Cost Estimation Flashcards

1
Q

What is the purpose of cost estimation?

A
  • project viability
  • option comparison
  • funding approvals
  • cost control
  • programming/ cashflow
  • financial planning
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are different phases of cost estimates?

A
  • feasibility estimate (FE)
  • Option estimate (OE)
  • Scheme Estimate (SE)
  • Pre-design estimate (PE)
  • Design estimate (DE)
  • Construction Estimate (CE)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the accuracy of cost estimates in concept stage?

A

50%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the accuracy of cost estimates in pre-feasibility stage?

A

30%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the accuracy of cost estimates in feasibility stage?

A

25%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the accuracy of cost estimates in preliminary design stage?

A

20%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the accuracy of cost estimates in detailed design

A

15%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Capital cost estimate - CAPEX

A
  • land acquisition
  • pre-feasibility studies
  • resource consent
  • investigations
  • design
  • consents + fees
  • construction
  • supervision
  • insurance and taxes
  • construction overheads
  • inspections, testing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Design fees are dependent on…

A

project complexity, site constraints, number of options assessed, field investigations, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Stages of design, where fees are present:

A
  • concept
  • pre-feasibility
  • feasibility
  • preliminary
  • detailed design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Examples of field investigations:

A
  • geotechnical investigations
  • geological
  • topographical survey
  • contaminated site
  • hydrological
  • water quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Approvals needed for

A
  • resource consents (technical studies, consent hearing, environment court, management plans)
  • property owner conditions of access
  • legal fees
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

General items on a construction cost estimate “bill of quantities”

A
  • P&G
  • mobilisation
  • management plans and submittals
  • misc
  • demobilisation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Specific items on a construction cost estimate “bill of quantities”

A
  • earthworks quantities
  • concrete volume
  • pipes
    etc
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Operating cost estimate - OPEX may include

A
  • operator fees
  • power supply
  • maintenance contracts
  • materials
  • administration
  • annual reporting
  • monitoring
    etc
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is net present value NPV?

A

The present value of a project based on projected future cash inflows discounted back to current day rates compared to current investment - discounted back to current day rates

17
Q

Explain an engineers estimate:

A
  • based on bill of quantities
  • rates based on experience/ similar jobs and reference materials
  • may use an independent QS
18
Q

What factors would a contractor consider for a earthworks construction cost estimate tender price?

A
  • haul distance
  • machine type
  • machine numbers
  • time of year
  • site commute
  • grade
19
Q

What factors would a contractor consider for a materials construction cost estimate tender price?

A
  • standard size
  • lead time
  • delivery cost
  • machinery needed to install
  • labour to install
20
Q

What is the difference between construction cost estimate and tender price?

A
  • contractors margin
  • risk assessment
  • hunger for the job…
  • speciality/ efficiencies not identified by the engineer
  • supplier relationship
21
Q

What are some weighted attributes of a tender evaluation?

A
  • relevant experience and track record
  • organisational structure
  • resources
  • programme
  • price
22
Q

What changes the actual construction cost?

A
  • unforeseen ground conditions
  • extreme weather
  • design inconsistencies
  • supplier delays
23
Q

What is financial risk assessment?

A
Probablistic cost estimation
- what are the risks to the project
- how do these relate to cost
- what is the likelihood of each risk
Accounts for project risks, cost of risks and probability
24
Q

Project cost elements included:

A
  • land purchase/ easement
  • resource consents
  • field investigations
  • design
  • construction
  • regulatory fees