Contractors Perspective Flashcards
1
Q
What are 2 types of risk?
A
- holistic risks
- contract and site specific risks
2
Q
What is holistic risk?
A
A risk that could affect any project but none the less needs considering as to how your team will address (e.g. rising market, pressurised supply chain)
3
Q
What is holistic risk?
A
A risk that could affect any project but none the less needs considering as to how your team will address (e.g. rising market, pressurised supply chain)
4
Q
Concept:
A
- agreed design brief
- agree roles and responsibilities
- agree programme and approvals
- options studies report
- costing on a m^2 basis, etc
- consider environmental matters
- approved design goes to project information memorandum to identify risks and consequence issues
- concept schedule of materials and finishes
5
Q
Preliminary:
A
- consult with T/A re acceptable solutions and contentious issues
- documentation for a resource consent
- schedule of areas and design features
- overall site plan
- define assumed construction method
- highlight projects risks
6
Q
Developed:
A
- confirm compliance with all relevant rules
- co-ordinate between all parties
- elemental cost estimates
- defined scope of elements
- schedule of finishes
- review and revise programme
7
Q
Things to consider when staging a project.
A
- is it a realistic programme
- is there a period of high risk change over
- communicate the staging with simple illustrations
8
Q
Key items of Forsyth Barr Stadium
A
- Early contractor involvement (ECI)
- programme and planning
- steel
- the pitch