Contract / Admin Law Flashcards
CDM 2015 Principal Objectives
- Ensure consideration of HS issues (feasibil-complet),
- Encourage better safety management
- Adequate resource/sufficient time to complete duties
- Involve directly clients/PD/other D/PC/other C/suppliers.
Difference between CDM 2007/15
- Apply dome/ind projects, 2/3 of 44 deaths smaller sites,
- Removal of CDM Coordi role (often appointed late),
- Introduction of principal contractor,
- HSE notif +30 days/500 pers days/<20 workers at once
- PD and PC where there are 2 or more contractors,
- Requirement to have necessary skills/knowledge/experience/org capacity for the project.
What Commercial Clients have to do
- Appoint principal contractor and designer
- Confirm competence of duty holder
- Duty holder has nec skill/knowle/experi/org capa for proj
- Notify HSE
- Prov pre-const info Docu/commu/co-op w/ proj member
- Check PC construction phase health and safety plan
- Ensure minimum HS standards are maintained on site
- Necessary minimum welfare facilit are provided on site
Principal Designer Role
- PD control over the pre-construction phase.
- Identify/eliminate/control foreseeable risks
- Ensure other designers are carrying out their duties
- Provide info to PC to help then plan/manage/monitor and co-ord HS in the Const Phase HS Plan,
- Provide info for HS file
Designer Role
- An org/individ who prep/modifie design for const project
- Eliminate/reduce/control foreseeable risks in construction/maintenance
- Provide design information
- Establish how designs interacts and influence HS
Principal Contractor Role
- Prepare construction phase HS plan
- Plan/manage/control/monitor HS in construction phase
- Provide info for HS file,
- Provide adequate welfare facilit/suitable site inductions,
- Steps to prevent unauthorised entry,
- Ensure workers are consulted on HS on site
Contractor Role
- Plan/manage/monitor const work in control w/ HS risk
- 1 contractor projects prep the HS plan /welfare facilities
- Multi-contractor must comply with PD/PC,
- Mustn’t employ without neces skill/knowle/exper/training
- Prov worker with appropiate supervision/instructions/info
- Steps to prevent unauthorised entry before work begins.
Expressions of Interest Stage
- Skills/knowledge/train assess in the tender process
- Company/org HS mngm procedure check, again at formal tender stage when specific to project.
- May include Company HS policy,
- Qualification/experience of employees
- Accident reporting/enforcement action
- Welfare provisions
- RIDDOR Procedures
RIDDOR
-(The Reporting of Injuries, Diseases and Dangerous Occurrence’s Regulations)
Pre-Construction Information Individuals
- Principal Designer
- Architect
- Structural engineer
- BSE
Construction HS Plan
Principal Contract/Other Contract/Sub-contract/Supplier
Develop before constr, otherwise gross negligence
Pre-Construction Information
- Prov info those bid/plan work/devel const phase plan/HS file.
- Info client has about building or reasonably attainable,
- Provide basis for prep of the const phase plan
- Info appro to project/appro detail/proportio to risks
- Include client brief/key const dates, resources used/time allocat to each stage arrange to ensure coop
- Site HS hazards and how they will be addressed
Construction Phase Plan
- How HS will be managed during the const phase
- Level of detail proportionate to risks involved
- HS arrangements for construction phase
- Site rules,
- Where relevant specific measures
- Record plan for significant HS / how to comm this
- Doesn’t include risk asses/records of how decisions were reached/const method statement
Health and Safety File
- Principal Designers responsibility
- Presented to client on conclusion of works
- Collection of infor on foreseeable hazards/materi used
- Retained to ensure safe mainten/cleaning/altera/demolit
- Passed onto and made available to leaseholders
- Hazards not eliminated
- Construction processes
- Hazardous materials used
Objectives of HS At Work Act 1974
- Secure HS of persons at work
- Control keeping and use of dangerous substances
- Control the emission of noxious / offensive substances
- Protect persons other than persons at work against HS risks out of work activities
HS Laws
- Ensure, reasonab practicable, HS/welf of employees
- Ensure, service/mainte of safe plant/systems of work
- Prov safe systems use/storage/transport of substances
- Prov correct info/instruct/training/supervision
- Safe place of work/safe access to and egress
- Prov/maintain a safe working environment
- Prov/maint a written statement of safety detailing policy
What is Procurement
Establishes roles, responsibilities, relationships and the risks carried out by parties that form the organisation and the contractual arrangements for the project
Traditional Procurement Information
- Sequential one stage finishes before next starts
- Sequence of working Brief, Design, Competition, Const
- Low cost risk, Med time, Low quali/perfor/design
- Up front time to devel design before const time if profit
- Separate parties involved project time overrun/cost
- Separate Design and build stages
- Slow start on site have to do complete design first
Traditional Contractual Relationships
Client -PM/Main Contrac/Desi+Cost consult/CDM Regs
Main Contractor - Sub Contractor / Suppliers
Design and Build Variants
- Direct
- Competitive
- Develop and Construct
- Novated Develop and Construct
D+B Common feature
Contractor led, providing client with single point of contact and single point of responsibility
One organisation totally responsible
Lowest bid or MEAT
D+B Contractual Relationships
- Client - PM / CDM 2015 / D+B COntractor
- D+B - Sub contractor / Designers / Suppliers
- Brief / Competition / Design + Construction
D+B Risks to Client / Information
- Lowest overall risk / buildability + lump sum tender
- Low design risk
- Low cost risk
- High quality/performance/design risk
- Client driven changes expensive / difficult
Management Contractual Relationships
- Client - PM / Mngm Contractor / Desig/Cost/HS consult
- Mngm Contractor - Works packages / Trade contractors
- Brief / Design + Construction
Management Risks to Client / Information
- Medium Cost / Time Risk Low quality/perform/time risk
- Mngm contract have responsib to program/plan work
- Overlap in const/design package competitive tender
- Buildability better team performance
- Client doesn’t know package costs added up/time
Management Contracting Contractual Relationships
Client - PM/Work Pack/Des/£/HS consult + Const Manag
- Brief / Design + Construction
- Medium Cost / Time Risk Low quality/perform/time risk
Management Contracting Information
- Experiences clients develop with own project teams
- Trade contractors in direct connection to client
- Overlap client later design decisions modify/develop
- Design tender build for each stage sequential design
Procurement Project Managers
- Appointed by client as advisers
- Help develop business case
- Project investment appraisals
- Risk assessments
- Procurement selection
- Appointing / selecting team monitoring performance
- More experienced the client less help don’t have PM
The Construction Round Table 1995
Procurement Choice Considerations
- Clients objectives/priorities
- Time
- Price Certainty - Importance of lump sum tender
- Qual/Perform level - D+B contract respon may change
- Complexity - Technically complex may turn org complex
- Competition
- Controllable variation - Ability to change design
- Division of Mngm responsibility - Manage 1 or many
- Extent of professional responsibility required -
- Risk avoidance
D+B / Traditional / Management Reason Why
Offers reliable quality / economy / speed
Innovative design / higher perform / more cost/program
Flexible / fast completion / trade off client risk early start
Time / Quality
Quality / Cost
Cost / Time
Management Procurement
Traditional Procurement
Design + Build
Cost Led Procurement
Client selects integrated supply chain teams from framework
Based on collaborative manner to complete at low cost
Need to maintain quality as well
Integrated Project Insurance
Competition for team responsible for delivery
Single insurance policy to cover all delivery risks
Packaging up all insurances normally held by client/SCM
Supply chain memebers
Two Stage Open Book
Invite suppliers on a framework
Bid basis on outline brief / cost benchmark
Successful team works up a detailed proposal
Detailed proposal based on open book cost
Main Idea of On Trial Procurement
Early involvement of Supply chain team
Create team to work in collaborative/integrative manner
Reduce risk / greater cost certainty / time performance
Bennett/Jayes report 1995
Partnering can lead to: Cost Saving Improved quality Better design/configuration Safer const methods Ealier completion time Bigger profits to be shared
High Profile unsuccessful; corporate prosecutions
R v PO Ferries Ltd 1990
Leaving Zeebrugge 193 people died