Cost Formulas Flashcards

1
Q

Actual Cost (AC) (ACWP)

A

Represents the current amount actually spent on the project or during a particular time period

FORMULA => The addition of actual expenses to date, or during a particular time period on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value (EV) (BCWP)

A

Represents the current amount of work (product) completed during a particular time period, regardless of cost or time.

FORMULA => The percent complete of each activity multiplied by the planned value (PV) of the activity during a particular time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Planned Value (PV) (BCWS)

A

Represents the current amount that should have been spent on the project during a particular time period.

FORMULA => The addition of all work that should have been completed to date or during a particular time period on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget at Completion (BAC)

A

Represents the total budget projected for the project. Also is the sum of all planned value (PV).

FORMULA => The total amount originally (or approved revision) expected to be spent on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Performance Index (CPI)

A

Represents the current efficiency of spending on the project. Less than 1.0 is bad, greater than 1.0 is good, and 1.0 is on track.

FORMULA => CPI = EV /AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Variance (CV)

A

Represents the difference between what you have accomplished and what you have spent.

FORMULA => CV = EV- AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Performance Index (SPI)

A

Represents the current efficiency of progress on the project. Less than 1.0 is bad; greater than 1.0 is good; 1.0 is on track.

FORMULA => SPI = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Variance (SV)

A

Represents the difference between what you have accomplished and what it should have taken to do it.

FORMULA => SV = EV- PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

To Complete Performance Index (TCPI)

A

Represents the efficiency needed from the remaining resources to meet the cost goals of the project.

FORMULA => TCPI = (BAC-EV)/(BAC-AC) or (BAC-EV)/(EAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion (EAC)

A

Represents the current total project cost based on the current efficiency (CPI) of project spending.

FORMULAS => EAC=BAC/CPI
or EAC=BAC/Cumulative CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate at Completion (EAC) using a new estimate

A

Represents the actual cost (AC) to date plus a new ETC.

FORMULA => EAC = AC +ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate at Completion (EAC) using the remaining budget

A

Represents the budget needed to complete the remaining work plus the actual cost (AC). The budget needed to complete the remaining work is the budget at completion (BAC) minus the earned value (EV).

FORMULA => EAC = AC + BAC-EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimate at Completion (EAC) using CPI

A

also EAC = AC + BAC - EV EAC = EAC = $43,477 = $7,000 +
Represents the budget needed to complete the remaining work plus the actual cost (AC). However, the budget required to complete the remaining work is adjusted by a performance factor, very often CPl.

FORMULA => EAC=AC+(BAC-EV)/(CPIxSPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate to Complete (ETC)

A

Represents the current total project cost REMAINING to be spent, based on the current efficiency (CPI) of project spending.

FORMULA => ETC= EAC- AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Variance at Completion (VAC)

A

Represents the difference between the BAC completion and EAC.

FORMULA => VAC = BAC- EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Present Value (PV)

A

Shows the amount of money needed now at the interest rate (r) for a desired future outcome (FV) over a number of periods (n).

FORMULA => PV=FV/(1+r)^n

17
Q

Future Value (FV)

A

Shows the amount of money in the future at the set interest rate (r) for an amount of money (PV) now over a number of periods (n).

FORMULA => FV=PV x (1+r)^n

18
Q

PERT (could be considered a three-point estimate)

A

Ce = (Co + 4Cm + Cp)/6