When specifying the roof for the school in Tonbridge, what was the build up?
The deck was concrete, so the deck was primed, VCL installed, aluminium foil tape compatible with VCL, Insultation, 3 layer mineral felt membrane (underlay, primer and torch on felt).
How did you address the ponding on the roof?
Check you drains, remove any blockages using a specialist contractor.