Commercial Management Flashcards

1
Q

What is your understanding of the components that make the cost of the project to the contractor?

A

Staff, Labour, Materials, Plant, Professional Fees, Subcontract Labour, Subcontractors, Preliminaries and Overhead and Profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why do you understand my the term working estimate?

A

Used to estimate and bid for a job (usually just referred to as an estimate). It is an estimate that includes costs and will be used during tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key components of a CVR report in respect to cost/value to date?

A

Value earned to date, against costs incurred to date including liabilities and accruals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the key components of a CVR report in respect to cost/value to complete?

A

Forecast of costs required to complete the project against forecasted estimated final value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Explain the CVR process?

A

The CVR process is to establish the current and projected profit margin of the construction project. To establish this, I assess all costs incurred to date over the following cost heading; staff, preliminaries, labour, subs, plant and materials. I then calculate any accruals to finalise costs to date. I then update the expected final value of all these cost headings to produce a profit and loss statement for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What do you understand by the term liability?

A

A liability is the total cost the contracting organisation must pay out to a vendor at a point in time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How does this differ from cost?

A

Liability is the total cost due to be paid out, where as the cost is the total paid to date, the difference between the two is an accrual.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What would you consider before constructing a project cash flow forecast?

A

Before constructing a cash flow forecast I would consider the following:
1. Programme Start Date, Completion Date and Duration
2. Any advance payments
3. Cost to mobilise on site
4. Contractual provisions – materials on site, off site, how is work valued
5. Supply chain payments
6. Management costs
7. Variations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why is the construction of a cash flow forecast so important?

A
  1. Allows organisations to pay expenses when they become due.
  2. Provides money to make investments, for example purchasing hire equipment.
  3. Security to lenders for credit.
  4. Provides contingency for unexpected issues.
  5. Enables a red flag system if extra credit is required to cover expenditure.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How is wastage calculated?

A

Wastage is allowed for as allocated contingency within construction budgets.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What insurances are required under a contract? How are they included in a tender?

A
  1. Public Liability Insurance
  2. Employer’s liability insurance
  3. Contractors All Risk Insurance
  4. Contractor’s Plant and Equipment Insurance
  5. Temporary buildings insurance
  6. Terrorism insurance
  7. Latent defect cover
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What you understand by the term project budget?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does this differ from the tender budget?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What current challenges is Covid and/or Brexit bringing to Commercial Management?

A

As a QS who has worked through COVID I have noticed a trend in Value Engineering becoming much more common during the tender and PCSA period as I do not believe PQS’s benchmarking data has been updated efficiently to reflect the cost increases we have seen and now labour cost increases due to labour shortages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

On your South Kensington Project, talk me through how you updated your CVR on a monthly basis?

A

To complete my monthly CVR’s I export from the company’s accounting software the latest cost report. From this I create a pivot table that sorts these costs into staff, labour, preliminaries, materials, plant hire, subcontractors, and subcontract labour. I ensure costs are up to date for that reporting month and accrue for any payments that are not showing on the cost report. I then input value against each subheading ensuring this is inline with the construction budget, which produces the profit and loss account for that project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Talk me through how you carried out a cost to complete exercise?

A

To carry out the cost to completion exercise, I export from the company’s accounting software the latest cost report. From this I create a pivot table that sorts these costs into staff, labour, preliminaries, materials, plant hire, subcontractors, and subcontract labour. I ensure costs are up to date for that reporting month and then calculate the liabilities against each cost heading. I then forecast value against each subheading ensuring this is in line with the forecast final account, which produces the forecast profit and loss account for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What did you include in your forecast for unagreed change?

A

For unagreed change I inputted the costs for the change and the estimated likely value I would receive from the CA. This would always be a commercial management decision that I would make and check with my director to ensure he is happy with the management of that risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Talk me through how you prepared the cash flow forecast?

A

To prepare the internal cashflow forecast, I calculate the likely monthly spend for each cost heading. This is calculated by fixed costs which I know will be paid to staff, subcontractors, and estimated costs on labour, materials, plant hire and preliminaries. This is split per month which allows me to input this into a cashflow with shows the likely spend during each month.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What document(s) other than the CTC did you need in order to do this?

A

To complete this I utilised cost report data from accounts, subcontractor liabilities and payment schedule, the construction budget, and construction programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What did you identify as the cause of the labour overspend?

A

I identified the cause of the labour overspend to be the site manager retaining labour on site due to variations that had occurred.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What options did you consider to address this?

A

To address the overspend I considered reducing the labour on site, analysis the labour timesheets to produce a labour tracker which would identify what work was being carried out and leaving the labour on site as I did not want to jeopardise the programme which could result in exposure to LADs or extended management costs that would not have a value.

22
Q

How did this issue identify a failure in the correct administration of the contract?

A

From the labour timesheets I completed a labour tracker which identified work activities on site that could not be costed against any works in my construction budget. I identified these tasks and put them forward to the CA who instructed the works accordingly.

23
Q

What were the commercial issues relating to the welfare facilities?

A

The commercial issue relating to the welfare facilities was the programme was slipping and I had additional labour on site than forecasted to move welfare facilities and move materials continuously due to restricted space. This was incurring addition costs, that was unrecoverable.

24
Q

What options did you consider?

A

It was a commercial discussion to hire welfare cabins and suspend parking bays close to the property, move offices elsewhere and rent space or place a temporary structure on the roof terrace to house materials and staff.

25
Q

How did you come to your preferred option?

A

The roof terrace idea was my preferred solution as it provided a fixed cost was known and could be recycled and use elsewhere. It was also the cheapest option our of all 3 and enabled staff to be close to the job and control site efficiently.

26
Q

What advice did you provide to your senior management?

A

I advised senior management on the cost implications of the options, to suspend bays in Westminster was circa £20k for 3 months plus welfare cabin hire charges, office space was circa £3k a month but the construction of a temporary office was approximately £10k and was fixed known cost.

27
Q

Can you give a brief overview of the commercial managers job in construction?

A
  1. Maximise profitability
  2. Monitor and control internal processes
  3. Manage external relationships, including customers, clients, and the supply chain.
  4. Monitor financial performance
  5. Manage risk
28
Q

Can you tell us the 8 key tasks mentioned in the Commercial Management Guidance Note?

A
  1. Understand Estimate
  2. Value Engineering
  3. Supply chain management
  4. Valuing work
  5. Understanding cost
  6. Cost/Value Analysis
  7. Cashflow
  8. Commercial decision making
29
Q

What are the different payment/procurement methods?

A
  1. Lump Sum
  2. Remeasurement Contract
  3. Target Price
  4. Guaranteed Maximum Price
  5. Cost Reimbursable
  6. Management Contracts
30
Q

What is an activity?

A

An item of work within a project or contract.

31
Q

What is a budget?

A

A budget is an evolution of an estimate, and is updated regularly to reflect updated cost information until completion of the project.

32
Q

What do you understand my common analysis levels?

A

Consistent use of cost and activity elements through estimates, budgets, forecasts, valuations, CVRs, cash flow, cost reports and risk register.

33
Q

What do you understand by CTC (cost-to-complete)?

A

Forecast of cost required to complete a project from a point in time.

34
Q

What to you understand by CVR (cost value reconciliation)?

A

This is a project’s profit and loss statement, comparing internal valuations with costs incurred including accruals and liabilities.

35
Q

What is an estimate?

A

Approximation of costs, usually produced pre-contract or pre-construction to progress to construction.

36
Q

What do you understand by the term EVA (earned-value analysis)?

A

Assessing the work complete and forecast final cost and final value.

37
Q

What is an external valuation?

A

An external valuation is a valuation works carried out by a contractor for the purpose of applying for payment to the client.

38
Q

What is a forecast?

A

Forecast between revenue and costs.

39
Q

What is an internal valuation?

A

An assessment carried out internally to asses work done.

40
Q

What is a programme?

A

A schedule of tasks that must be completed on time to achieve a desired outcome.

41
Q

What do you understand by the term subcontractor?

A

Goods/services/and install

42
Q

What do you understand by then term vendor?

A

Just goods and services or hire of plant etc.

43
Q

What do you understand by a WBS (Work breakdown structure)?

A

A work breakdown structure is a project specific analysis or where an estimate resource will be utilised and where actual resources are allocated.

44
Q

What do you understand by a detailed estimate?

A

The most accurate estimate that can be provided, however it requires the most amount of time and requires a high level of information including detailed drawings and specifications.

45
Q

What are the stages of a detailed estimate?

A

Stage 1: Production of Bills of Quantities
Stage 2: Pricing of Bills of Quantities through labour, plant, materials, SC, waste, hire, and provisional items.

46
Q

What do you understand by the term composite item?

A

A composite item is a lump sum price for something priced superficially with composite rates.

47
Q

What is included in a detailed cost estimate?

A
48
Q

What do you assess during re-budgeting?

A
49
Q

What do you understand by the term ‘Value Engineering’?

A

Value engineering is a process designed to maximise value through either improved design, enhanced function, reduced cost, reduced risk or reduced whole life cost of
the asset being constructed.

50
Q

What techniques do you adopt as a commercial manager to manage the supply chain?

A
  1. Vendor Management
  2. Procurement and Pre-Contract
  3. Contract Administration
  4. Final Account
51
Q

Why is a strong cash position important?

A
  1. Allows organisations to pay expenses when they become due.
  2. Provides money to make investments, for example purchasing hire equipment.
  3. Security to lenders for credit.
  4. Provides contingency for unexpected issues.