Contract Practice Flashcards
How do variation requests work?
Covered under Section 5 of the JCT Contract, and is defined as an alteration or modification of the design, quality or quantity of the work.
What are the JCT suite of contract options?
JCT Minor Works Building Contract
JCT Intermediate Building Contract
JCT Standard Building Contract
JCT Major Project Construction Contract
JCT Construction Management Contract
JCT Design and Build Contract
JCT Management Building Contract
JCT Prime Cost Building Contract
JCT Repair and Maintenance Contract
NEC Contracts?
A = Priced Activity Schedule
B = Priced Bill of Quantities
C = Target Cost Activity Schedule
D = Target Cost BofQ
E = Cost Reimbursable
F = Management
NEC4 Design, Build and Operate Contract (DBO), released in 2017
How do the two suites of contracts differ?
- NEC promotes collaborative working
- A programme is a contract document under NEC
- JCT has variations, NEC has compensation events
- Each has a person allocated on behalf of the employer (CA in JCT, PM in NEC)
- JCT has provisional sums, NEC does not
- QS is only mentioned in JCT contracts
How does a standardised form benefit a project?
A standardised form benefits a contract as it is inexpensive, saves time and resources, and ensures both parties are familiar with their rights and obligations. It is drafted by a legal professional so it should reduce the chance of disputes and improve overall efficiency.
What typical amendments have you encountered?
Amendments I have encountered are when clients have proposed to amend the payment dates on contracts or remove some relevant events or matters, notably adverse weather.
Do you agree with them?
No, I do not. You should not amend standardised forms as it is expensive for the client and contractor to appoint legal professionals and can increase the risk of dispute.
What if you were asked to provide advice?
I would tell a client that is best practice to work under an amended standard form, but if an amendment was important, they must appoint a legal professional to do this and it is outside my scope of competence.
What are the parties’ responsibilities and duties under a contract?
Under a JCT contract (excluding D&B), the client is responsible for the design, appointing a CA and PQS for the contract. It is their responsibility to ensure these roles are filled through the duration of the works.
It is the contractor’s responsibility to manage the budget alongside the PQS and ensure the project is completed on time.
What is the significance of the Local Democracy, Economic Development and Construction Act 2009?
The LDEDC introduced the following:
* Contracts – oral contracts are now covered under this act and allows parties to adjudicate even though the contract is not in writing.
* Pay when certified clauses have been removed
* Payment Notice must be issued 5 days after the due date
* If no payment notice is issued, the payee is entitled to issue a default payment notice
* Right to suspend work – contractor can suspend work in the event of non-payment, the payer must pay costs or expenses for the contractor to suspend the work.
What are the essential components of a valid contract?
Offer, Acceptance, Consideration, Intent to create legal relations and Capacity
Can you name 2 types of performance bond?
- Performance bond
- Retention bond
What is the principal difference between a parent company guarantee and a performance bond?
What type of letter of intent was used?
- Consent to Spend – allows work to proceed up to a certain value while the contract is being finalised. The type of letter will create a legally binding contract which will pre-date the principal contract and will be suspended once that contract is executed.
What were the key terms?
- Consent to spend up to £300,000.00
- Allowed programmed activities to commence up to a specific date (31st May 2023)
- Start Date
- Retention
- Right to adjudicate
What are standard forms of contracts?
JCT Suite
FIDIC
NEC 3/4
PPC 2000
What is PPC2000 for?
Partnering contracts
Why use standard forms?
- saves time and cost
- benefit from familiarity
- provide benchmark for negotiating
- flexibility
- checklist for items to be agreed
- judicial decisions on contract terms
How do you select the most appropriate form?
- Understand client’s objectives
- Undertake a broad review of standard contracts
- Advise client on contract terms and obligations
- If client wants to make amendments advice them to consult with a lawyer
What should a Letter of Intent include?
- How work is to be valued
- A cap of the value of work
- Does the client have step in rights to subcontractors if the contract is terminated
- Contract the standard form is to be based on
- Scope of work covered
- Insurances