Construction Management(BB-CH4) Flashcards

1
Q

determining requirements, devising and developing methods for construction projects

A

planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

determining amount+type of work to be performed+quantities of material, equipment, labor

A

estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

individual evaluates a job, has working knowledge of all phases of construction, mentally pictures separate operations

A

estimator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

determining when action must be taken, when material equipment and manpower are required

A

scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

type of schedule used to coordinate manpower requirements of a project and show # personnel required

A

manpower

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

(blueprints) what folder should you check to ensure changes were recorded

A

revisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

(specifications) list of unusual/unfamiliar items of work or materials

A

notes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

best procedure to check your estimates

A

have another person make an independent and compare the two

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

which problems can lead to omissions in your quantity estimates?

A

failure to read all notes, scaling errors, failure to allow for waste(aota)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what should experienced estimator do if he finds that details on a drawing are not drawn to scale

A

obtain dimensions from other source

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

type of estimate is used as a basis for purchasing materials, determining equipment+manpower

A

quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

which provides info of material, equipment, manpower requirements

A

construction activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

(estimating) how should an activity be defined

A

single task, single trade

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

material estimates have which of the following uses

A

procurement+determination of availability of materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

when estimating, which of the forms should be used to list required materials needed for each activity

A

estimating worksheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

which publications contain conversion and waste factors for construction materials

A

NTRP 4-04.2.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

average rate of speed for vehicle moving materials over roadways compared to speed limit(percentage

A

40%-56%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

which estimate consists of listing DL Mandays required to complete various projects

A

manpower

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

which labor included all expended directly on assigned tasks, either in field or in shop

20
Q

man hour tables in NTRP 4-04.2.3 are arranged into how many divisions

21
Q

The work schedule of a deployed Seabee battalion is based on an average of 65 hours per man per week. t/f

22
Q

CPA, CPM, and PERT are techniques used in the analysis of events and activities of a construction project. What is the generic title covering these techniques?

A

Network analysis

23
Q

Placing underslab conduit runs before pouring concrete is considered what type of dependency

24
Q

In precedence diagrams, how are activities represented?

A

A rectangular box

25
In a precedence diagram, what information about an activity can be found on the right side of an activity box
the completion
26
In a precedence diagram, activities may be divided into how many distinct groups?
3
27
In a precedence diagram, intermediate goals with no time duration relate to what kind of activities?
working
28
How are critical activities in a precedence diagram identified?
slash marks through activity connector
29
Which of the following rules governs the drawing of a network?
The start of an activity must be linked to the ends of all completed activities before the start may take place
30
When two network activities are remote from each other but must be connected to show dependency, what type of connector should be used?
Splitting
31
In a network, what is the main objective of the forward pass?
determine the duration of the network
32
What term identifies the amount of scheduled leeway allowed in a network?
float
33
When you become a Builder petty officer, you automatically assume which of the following additional responsibilities?
Crew leader
34
When planning a project, you must consider both the tools and equipment you will need and the capability of the crew. t/f
true
35
To ensure a job is completed on schedule, you should take which of the following actions?
Encourage teamwork and establish goals
36
A standard Builder tool kit contains the hand tools required for what maximum size crew?
Four persons
37
As a crew leader, you are NOT authorized to draw the tools required by the individual crewmembers. t/f
false
38
What form should a crew leader use to order materials?
dd 1250
39
Labor that includes actual mandays expended to support construction operations but which does not produce an end product in itself is what type?
Indirect
40
As a petty officer, you must be familiar with the safety program at your activity. t/f
false
41
The safety policy committee is presided over by what person?
The safety officer
42
What is the primary purpose of the safety policy committee
Review all vehicle accident reports and determine the causes of accidents
43
What is the primary purpose of the safety supervisors' committee?
Establish work procedures
44
Which of the following committees reviews vehicle mishaps?
The equipment committee
45