CPM & PERT; Cost-Effective Analysis Flashcards
Details of Critical Paths
Activity
Predecessor
Duration
Defined as the difference between the Latest Start and Earliest Start.
Slack or Total Float
TRUE or FALSE
When an activity has zero Total Float, Free Float will also be zero.
True
TRUE or FALSE
Activities with zero Total Float are on the Critical Path
True
A type of bar chart used in scheduling of activities.
Gantt Chart
Uses 3-time estimates
Program Evaluation Review Technique (PERT)
2 Types of Float or Slack
Total Float
Free Float
To compute a __________, the effectiveness is divided by the cost of a given alternative.
_____ = E/C
Effectiveness-Cost Ratio
Is for those times when you are pretty sure about the duration of each task.
Critical Path Method (CPM)
Weighing costs and benefits when benefits are not measured in terms of money.
Cost-Effectiveness Analysis (CEA)
Is the spare time available when all preceding activities occur at the earliest possible times and all succeeding activities occur at the earliest possible times.
Free Float
2 of the most important assumptions made by PERT
- The Beta distribution is appropriate for calculation of activity durations.
- Activities are independent, and the time required to complete one activity has no bearing on the completion times of it’s successor activities in the network. The validity of this assumption is questionable when we consider that in practice, many activities have dependencies.
Is the spare time available when all preceding activities occur at the earliest possible times and all succeeding activities occur at the latest possible times.
Total Float
3 Time Estimates of PERT
A - Optimistic Time
B - Pessimistic Time
M - Most Likely Time
Is used in more uncertain situations.
Program Evaluation Review Technique (PERT)