Contract Administration L2 Cruyff Court Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

Outline the matters discussed at the pre-start meeting.

A

Introductions
Overview of works
Contract documents
Contract sum
Contract dates
Programme
Insurances
Site set up
Key contacts
CDM/H&S
CP Plan
Asbestos R&D Survey
Risk Log
Construction drawings
Planning / Building Control
Valuation Dates
Client items
AOB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Outline the matters discussed at the monthly site meetings.

A

Progress
Programme
Quality
Issues
H&S & CDM
Client issues - any impact on site
Valuations
Risk log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain how you undertook the quality and progress inspections.

A

Site inspections at two-week intervals which I aimed to align with key points of progress or stages of work such as setting site out, groundworks, fence & goals set out, macadam laid etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain how you used the contractor’s programme to measure progress on site.

A

I measured the estimated completion of a works package or element as a percentage against the programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What information was issued to your client following these inspections?

A

Update on progress against programme
Any H&S issues
Any issues / client issues
Valuations when due

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Explain how you prepared the valuations and certified payment to the contractor.

A

I estimated the percentage completion of priced items/packages, adding the total minus previous valuations. I then issued a certificate of payment to the contractor and copied it to the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How did you determine when PC had been achieved?

A

The works had been completed as per the contract, and the court was in a condition that allowed full use by the client, free from any known defects. H&S file/documentation had been handed over.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What information was included on the PC Certificate?

A

Description of work
Job reference
Contract date
Issue Date
Practical Completion Certificate serial no.
Date of Practical Completion
The expiry date of Rectification Period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What other information/documents were issued with the PC Certificate?

A

H&S file
Certificates - Electrical/fire alarm/gas etc
O+M manuals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Explain the process of issuing the Certificate of Making Good.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you deal with Liquidated Damages on this contract (or an alternative if you did not use them on this job)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you determine how long the Defects Liability Period should be on the projects you undertake?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What factors influence increasing/reducing the DLP?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Explain why you used the NEC4 FM short contract for this project.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Explain the difference between part A and part B.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Explain how the work was ordered on this contract.

A
17
Q

Explain how the monthly applications for payment were processed

A