Contract Administration Flashcards

1
Q

What is a Notice of Non-Completion Certificate?

A

A Notice of Non-Completion (clause 2.28, JCT 2016 Design and Build): If the Contractor fails to complete the Works or a Section by the relevant Completion Date, the Employer is required to issue a notice to that effect. If an extension of time is awarded subsequently, a fresh Notice of Non-Completion must be issued by the Employer.
It is a pre-requisite to deduct LAD’s.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Requirements to get into contract?

A
  • Consideration
  • Offer and acceptance
  • Legal purpose
  • Capable parties
  • Mutual assent
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Difference between a Loss and Expense and an Extension of Time

A

Extension of Time - as a result of a Relevant Event, enabling the Contractor to Time.

Loss and Expense - as a result of a Relevant Matter, enabling the Contractor to Time and Costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What needs to be in place to deduct L&D’s?

A

In order to claim liquidated damages, the Contract requires the employer to issue a notice of non-completion if the contractor has not completed the works (or a section) by the completion date stated in the contract (subject to any extension of time awarded).
This is to be deducted in a Pay Less Notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is included and excluded on a Final Account statement?

A

Inclusions
* provisional sums (which can only be expended by
issue of a contact instruction)
* agreeing prime cost sums (where applicable)
* any loss and expense associated with extensions of
time
* adjustment of provisional/approximate quantities
* fluctuations
* any set-off/contra charges (typically a subcontractor
issue) or
* any other items affecting total cost.

Exclusions
- Liquidated and Ascertained Damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Is Retention to be deducted from everything on a Contractor application?

A

Not to be deducted against the following;
- Staff and Management costs
- Bonds & Insurance costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Final Account?

A

The final account is the conclusion of the contract sum
(including all necessary adjustments) and signifies the
agreed amount that the employer will pay the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does ‘Time at Large’ mean?

A

a PC date has not been fully confirmed by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the difference between a Divergence and a Discrepancy?

A

Divergence - A divergence is when the documents do not comply with the Statutory Requirements.

Discrepancy - discrepancy is referred to as an inconsistency between the contract documents. (Something refers to something else in the contract docs which isn’t there or in agreement)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly