CPM & PERT; Cost-Effective Analysis Flashcards

1
Q

Details of Critical Paths

A

Activity
Predecessor
Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Defined as the difference between the Latest Start and Earliest Start.

A

Slack or Total Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

TRUE or FALSE

When an activity has zero Total Float, Free Float will also be zero.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

TRUE or FALSE

Activities with zero Total Float are on the Critical Path

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A type of bar chart used in scheduling of activities.

A

Gantt Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Uses 3-time estimates

A

Program Evaluation Review Technique (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

2 Types of Float or Slack

A

Total Float

Free Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

To compute a __________, the effectiveness is divided by the cost of a given alternative.

_____ = E/C

A

Effectiveness-Cost Ratio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Is for those times when you are pretty sure about the duration of each task.

A

Critical Path Method (CPM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Weighing costs and benefits when benefits are not measured in terms of money.

A

Cost-Effectiveness Analysis (CEA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Is the spare time available when all preceding activities occur at the earliest possible times and all succeeding activities occur at the earliest possible times.

A

Free Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

2 of the most important assumptions made by PERT

A
  1. The Beta distribution is appropriate for calculation of activity durations.
  2. Activities are independent, and the time required to complete one activity has no bearing on the completion times of it’s successor activities in the network. The validity of this assumption is questionable when we consider that in practice, many activities have dependencies.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Is the spare time available when all preceding activities occur at the earliest possible times and all succeeding activities occur at the latest possible times.

A

Total Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

3 Time Estimates of PERT

A

A - Optimistic Time
B - Pessimistic Time
M - Most Likely Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Is used in more uncertain situations.

A

Program Evaluation Review Technique (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project management techniques, which have been created out of the need of Western industrial and military establishments to plan, schedule and control complex projects.

A

CPM (Critical Path Method) and PERT (Programme Evaluation Review Technique)

17
Q

Is designed to compare the costs and effects of two or more alternatives with similar objectives.

Ex: Number of lives saved per peso/dollar spent on alternative cancer treatments

A

Cost-Effectiveness Analysis (CEA)

18
Q

The longest time path through the network.

A

Critical Path

19
Q

An analysis tool used for some programs, projects and policies, wherein the benefits are not directly measured in terms of money either because no monetary values have been estimated or because the analyst cannot or will not use monetary values to measure the benefit.

A

Cost-Effectiveness Analysis (CEA)

20
Q

To compute a __________, the cost of a given alternative is divided by effectiveness:

_____ = C/E

A

Cost-Effectiveness Ratio

21
Q

Challenges in using Cost-Effective Analysis (CEA)

A
  1. Linking objectives and effectiveness
    • Reliability
    • Validity
  2. Intermediate vs final outcomes
    • Lack of data
    • No proper measures
    • Hypothesize link between intermediate and final outcomes
    • Use secondary source to establish link
  3. Dealing with multiple outcomes
    • Conduct a separate CEA for each measure of effectiveness
    • Present results of each CEA and clearly describe the relevant tradeoffs
    • Conduct Cost-Utility Analysis
  4. Distribution effects
    • Ignore uneven distribution (“average”)
    • Calculate separate estimates of effectiveness for each group
    • Average the effectiveness measure for a number of groups into a single summary measure
22
Q

________ or Network Analysis as the technique is sometimes called, developed along two parallel streams, one industrial and the other military.

A

CPM/PERT

23
Q

Advantages of Cost-Effective Analysis (CEA)

A
  • Avoids some of the most controversial issues in Cost-Benefit Analysis, such as measuring the benefits of saving a life in monetary terms.
  • Where direct comparisons of the effects of different policies are possible, CEA can provide some easily understandable and persuasive evidence.
24
Q

It compares costs per unit of benefit of alternative programs.

A

Cost-Effectiveness Analysis (CEA)

25
Q

Uses 1-time estimate

A

Critical Path Method (CPM)

26
Q

TRUE or FALSE

Programs with different objectives will have entirely different indicators of effectiveness, so they CAN be readily compared with the CE framework.

A

FALSE - “CANNOT”

27
Q

Is calculated by

Due date minus Expected date

A

Z-score

28
Q

Is one of two ways or tools to identify the paths through your project.

A

Critical Path Method (CPM)