CVCS (BAST, Makeup, and Transfer System) Flashcards

1
Q

BASTs

A
  • 2 tanks

- TRM requirement to have enough boric acid to borate to cold shutdown (>3080gal, 20,000-22,500ppm,>145F)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A Boric Acid Transfer Pump, and 2 immersion heaters for each Storage Tank.
Power supplies?

A
  • Tank A- MCC-5

- Tank B-MCC-6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Modes of operations

A
  • Automatic
  • Borate
  • Dilute
  • Alternate Dilute
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

MOV-350

Emergency Boration Vlave

A
  • Powered by MCC-5
  • Lines up BA pump directly to Charging Pump suction for Emergency Boratian
  • normally 65gpm
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Heat Tracing power supplies and why?

A
  • ITS min temp is 145F, boric acid starts to solidify

- Powered by MMC-6 or 5 (Primary/Secondary)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Boric acid filter

A
  • Located in CCW pump room
  • Max dp is 20psid
  • can be bypassed for cartridge replacement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Batching tank and acid blender

A
  • 2 floor aux building batch tank
  • Blender promotes mixing of boric acid solution and primary water, shortens the pipe length required to homogenize the mixture. Located in CCW pump room
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Primary Water Pumps

A
  • A-MCC-1

- B-MCC-2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly