Contracts Flashcards

1
Q

What are the elements of a contract

A
Capacity
Intention (5 days cooling off)
Agreement (Offer - Acceptance)
Consideration 
Operation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When does a contract legally have to be in writing according to the Building Services Act 1991

A

If the building work is more than $10,000 before building work has start or if the contract is less than $10,000 before building work is finished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What must the building contract state

A
The scope of the work
When work will be completed 
The amount paid 
The retention amounts and securities
The name of the contractor
Licence number of the contractor
The address of the building work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Best value of procurement

A

Best value requires that organisations operate effectively and efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a generic procurement process (six principal activities)

A

The establishment of what is to be procured
A decision on strategies
The seeking tender offers
Evaluation on offers
Award of the contract
Administration and compliance of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Fixed Price Contract

A

Risk is to the contractor

If cost overrun quality may be reduced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule of Rates/ Fixed Price

A

Final Price not known
Variations easily implemented
Contractor risk of price changes
Delay Issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are some elements of cost Plus Contracts

A
Fixed percentage
Time incentives
Variable Percentage 
Target Estimate
Scope is not known
Risk to owner
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Elements of a Construction Management Contract

A
AS 4916-2002
Project Manager
-Design
-Construct
-Deliver
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Difference between hard and soft risks in contracts

A

Hard - Risks are allocated

Soft - Risks are shared

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Build Own Operate Transfer

A

A single organisation designs, builds, funds and operates for a period of time before transferring ownership to an agreed party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does AS 2124 Cover

A

General Conditions of Contract

  • Variations
  • Liquidated Damages
  • Interest
  • Defects Liability Period
  • Dispute Resolution
How well did you know this?
1
Not at all
2
3
4
5
Perfectly