Cost Estimation Flashcards
What is the purpose of cost estimation?
- project viability
- option comparison
- funding approvals
- cost control
- programming/ cashflow
- financial planning
What are different phases of cost estimates?
- feasibility estimate (FE)
- Option estimate (OE)
- Scheme Estimate (SE)
- Pre-design estimate (PE)
- Design estimate (DE)
- Construction Estimate (CE)
What is the accuracy of cost estimates in concept stage?
50%
What is the accuracy of cost estimates in pre-feasibility stage?
30%
What is the accuracy of cost estimates in feasibility stage?
25%
What is the accuracy of cost estimates in preliminary design stage?
20%
What is the accuracy of cost estimates in detailed design
15%
Capital cost estimate - CAPEX
- land acquisition
- pre-feasibility studies
- resource consent
- investigations
- design
- consents + fees
- construction
- supervision
- insurance and taxes
- construction overheads
- inspections, testing
Design fees are dependent on…
project complexity, site constraints, number of options assessed, field investigations, etc
Stages of design, where fees are present:
- concept
- pre-feasibility
- feasibility
- preliminary
- detailed design
Examples of field investigations:
- geotechnical investigations
- geological
- topographical survey
- contaminated site
- hydrological
- water quality
Approvals needed for
- resource consents (technical studies, consent hearing, environment court, management plans)
- property owner conditions of access
- legal fees
General items on a construction cost estimate “bill of quantities”
- P&G
- mobilisation
- management plans and submittals
- misc
- demobilisation
Specific items on a construction cost estimate “bill of quantities”
- earthworks quantities
- concrete volume
- pipes
etc
Operating cost estimate - OPEX may include
- operator fees
- power supply
- maintenance contracts
- materials
- administration
- annual reporting
- monitoring
etc