Construction and Works of a temporary nature - Hazards and Controls Flashcards
Range of Construction Activities
Site Clearance Demolition and Dismantling Excavation Loading, unloading and storage of materials Vehicle movements Fabrication Decoration Cleaning Site Services - Utilities Landscaping
Particular construction issues
Transitory nature of workers
Temporary nature of construction activities and the constantly changing workplace
Time pressure
Weather conditions
Literacy, numeracy and language
Regulations covering Construction Projects
Construction (Design and Management) Regulations 2015 - CDM
What all construction projects must have
Workers with the right skills, knowledge, training and experience
Contractors providing appropriate supervision, instruction and information
A written construction phase plan
What projects with more than one contractor must have
All for construction projects plus:
Principal designer and principal contractor must be appointed
Needs a health and safety file
When must client notify the HSE
If the project lasts longer than 30 days and has more than 20 workers or exceeds 500 person days
Types of duty holder under CDM
1) Clients
2) Domestic Clients
3) Designers
4) Principal Designers
5) Principal Contractors
6) Workers
Principal Designer responsibilities
Plan, manage and coordinate H&S in the pre-construction phase of a project, including identifying. eliminating and controlling risks and ensuring the designers carry out their duties
Principal Contractor responsibilities
Plan, manage and coordinate H&S in the construction phase of a project, including:
Liaising with client and principal designer
Preparing construction phase plan
Organising cooperation between contractors and coordinating their work
Pre-Construction Information
Provides the H&S info needed in advance of work and is used to prep the construction phase plan.
Provided by the client and contains things like H&S file, Asbestos surveys etc…
Info must be relevant to the project and have appropriate level of detail and be proportionate to the nature of the risk
Construction Phase Plan
Outlines:
H&S arrangements for managing significant H&S risks associated with the project
The site rules
Any specific measures concerning work listed in CDM as involving particular risks
Client must ensure it is in place before the work begins
Works under CDM which involve particular risks
Risk of burial under earth, engulfment or falling from height
Risk from chemical or biological hazard
Ionising radiation work in controlled areas
Near high voltage power lines
Exposure to risk of drowning
Work on wells, underground earthworks and tunnels
Divers using a system of air supply
Workers in cassions with a compressed air atmosphere
Involving explosives
Assembly or dismantling of heavy prefabricated components
Who preps the Construction Phase Plan
Single-contractor projects it is the Contractor
Multi-contractor projects it is the Principal Contractors duty
Health and Safety File
Must contain info about the project likely to be needed to ensure H&S
Only required from projects with more than one contractor
Should be clear, concise and easily understandable in a conveniently accessible format
General site security precautions
Perimeter fencing with adequate signage and lighting
Doors and gates
Storage compounds and facilities for plant, hazardous and dangerous substances
Height of perimeter fencing
2m
What should be included in site inductions
Signing in/out arrangements Fitness to work / alcohol / drug screening procedures Parking and site traffic rules PPE requirements Working conditions on site Emergency procedures Use of mobiles, smoking Specific PTW requirements Use of welfare facilities
Regulations covering Height
Working at Height Regs 2005
Examples of Working at Height
Gutter cleaning Putting up a display Minor roof work Shelf stacking Window cleaning Unloading a vehicle Machine maintenance
Hierarchy for managing work at height
Avoid where possible
Use work equipment or other measures to prevent falls
Use work equipment or other measures to minimise distance and consequence of falls
Priority of preventing falls
Prevention over consequence limitation
Collective measures over personal protective measures
Passive preferred to active measures
Fall prevention equipment
Guard rails
Work restraints
Fall Arrest equipment
Lanyard and shock absorber
Landing systems
Types of common access equipment
Ladders and step ladders
Trestles and staging platforms
Independent tied scaffolds
Mobile tower scaffolds
Hazards of using ladders and stepladders
Overloading - Exceeding the max weight of the ladder
Overreaching - body not remaining between stiles and not having both feet on the same rung
Selecting a ladder
Suitable for worst case surface conditions
Suitable for task/environment
Class 1 ladders for work
Suitable size
Used with manufacturers recommended stability devices