Contracts I - Remedies - Cases Flashcards

1
Q

In Spang Industries, Fort Pitt Bridge Division v. Aetna Casualty & Surety Co. (1975), the key issue in the case was whether Torrington could recover damages resulting from Fort Pitt’s delayed delivery of steel. The main issue revolved around general or special damages (Hadley definition). What was the reason that led the court to decide that Torrington could recover?

A

Two points.

First, the counterparty argued that Torrington’s damages were “special” or “consequential,” meaning they were not reasonably foreseeable to them at the time of contract formation. The court disagreed. The court found that they were general damages and they should have reasonably anticipated the sequence of work in the construction project.

Second, Torrington acted in good faith to mitigate the damages by organizing a subcontractor that would offload the material when the counterparty failed to organize a subcontractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When considering the avoidability (mitigation), is it sufficient that the plaintiff has taken steps to mitigate the damages?

A

One cannot recover damages that one could have avoided without
undue expense, undue hardship or risk, or undue humiliation.

I would argue that they also need to be in good faith (Spang Industries v. Aetna).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

For damages, if the damages suffered do not flow from the breach, what must be done?

A

If the damages suffered do not flow from the breach, then it must be established that special circumstances giving rise to them should reasonably have been anticipated at the time the contract was made.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How would you define general damages?

A

General damages, also known as direct damages, are damages that flow directly from a breach of contract, and they are presumed to arise naturally from the breach. General damages are recoverable if they are a direct and foreseeable result of the breach.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which case established the foundational principles governing the recovery of both special and general damages in contract law?

A

Hadley v. Baxendale

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

To recover special damages, the injured party must demonstrate what?

A

That these damages were in the contemplation of both parties at the time the contract was formed or that the breaching party had knowledge of the special circumstances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In construction projects, is it foreseeable that when I don’t do the work, that someone else would have to do it? For what kind of damages would that speak?

A

Yes. General damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In Spang Industries, Fort Pitt Bridge Division v. Aetna Casualty & Surety Co. (1975), the key issue in the case was whether Torrington could recover damages resulting from Fort Pitt’s delayed delivery of steel. One of the key questions was at what time the breaching party must have had foreseeability. Original contract stated “delivery mutually agreed upon”. There were subsequent delivery dates afterwards. When does it have to be foreseeable?

A

Court says when you reached an agreement on the date. The relevant point in time is not the signing of original contract. It was the agreement on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If there is no agreed price in a contract, what would a court likely find?

A

A reasonable price. Fair market price at time and place of delivery. That is a reasonable price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In Hadley v. Baxendale (1854), the plaintiffs, who ran a milling business, needed a new crankshaft for their mill and hired the defendants, Pickford & Co., to transport the broken crankshaft to a manufacturer for a replacement. The plaintiffs explicitly informed the defendants about the urgency of the delivery and were promised a swift delivery if the crankshaft was handed over by noon. However, despite collecting the crankshaft on time, the defendants failed to deliver it promptly, resulting in the plaintiffs incurring financial losses due to extended downtime of their mill. Why were no damages awarded to Hadley for the loss of profits?

A

The court concluded that the loss of profits in this case could not reasonably be considered a consequence of the breach that both parties could have contemplated when making the contract because the special circumstances (causing the delay) were never communicated to the defendants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In Simard v. Burson (2011), Simard made the highest bid of $192,000 at a foreclosure sale, but he did not proceed to settlement. The property was then resold to Zimmerman for $163,000, who also failed to go to settlement. A second resale occurred, which was completed at $130,000. What damages could Burson (seller) claim? What did he receive? What measure of damages is this?

A

Only the difference between 192 k and 163 k.
The court held that Burson could not recover the difference between 192 k and 130 k because there lacked causation. Simard did not cause the fault of Zimmerman.
Expectancy (as if the contract had been performed).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In Simard v. Burson (2011), Professor Corbin mentioned the “Uniformity of Sequence” in his reference to the Restatements. In what context?

A

Professor Corbin is emphasizing that causation in the context of legal disputes is based on the concept of foreseeability, which, in turn, relies on the degree of uniformity of sequence between events. He suggests that causation is established when there is a consistent and predictable relationship between two events, allowing for a reasonable prediction of one event following another based on past experiences and observations. This uniformity of sequence is a key factor in determining whether an event can be considered the cause of another event in legal proceedings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

According to Professor Corbin’s reference to the Restatements, how are foreseeability and causality connected to the Uniformity of Sequence?

A

Corbin’s statement that causation is determined by foreseeability, based on uniformity of sequence in experience, aligns with the principles outlined in the Second Restatement. This indicates that the Second Restatement is a valuable resource for understanding how causation is established in contract law. However, the Professor believes that causation has more to do with avoidability (mitigation).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

§ 351(3) RESTATEMENTS highlights that courts have the authority to limit damages for foreseeable loss in order to ensure justice in certain circumstances. Such circumstances are disproportionality and informality of dealing. What is disproportionality and informality of dealing?

A

In the context of the Second Restatement of Contracts, “disproportionality” refers to a situation where the amount of damages awarded to a party might be considered excessive or unfair when compared to the actual harm or loss suffered. This means that if the damages awarded by a court appear to greatly outweigh the actual damage incurred, the court can limit or adjust the damages to ensure a fair and just outcome.

“Informality of dealing” refers to contractual situations where the parties involved have not established their rights and obligations through a formal, written contract. In such informal dealings, the terms and conditions of the agreement may not be clearly spelled out in a detailed contract. This informality can affect how damages are determined in case of a breach of contract, and courts may have more flexibility in assessing damages when a formal written contract is absent. This include the absence of a written contract allocating the risk to parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In measuring damages, what is the “usual rule”?

A

The “usual rule” in contract law, as mentioned in “Foster v. Bartolomeo,” is a principle that governs the calculation of damages when a contract is breached. According to this rule, when a breach of contract occurs, the injured party (the plaintiff) is typically entitled to recover the difference between the contract price and the market price of the subject matter of the contract at the time of the breach.

In simpler terms, if one party breaches a contract, and the item or service covered by the contract is now more expensive or less valuable in the open market, the injured party can claim damages equal to the financial loss they suffered due to the breach (hence, expectancy). This measure of damages aims to put the injured party in the position they would have been in if the contract had been fully performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In Cricket Alley Corp. v. Data Terminal Systems, Inc. (1987), the courts awarded consequential (special) damages to the plaintiff (Hadley definition). Why would it be beneficial to plaintiffs to recover special damages instead of general damages?

A

Higher Compensation: Special damages are typically more extensive and can cover losses beyond the immediate and direct consequences of the breach. They can include specific economic losses, lost profits, additional expenses, or other consequential harm directly resulting from the breach. Recovering special damages allows plaintiffs to seek compensation for a broader range of losses, potentially resulting in a higher overall award.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In Cricket Alley Corp. v. Data Terminal Systems, Inc. (1987), the court also discussed the requirement of certainty of damages. What did the court say and why was the certainty of damages requirement fulfilled?

A

The court emphasized that under the UCC, damages need not be proven with mathematical precision. Instead, they must be reasonable under the circumstances. In this case, evidence including employee payroll records and testimony about additional labor costs incurred due to the failure of the DTS equipment to perform satisfactorily supported Plaintiff’s claim for damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Under the UCC, what can buyers do when they receive the goods but they have non-conformities?

A

Notify the seller of any non-conformity within a reasonable time after discovering it. If the buyer has accepted the goods and provided the required notice of non-conformity, they are entitled to recover damages for the non-conformity. Damages are essentially compensation for the harm or losses suffered due to the seller’s breach of contract (expectation damages).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Contract price vs. market price idea

A

Buyer: Cover price – contract price (basic remedy) [cover price = market price]
Seller: Contract price – resale price (basic remedy) [resale price = market price]

For buyer, no injury unless the price goes up.
Seller is the opposite, price goes up, the seller is happy. If the price goes down, there is an injury. Look at it from opposite directions. There is no injury if the price moves up.

The basic premise in opposite directions. Market price differential formula. Different formula depending on if the injured party is buyer or seller.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The Drews Co. v. Ledwith-Wolfe Associates, Inc. (1988) discussed a case where a contractor, after disputes and delays, withdrew from a construction project. The owner wanted to establish a restaurant. What damages did both parties claim?

A

Constructor: Restitution (backwards) as if no contract. For the work done.

Owner: Expectancy (forwards). Wanted to claim the lost profits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The Drews Co. v. Ledwith-Wolfe Associates, Inc. (1988): Lost profits and “new business rule”. What does the Restatements say about claiming lost profits from new businesses? What are the requirements?

A

RESTATEMENT (SECOND) OF CONTRACTS § 352, at 146 (1981) (proof of lost profits “may be established with reasonable certainty with the aid of expert testimony, economic and financial data, market surveys and analyses, business records of similar enterprises, and the like”).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the difference between fact of loss and amount of loss?

A

Breaching party should not take advantage of breach. Courts make a distinction between fact of loss and amount of loss. More proof is required for fact of loss than amount of loss. In cases of breach of contract, the burden of proof is typically on the non-breaching party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The Drews Co. v. Ledwith-Wolfe Associates, Inc. (1988): Before this case, what was the “hard rule” on new businesses?

A

Hard rule: New businesses could not recover. Was treated as an absolute rule. If you can prove, with reasonable certainty, you can recover but it’s going to be difficult to prove. Wolfe was not able to prove what their loss was.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The Drews Co. v. Ledwith-Wolfe Associates, Inc. (1988): The injured party (owner) who wanted to establish a restaurant claimed lost profits. Lost profits were deemed recoverable consequential damages, but the challenge was determining the certainty of such profits. What are consequential damages? (Hadley definition). Can lost profits only be claimed under consequential damages?

A

They are special damages.

The UCC “Hadley” rule is mentioned in the context of distinguishing between general and special damages in contract law:
1. General Damages: General damages are those that a reasonable person would foresee as a natural consequence of a contract breach at the time the contract was made. These damages are considered typical and do not require special notice. The UCC recognizes general damages as recoverable.
2. Special Damages: Special damages, on the other hand, are damages that a party would not have reason to foresee as a natural consequence of the breach unless they were notified of specific circumstances at the time of contract formation. To recover special damages, the party seeking them must show that the other party had knowledge of the unique circumstances that would lead to these damages.

No. “Consequential” damages are often equated with lost profits which are assumed to be “special” damages. It is, however, clear that lost profits are recoverable as general damages (which a reasonable person is presumed to know without any special notice) where they flow directly and immediately from the breach of contract. (p. 642).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Where do we find the expression “consequential damages” in UCC?

A

UCC § 2-715(2)(a): This section allows the buyer to recover consequential damages resulting from the seller’s breach of contract. Consequential damages are recoverable only if the seller had reason to know about them at the time of contracting (either general or special). These damages must be foreseeable, and the seller’s breach must have caused them.

Under the UCC, consequential damages are damages resulting from the seller’s breach including (a) any loss resulting from requirements and needs of the buyer of which the seller had reason to know at the time of contracting and which could not reasonably be prevented by cover or otherwise; and (b) injury to persons or property proximately resulting from any breach of warranty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

New Business Rule. What does the UCC say?

A

UCC § 2-708: “It is not necessary to a recovery of “profits” to show a history of earnings, especially if a new venture is involved”

26
Q

General limitations on substitutional reliefs are foreseeability, certainty, and avoidance (mitigation). Why should mitigation not be considered a ‘duty to mitigate’?

A

Duty gives a right to someone else to sue. The breaching party can they sue for failure to mitigate. If it’s wrong to say it’s a duty, it implies that there is no possibility to sue. It’s wrong to call it a duty because you cannot.

27
Q

Elaborate on the positive and negative aspect of mitigation following a breach of contract

A

When someone suffers harm due to a breach of contract or another person’s wrongdoing, they have a responsibility to minimize or “mitigate” the damages, which means they should take reasonable steps to prevent further harm or losses. This includes not doing things that would make the situation worse.

Here’s a breakdown of the concept:

  1. Negative Aspect: The person who was harmed shouldn’t make their situation worse. For example, if someone’s car is damaged, they shouldn’t keep driving it and causing more damage.
  2. Positive Aspect: The person should take reasonable actions to prevent additional harm. Using the car example, they should get it repaired promptly to avoid more damage.

The idea is to ensure that the harmed party does what’s reasonable to limit the losses and not expect full compensation for harm that they could have reasonably prevented.

28
Q

Soules v. Independent School District No. 518 (1977). A teacher was let got and she sued for damages (expectancy). What were here obligations as a laid off employee?

A

Yes, in this legal context, the plaintiff would have been expected to make reasonable efforts to find new employment or take steps to mitigate (reduce) the damages resulting from the breach of her employment contract. Specifically, she should have looked for suitable teaching positions to replace the one she lost when her contract was wrongfully terminated. The key is that the efforts she made to find new employment should have been reasonable and not overly burdensome. If she failed to do so without a valid reason, it could lead to a reduction in the damages she can claim in a lawsuit for the breach of her contract.

29
Q

Soules v. Independent School District No. 518 (1977). A teacher was let got and she sued for damages (expectancy). If she took up new employment, would the income be offset against her damages from the original contract?

A

That’s correct. If the plaintiff takes up new employment, the earnings from that new employment could be offset against the damages she can claim for the breach of the original contract. This principle is based on the idea that the plaintiff should not recover damages twice for the same period; she shouldn’t be compensated for the same salary by both her original employer (the one who breached the contract) and the new employer. The goal is to make sure she is not in a better financial position as a result of the breach of the contract than she would have been if the contract had been fully performed.

30
Q

If an employer lets go an employee and the employee sues the employer for expectancy damages, what obligation does the employer have?

A

It noted that when a wrongfully discharged employee fails to make reasonable efforts to pursue or accept other employment, the rule of avoidable consequences may prevent them from recovering the full amount of salary promised under the contract.

The employer must also demonstrate that the employee could have avoided damages, in whole or in part, without undue risk, expense, or humiliation. The burden of proof lies with the employer to show that the employee could have avoided the damages without undue risk, expense, or humiliation.

31
Q

Important: In construction cases, what is the standard measure of damage for the injured party (owner of the property)? What are the four exceptions? Are these rules?

A

Expectancy (cost of completing the work).

Four exceptions are
1. Willful breach (good faith)
2. Apparent economic waste
3. Disproportionate
4. Intent

These are variables, not rules. This was best shown in Groves v. John Wunder Co. (1939). However, only the first three were considered.

32
Q

in Groves v. John Wunder Co. (1939), the court identified four variables to determine whether the cost to complete or property value would be the right measure of damage. Intent was only mentioned by the dissenting judge. What does it mean?

A

What did the parties intend to do when they made the contract.

33
Q

What is the classic example of “apparent economic waste”?

A

Pipe case: The pipe was just as good but from a different manufacturer. Not inferior in quality. Court says no you cannot demolish the house just to the replace the pipe.

34
Q

Lind Building Corp. v. Pacific Bellevue Developments (1989) looked at liquidated damages. Are they enforceable?

A

1) They are not enforceable if they are punitive in nature.

2) To validate if they are enforceable, courts need to look at two things.

A) Did the injured party actually suffer a loss?
B) Is the amount in the liquidated damages clause proportionate to the loss suffered?

Both UCC and Restatements state the same in this regard.

35
Q

In Lind Building Corp. v. Pacific Bellevue Developments (1989), the liquidated damages specified in the contract was not enforced by the court. Why?

A

The injured party actually made a profit from selling the property to another buyer, although at a later time.

36
Q

What is a blunderbluss clause?

A

A blunderbuss clause in contract law is a catch-all provision that mandates payment of damages for any breach of the contract, regardless of the breach’s magnitude.

Some courts interpret this clause as requiring an assessment based on the smallest possible breach, while others consider the circumstances of the actual case.

If the actual breach is a non-material one, courts will decline to apply the liquidated damages clause.

37
Q

The court referred to the rule established in Jacob & Youngs v. Kent. What was established in this case regarding the measure of damages?

A

The cost of completion is the appropriate measure of damages in building and construction cases.

38
Q

What needs to be proven when arguing for the diminution in value measure?

A

1) Good faith in performing the contract
2) Cost of completion would be economic waste
3) Cost of completion would be disproportionate

(Also intent, dissenting judge in Jacobs & Youngs v. Kent)

39
Q

What is a quantum meruit claim?

A

A claim for quantum meruit is a claim for restitution and can arise in two distinct scenarios, depending on the presence or absence of a formal contract:

With Quasi-Contract.

With a Contract: Even when there is an existing contract, a claim for quantum meruit can still arise under specific circumstances:

1) When no price has been fixed in the contract.
2) When the contract includes an agreement to pay a reasonable sum for the services provided.
3) When the work carried out goes beyond the scope of work defined in the original contract.

40
Q

In construction projects, why does it matter if the work has been fully performed or not? (important!)

A

When the work has not been fully performed, the plaintiff can sue based on quasi-contract or contract (quantum meruit).

When the work has been fully performed, the only thing a plaintiff can do is to waive the contract and claim restitution for the actual costs that they have incurred. Because once the work has been fully performed, under the contract, the only thing a plaintiff can claim is the contract price.

41
Q

At what stage is a construction project considered as completed?

A

There’s no precedent that sets the limit at which percentage a contract is fully performed. Courts have room to play. You have options.

42
Q

Assume that in a construction project, the work is not completed. It’s possible to sue either under contract or quasi-contract. Which one to choose? How is this kind of claim called?

A

Quantum meruit (restitution; for what has been afforded).

Choose whichever it gives a higher reward.

43
Q

Which state accepts the material benefit doctrine?

A

Alabama.

44
Q

An implied contract can have two different meanings. Which?

A

In legal terminology, a contract can be implied in law and implied in fact. These are two distinct concepts in contract law:

Implied in Fact Contract: An implied-in-fact contract is a true contract that is inferred from the conduct, actions, or circumstances of the parties involved, rather than from an explicit written or oral agreement. It arises when the parties’ behavior suggests an intention to be bound by contract terms. For example, when you order a meal at a restaurant, there’s an implied contract that you will pay for the meal in exchange for the food and service provided.

Implied in Law (Quasi-Contract or Contract Implied by Law): An implied-in-law contract, also known as a quasi-contract or contract implied by law, is not an actual contract but is a legal remedy that arises when one party has been unjustly enriched at the expense of another. It’s a legal fiction to prevent unjust enrichment. The law imposes an obligation to pay for the benefit received, even if there was no actual contract. For example, if someone provides emergency medical assistance to an unconscious person, and the person recovers, the law may imply an obligation to pay for the medical services rendered.

45
Q

Can an injured party claim both reliance and restitution damages?

A

Yes. But only once at a time.

Restitution Damages (POV breaching party): Restitution damages are intended to restore the injured party to the position they were in before the contract was formed. These damages focus on returning any benefits or payments that the injured party has conferred upon the breaching party. It’s a “giveback” approach to prevent unjust enrichment. For example, if you’ve paid money to the other party under the contract, restitution damages would aim to get that money back.

Reliance Damages (POV injured party): Reliance damages are designed to compensate the injured party for the losses and expenses incurred in reliance on the contract. These damages aim to put the injured party in the position they would have been in if the contract had never been formed. They cover costs that were reasonably foreseeable and incurred as a result of the contract. For instance, if you’ve incurred expenses in preparing to fulfill your obligations under the contract, reliance damages would seek to compensate you for those expenses.

They are both backwards looking. The amount might be the same, but it’s not always the same.

In CBS Inc. v. Merrick, the court gave CBS both reliance and restitution damages. Professor thinks this was a mistake and that all the claims could have been brought under reliance damages.

46
Q

In Doehring Equipment Co v John Deere Co. (2004), why could Doehring not recover the damages claimed?

A

Because they could not demonstrate a causal relationship between the damages and the facts. They are operational losses. They cannot be recovered with reliance, expectancy, or restitution.

47
Q

Why is Oliver v. Campbell worth remembering?

A

This case concerns the difference between restitution and reliance damages for completed projects.

An attorney entered into a contract with a client to perform certain legal services for a set fee. The client terminated the attorney’s representation immediately before judgment was to be rendered in the matter.

“[R]estitution in money is not available to one who has fully performed his part of contract, if only part of agreed exchange for such performance that has not been rendered by defendant is sum of money constituting a liquidated debt, but that full performance does not make restitution unavailable if any part of consideration due from defendant in return is something other than a liquidated debt; in such cases he recovers full contract price and no more.”

The value of the services rendered was 5000 USD, the contract price was 450 USD. Restitution is not available when the performance has been completed. The court here decided that performance was complete (although it can be argued that it was not).

48
Q

In which cases does it make sense to claim restitution instead of reliance?

A

In cases where the value of the services rendered are higher than the price agreed. For instance, when a price of 500 USD is agreed upon but the value of the service ends up being 1000 USD.

Assume that 80% of the work has been rendered, 80% of 500 USD could be claimed with reliance. With restitution, it could be 80% of 1000 USD.

Note that restitution is not available for contracts that have been performed (Oliver v. Campbell).

49
Q

Can restitution also be asked under contracts?

A

Yes, but some states only allow it under quasi contracts.

50
Q

What is the expected measure of damage for quasi contracts?

A

Restitution. But reliance and Disgorgement are also possible. There is NO expectancy damages for quasi contracts.

51
Q

Which principle must be understood in connection with restitution damages?

A

Principle of unjust enrichment.

52
Q

For reliance and restitution, where do the restatements put a limit on the damages?

A

Recovery cannot be larger than the breaching party’s gain in wealth (restitution). Reliance is essentially “what I have lost” vs. Restitution “what the other party has gained”

53
Q

Under what circumstances can reliance damages be higher than restitution damages?

A

A party who breaches a contract may recover (1) restitution for any benefit that he has conferred by his partial performance or (2) reliance in excess of the loss he caused by his breach.

There might be circumstances where the injured party has rendered 100k USD in services (costs) but these were of lower value to the counterparty. In such a case, reliance damages should be claimed.

54
Q

Assume that company A has a contract with company B to provide services. Company A fails to provide the services but tries, in good faith, to mitigate the failure. Can company A claim expectancy damages?

A

Company A would typically not be entitled to claim expectancy damages. Expectancy damages are a type of compensatory damages that aim to put the non-breaching party (Company B, in this case) in the position they would have been in had the contract been fully performed.

Company A could sue for a quasi contract though.

However, when the breaching party (Company A) has made good-faith efforts to mitigate the consequences of the breach and to minimize the losses suffered by the non-breaching party (Company B), the law often takes this into account. In such cases, the breaching party’s liability may be reduced by the amount that the non-breaching party would have been able to mitigate.

55
Q

Explain the importance of Britton v. Turner (1834)

A

Britton v. Turner, 6 N.H. 481 (1834), was a case decided by the Supreme Court of New Hampshire that marked one of the first appearances of the contract law concept of guilty party restitution.

The plaintiff made a one-year employment contract with the defendant for labor for one year, from some time in March 1831 to some time in March 1832. The employment contract specified that the plaintiff would be paid $120 at the end of the contract period. The plaintiff voluntarily left his employment on December 27, 1831. The defendant refused to pay the plaintiff, and the jury in the Court of Common Pleas awarded the plaintiff $95. The defendant appealed the jury verdict.

The Supreme Court of New Hampshire upheld the jury verdict. The Court reasoned that barring the plaintiff from recovering for the work that he had done presented a disproportionate forfeiture. If the Court did not allow restitution, the employer using a similar contract would be motivated to drive away the employee by mistreatment at the end of the employment period to avoid paying anything. The Court determined that such an employment contract should be viewed as accepting part performance day by day and that the employer should compensate for the benefit received.

56
Q

In Walgreen Company v Sara Creek Property Company (1992), Walgreen Company (Plaintiff) had a lease agreement with Sara Creek Property Company (Defendant) for space in a shopping mall. The lease included an exclusivity clause that prohibited the Defendant from leasing space to another pharmacy. However, the Defendant planned to lease space to a deep discount store, which would include a pharmacy, thereby breaching the exclusivity clause. As a result, Walgreen filed a lawsuit against the Defendant, seeking an injunction to prevent this breach of the exclusivity clause. What did the court find?

A

The court held in favor of the Plaintiff, granting the injunction. The decision was based on the idea that when money damages are challenging to calculate or insufficient to fully address the harm suffered by the plaintiff, injunctive relief is an appropriate remedy. The court recognized that projecting damages, especially over a ten-year lease period, was fraught with uncertainty and that the damages remedy would be costly and inaccurate. In contrast, the injunction was a more practical and cost-effective solution.

57
Q

When discussing causation, what must be remembered?

A

Professor Corbin’s Uniformity of Sequence Theory

58
Q

The cost of completion is the appropriate measure of damages in building and construction cases. Which case?

A

Jacobs & Young v. Kent (1921)
Judge Cardozo

59
Q

Famous “pipe” case in construction law. Which case?

A

The cost of completion is the appropriate measure of damages in building and construction cases.

Jacobs & Young v. Kent (1921)
Judge Cardozo

60
Q

When there exists a contract, under which circumstances can quantum meruit be claimed? (3)

A

With a Contract: Even when there is an existing contract, a claim for quantum meruit can still arise under specific circumstances:

1) When no price has been fixed in the contract.
2) When the contract includes an agreement to pay a reasonable sum for the services provided.
3) When the work carried out goes beyond the scope of work defined in the original contract.

61
Q

Consideration for a promise, by either the employee or the employer, in an at-will employment, cannot be dependent on a period of continued employment. Why?

A

Such a promise would be illusory because it fails to bind the promisor who always retains the option of discontinuing employment in lieu of performance. When illusory promises are all that support a purported bilateral contract.

62
Q

What is the “justification” for minors who can disaffirm contracts once they reach adulthood?

A

Public policy.