Contract Administration - General Flashcards
What does NEC Stand for?
New Engineering Contract
When was the NEC founded?
1993
Under the NEC contract what is the term for the person who acts on behalf of the employer?
Project Manager
How might you describe the NEC contract?
Progressive, Collaborative,
Uses objective language to remove ambiguity i.e 1 in 10 year weather event
What does JCT Stand for?
Joint Contract Tribunal
When was the JCT founded?
1931
Under the JCT Contract what is the term for the person who acts on behalf of the employer?
Contract Administrator
How might you describe the JCT Contract?
Traditional, Adversarial
Uses subjective language such as ‘An exceptionally adverse weather event’
Under the NEC, give some examples of what is required to be included within the programme?
Start date, access date, key dates and completion date
How they plan to achieve works i.e resources
The order and timing of the works
Provision of float, time risk allowances
How long does the project manager get to accept the programme (or notify the contractor they are not accepting the programme and reasons for not)?
2 Weeks
What may be reasons you could not accept the programme?
The contractors plans are not practicable
Information is not shown which the contract requires
Non-compliance with the works information
What clause of the NEC ECSC is the programme?
31
What clause of the NEC ECSC covers revisions to the programme?
32
Under the NEC ECSC what should be included within a revised programme?
Actual progress and effect on remaining works
Effects of Compensation Events
Plans to deal with delays or notified defects
Whos responsibility is it to notify defects under the NEC ECSC?
Both the contractor and the supervisor
The contractor corrects a defect whether or not the supervisor notifies him of it
The supervisor can instruct the contractor to search for a defect under clause 42