Cost Control Flashcards

1
Q

What are the three dimensions of project delivery

A

Time
Quality
Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Elements of construction schedule

A

Time
Resources
Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A construction schedule must include the following

A

Time for each element of the construction (cladding, services, superstructure)
Resources needed in labour
Resources needed in materials
Costs of each of these elements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is scheduling

A

Initiated from the work scope, by breaking each element of the project down in WBS and each part of that by decomposition into work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is activity sequencing

A

Logical relationships
Leads and lags
Precedence diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are analogous estimates

A

Last time we did the same thing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is a parametric Estimate

A

Quantity of work times the unit rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the main objective of construction schedule

A

Developing a detailed construction strategy that is properly sequenced and resourced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Time related causes of errors

A
Erroneous budget perception 
Inadequate budget backup
Inadequate cost checking 
Historical cost reporting
Late reports
Time overrun 
Decision delays
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are delaying factors for a project

A
Unavailable site
Late instructions 
Variation orders
Late approvals 
Design changes
Latent conditions 
Supplies
Acts and regulations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does PERT chart stand for

A

Program Evaluation Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of a PERT chart

A

It is required to show the start and finish dates of all the activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How much of the project cost is in the construction phase of the asset life

A

20% of the project life cycle is in construction the rest is maintenance and operation costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly