Contract Administration Flashcards

1
Q

What are the main principles that deem the minor works contract a suitable form of contract?

A

The front cover states 4 reasons for the appropriateness of the contract:

1. Simple in character
2. Designed by or on behalf of Employer
3. Employer provides drawings and/or     specification
4. Architect/CA administers the contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is the minor works contract not a suitable form of contract?

A
  1. Where BoQ’s are required
  2. Where provisions govern work carried out by Named Specialists
  3. Where Detailed control procedures are needed.
  4. Also not suitable where the works are of a complex nature.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Roles of the CA under the minor works contract?

A

Roles include:

- Issuing payment certs
- Valuing any variations or any work instructed in     
      respect of provisional sums
- Giving any extension to the time
   - Certifying practical completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are Liquidated Damages (LD’s)?

A

Pre-determined genuine pre-estimate of client’s loss.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you advise your client on LD’s?

A

It would have to be calculated using a formula, any random sum without substantiation may be considered by law as a penalty and this would not benefit the client in the long term.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What would happen if the LD’s stated nil and what would you advise your client if they wanted to do this?

A

It would not be wise to state nil as this means that even if the contractor delays the client cannot charge for liquidated damages. This also means there is less incentive for the contractor to complete on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What process needs to be undertaken that needs to happen to allow LD’s to be claimed?

A

To allow liquidated damages to be claimed, the contractor must be delayed beyond the completion date, the CA must issue a non-completion certificate and the client issues a pay less notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the process in relation to a late payment notice?

A

Late Payment Notice, JCT states that any late payments accrue a simple interest of 5% above the Bank of England rate. This can be dealt with between the contract. Less than £5000 debts can be dealt with in the small claims court, or adjudication could resolve in main contract. The construction act also includes provisions to promptly receive payment. The debt controllers tend to give companies a push to make payment within a specific time frame before legal action is taken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

So if LADs were then due, how were these calculated?

A

They a pre-determined genuine estimate of loss to the client in the event the contractor does not complete on time. On my project at John Adams Hall, where a bedroom could not be occupied, it was calculated by establishing the cost of putting a student in a hotel overnight.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What happens if the contractor doesn’t think the LADS in the contract are appropriate to the client’s loss but the contract has already been signed?

A

Then LD’s apply, they should not have signed up to the contract as these were already identified in the contract particulars. This should have been raised before the signing of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How would LADS be deducted from the contract?

A

LD’s are deducted by the Client issuing pay less notice to the contractor but only once a certificate of non-completion has been issued.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you assess whether an extension of time is valid?

A

I follow best practice using the RICS Guidance note on Extensions of Time. Under the JCT contract, the contractor must submit his notice for extension of time as soon as it is reasonably apparent that there is a delay. He must ensure that he makes reference to the amount of time required and mention the Relevant Event that has materially caused a delay. I then use the construction programme and assess the relevant event claim and also compare whether the works undertaken to date match the works that were meant to be undertaken. I then assess whether the delay has had an impact on the critical path. If there is an affect, I assess how much impact that has by dissecting the contract between the stages and state how many weeks need to be adjusted if they were out of the contractors control. I would then issue a certification if I felt it was due to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Talk me through the Extension of Time process? How did you determine the contractor’s application for Loss and Expense was fair and reasonable?

A

So, the contractor submitted his extension of time application to adjust the completion date. I requested for all substantial information to show what caused delay and how it affected the critical path. The contractor also confirmed the relevant event which caused the delay in line with the programme. I reviewed the construction programme and identified where the critical path was. I established that the additional stonework added additional lead time preventing the scaffold from being struck. I issued an extension of time certificate to adjust the completion date extending the liability to request liquidated damages.
The requested for justification based on the contractors tendered rates for loss and expense caused by the relevant matter – Issue of variations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

So if you did not grant extension of time in your project what happened at the end of the project?

A

If the Extension of Time was not granted, I could issue a Certificate of Non Completion which entitles the Client to claim for liquidated damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did you determine that the contractor was in delay? How and when did you determine the sectional completion was likely to be missed?.

A

Contractor confirmed in the progress meeting that they were behind schedule and it was clear from my regular site visits and comparing the progress with works undertaken on site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you assess and recommend extension of time?

A

Request information from the contractor, however the contractor is supposed to submit the claim, confirming the amount of time they think is due to them, confirming the relevant event under their claim. The CA then has 12 weeks to make the decision and assess whether the claim is warranted/justified and make an assessment themselves.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Can you name some of the Relevant Events listed under the JCT Contract Documents?

A

Exceptionally adverse weather, Civil Commotion, Variations, Access, Deferment of Possession to site, Force Majeure, CI’s in relation to provisional sums or opening up and inspection, Inaccurate Approximate Quantities, Loss or Damage by Specified Peril, Statutory power, Strikes, Impediment or prevention caused by Employer or member of the Employer project team.

EAW CC Variations A D FM CI-PS/O&T, SP S S CD

18
Q

What is float?

A

It is described as “any spare time within the programme after the time risk allowances have been included.” (spare time after time risk allowances).

19
Q

How do you deal with an Extension of Time on a Minor Works Contract?

A

Under Clause 2.7 Extension of Time is entitled to the contractor where there a delay deemed to be beyond his control.

20
Q

How then did you assess whether loss and expense was due?

A

At Daubeney Primary School, the contractor submitted a Loss and Expense claim alongside the Extension of Time claim. The contractor advised on the Relevant Matter under the JCT contract which caused a loss and or expense to the contractor.

21
Q

Can you name some of the Relevant Matters?

A

Failure to provide – Client Goods or Materials/Possession/Access; Discrepancies in contract documents; Delays in receiving instructions; Opening up works or testing works; Disruption caused by client; Inaccurate forcasting of works or approximate quantities; CDM related issues.

Failure (Client supplied Materials/Access /Posession) /Discrepancies /Delays /Disruption /Opening /inaccurate/CDM.

FDDDOI CDM

22
Q

What costs could be due if the Client was to fail to provide the Contractor with Possession?

A

Plant Hire
Stocking Charges for materials
Interest
Sub-contractor costs

23
Q

Can you explain loss and expense to me?

A

If the contractor is affected by a breach of contract, variation instructed or caused by the client that affects their ability to reasonably commence with the works, then the contractor may be due a loss and expense claim. This is the actual value caused by a relevant matter being breached and should be dealt with upon the next valuation. No retention is held on this sum of money.

24
Q

What is considered as compensation clauses within a contract?

A
  1. Loss and/or expense - compensates contractor caused by the employer
  2. Extension of time - compensates contractor for delays from employer or neutral event
  3. Liquidated damages - compensates Employer for delays post completion date when the contractor fails to complete on time.
25
Q

At Weald of Kent, how did you write sectional completion into the contract?

A

Sectional completion for Weald of Kent was written in the Contract Particulars of the JCT Intermediate Contract and completion dates were given for each section. The works were broken down into sections based on the number of elevations to be completed and sectional completion certificates can be issued for that section and Liquidated Damages can be applied to each of the sections.

26
Q

What are the effects of sectional completion?

A

Same effects of practical completion however it relates to the section only. Client takes possession, insurance is transferred, rectification period commences for that section, client releases half of the retention for that section and liquidated damages for this section cannot be claimed by client.

27
Q

How do you formally indicate practical completion? What certificate follows after practical completion certificate?

A

Issuing practical completion. This confirms that the works are a free of any patent defects and the contractor has fulfilled their obligations under the contract. After completion, the rectification period commences and making good certificate is issued at the end of this period and the contractor is responsible for rectifying any defects during this period. The CA must notify the contractor 14 days prior to the expiration of the contract, then issue the final certificate within 2 months after the expiration of the rectification period and the remaining half of retention is released.

28
Q

Can you name some other Forms of Contract other than JCT?

A

New Engineering Contract (NEC), FIDIC, Institution of Civil Engineers (ICE)

29
Q

Explain the differences between JCT and NEC?

A

The difference between the contract is:

	• CA is used in JCT whereas NEC 
         has a Project Manager
	• NEC uses more layman's terms. 
	• NEC promotes collaboration. 
	• NEC uses the Programme as a Contract 
          Document
	• NEC uses Early Warning Notices and 
          Compensation Events
	• JCT separates Extension of Time and Loss and 
          Expense
30
Q

What forms of contract do you usually use on your projects?

A

JCT Forms Intermediate and Minor Works as the projects are less complex and relatively low value.

31
Q

Can you name some of the other JCT Suites?

A

Design and Build, Standard Form (with or without quantities), Major Projects.

32
Q

What type of works is an NEC contract used for?

A

Used for procuring a diverse range of works, services and supply projects, spanning major works through to minor works and the purchasing of goods and materials.

33
Q

What are the advantages of using NEC?

A

Designed to 1) stimulate good management 2) used in a wide variety of commercial situations 3) They are clear, simple and written in plain English. 4) Improve collaboration.

34
Q

What is the FIDIC contract?

A

It is an engineering contract. The different suites are yellow (D+B), silver (Turnkey), Green (Short Form), White (Client/Consultant Agreement).

35
Q

What was one of the main changes to the JCT Contracts from 2011 to 2016?

A

CDM Regulations Change (Principal Designer) and Insurance provisions

36
Q

Do you know what the recommended JCT project totals they recommend for each of their types of contracts?

A

They do not base the contract on value anymore, they base it on the complexity of the project.

Minor Works Building Contract
Intermediate Building Contract
Standard JCT Building contract
Major Works Building Contract

Low complexity, minor structural works
Medium complexity, structural works
High complexity with structural works
High complexity with structural works

up to C250,00
Up to 1 million
Over 1 million
Over 10 million

37
Q

What Guidance Notes do the RICS offer for Valuations?

A

Interim Valuations and Payment, 2015.

It covers:

* conditions of contract
* payment mechanisms
* retention
* valuation process
* standard forms and covering letter
38
Q

How would you undergo an interim valuation?

A
  1. Review work on site on or after IVD, review contractors application if issued.
  2. Check works executed, variations/changes to contract and expenditure of provisional sums.
  3. Works executed includes fixed building materials and also includes preliminary costs expended to date.
  4. Issue certificate confirming the gross and net amount due to the contractor within 5 days of the due date.
39
Q

What are the purposes of certification?

A

A) To record an event – as in the case of a practical completion certificate, a certificate of making good and a final certificate.
B) A financial statement – as in the case of interim certificates, payment notices and pay less notice

40
Q

Under the JCT Intermediate Contract, if the contractor fails to submit a valuation, what is the process?

A

In cases where the contractor has failed to submit an interim application for payment by the due date, it is essential that the contract administrator makes an interim valuation for the purpose of an interim certificate.

41
Q

What happens if you fail to issue a Interim Certificate five days after the due date?

A

The interim application shall become an interim payment notice. Or if the contractor has not made an application, then they are entitled to issue a payment notice showing the gross with the deductions to form the net valuation.

42
Q

How do you avoid disputes in construction projects?

A

Record keeping. Pre-contract: allocate risk efficiently – ensure liabilities on risk are shared evenly on the contract, Post-contract: follow the contract, Communication, dealing with changes to the build programme, keep good records, Stick to payment terms