Contract Administration L3 Elmwood Residential Unit Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

Explain why you advised the contactor was entitled to payment for the un-instructed variations

A

I rejected the claim for in-instructed variations.

I referenced the Schedule of Workd the contractor had priced and identified claims that we’re within the SoW.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What advice did you give to the client in respect of this issue?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What advice did you give to the contractor in respect of this issue?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Did you issue a certificate of non-completion - if not explain why not?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Explain how you advised the client in respect of deducting Liquidated Damages

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How did you determine when PC had been achieved (L2)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly