Design And Spec Flashcards
What are preambles?
certain specification for how the job is to be done.
Explanation of document/process
an explanation of a document, commonly found in contracts, specficiations and bills of quantities. It can help with the interpretation of the document. A preamble might include a description of the parties to the contract, the background of the document, the objectives of the project etc.
What is a performance Spec?
An open spec with brief requirements
What is an output spec?
List of client requirements, can be a design and build
What is novation?
Where the contractor takes an architect from the client and appoints them.
What is a collateral Warranty?
Gives recourse for parties not involved in the main contract but may be affected. i.e a third party.
What is a latent defect?
A fault that couldn’t have been discovered with a thorough survey at the time
What is an Extension of Time?
Allowance in the contract for a contract completion date to be adjusted if there was a delay that was not the contractors fault.
What is a Relevant Event?
An event that causes a delay to the completion date, which is either caused by the client or is a neutral event not caused by either party.
Name some examples of a Relevant Event?
Variations
Exceptionally Adverse Weather
Civil Commotion or terrorism
Failure to provide information
Delay on the part of a nominated sub-contractor
Statutory undertakers work
Delay in giving contractor possession of the site
Force Majeure
Loss of specified peril, such as flood.
The supple of materials and goods by the client.
National Strikes
Changes in statutory requirements.
Delays in receiving permissions that the contractor has reasonable steps to avoid.
What is a provisional sum?
An allowance for a specific element of works that is not yet defined in enough detail for tenderer s to accurately price.
Which RIBA stages are pre-contract?
0-4
When do post contract stages start?
After the contract has been signed not at PC.
What are the RIBA stages of Work?
0 - Strategic Definition 1 - Preparation and Brief 2 - Concept Design 3 - Developed Design 4 - Technical Design 5 - Manufacturing and Construction 6 - Handover and Completion 7 - Use
Tell me about H&S regs and how they impact on design?
refer to CDM & Surveying safely guidance
What does intuitive mean?
User friendly
What is a designers risk assessment and how do you do it?
used to manage risks during the build phrase
Identify risk and put things in place to manage/reduce
Measured by likelihood/impact
Why are reputable manufacturers & contractors useful when designing
Early Involvement - guarantees and warranties
Buildability
Better understanding of risk management
Aware of conflics of interest
Can you name any manufacturers/products you use?
IKO, Bauder, Sika etc
When have you given advise on sustainability issues on a project?
SIP on Caistor BREEAM EPC Any others? Part L
What is the definition of embodied energy?
How much energy is used to make a product
What is a specification and how do you product one?
Pre-sambles, prelims and shcedule of works
PCIP
Drawings
It’s something the contractors work to to build something
What does NBS Stand for?
National Building Specification
What trade associations can help with design and spec?
TRADA NHBC LEAD SHEET ASSOCIATION Blue Book Mastic Asphalt Council Concrete Society Concrete Repair Association Concrete Block Association IEE (Electrical) FENSA BREEAM NIC/EIC Metal cladding and roofing association
Whats the difference between a prescriptive and performance specification?
Performance spec is a set of standards where the contractor then recommends a product/does the prescriptive spec
Prescriptive spec is what we do. Detailed specification with products.