Construction Risk Management Flashcards

1
Q

What are the 8 distinct phases of the Phyrr Pyramid

A

Ground Floor (Inception)
Loan Commitment
Interim Stage
Tenancy

Absorption
Maturing Process
Aging Process
Demise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Elements of the interim stage

A

Design and construction commence

Consequences for the life of the building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does risk management require

A

Accurate Data

Adequate resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is risk management

A

Risk management is the process of systematically identifying an organisations risks and analylsing them in terms of their likely and potential consequences in order to make informed decsions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 7 types of project risk

A
Financial 
Physical 
Contractual 
Perceptual 
Statutory 
Managerial 
Time Delays
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the structured approach to risk management

A

Analyse potential risk
Devise repose (prevent, transfer, mitigate, accept)
Implement response

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the risk management process

A
Familiarization 
Analysis 
Response
Report
Implement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is involved in the familiarization element of risk management process

A

Nature of project and objectives
Stakeholder requirements
Success criteria
Major project elements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is involved in the analysis element of risk management process

A

Identify (List factors)
Assess (likelihood, consequences)
Rank (matrix or scoring)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is involved in the response element of risk management process

A

Prevent
Mitigate
Transfer
Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is involved in the report element of risk management process

A

Document

Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the 8 risk management constraints

A
Invincibility 
Fear
Over caution 
Paralysis by analysis 
Negativity 
Resources
Continuity 
Culture
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are some objective (hard) Key Performance Indicators

A
OH & S 
Quality Training
Productivity
Asset Performance
Industrial Relations 
Environmental 
Time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are some subjective (soft) Key Performance Indicators

A
Quality of service providers management
Owner/Customer satisfaction
Level of innovation 
Commitment & responsiveness of provider
Communication
Change of culture
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are construction safety plans

A
Principal contractor must prepare CSP before construction work starts. 
Must state: 
Address
Name and address of principal contractor
ABN
WHS Committee
Start date 
Duration 
Type of construction 
Rules
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When is a work method statement required

A
High risk activities such as:
Entering a trench over 1.5m
Explosives
Confined Space
Hazardous Substance
Falling hazards