Conflict avoidance, management and dispute resolution procedures Flashcards

1
Q

How do you avoid conflict on a project?

A

• Firstly, ensure that the tender information is clear, concise when tendering the project. i.e. a clear scope of works.
- Remain respectful and honest
• If there is a dispute, use a people approach first and try to negotiate an agreement before going legal.
• As a last resort you should go legal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Talk me through how you would go about negotiating something?

A
  • Firstly I would prepare, as understanding you points fully is critical.
  • Try to negotiate a win/win situation.
  • Finally, I would negotiate the small deals before the big ones.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the Adjudication Process?

A
  • Notification of Adjudication from one party to another.
  • From receipt of notification, parties have up to 7 days to appoint the adjudicator.
  • Adjudicator will review parties cases, and make their decision within 28 days. (This can be extended to 42 days)
  • The adjudicator does not have the power to award costs, unless the parties agree to grant him this power.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Litigation?

A

• Litigation is the process of taking legal action, i.e. in the construction industry, it will typically be taken to the Construction and Technology Court.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Arbitration?

A
  • The use of an Arbitrator to settle disputes.

* It is a private, judicial determination of a dispute by an independent third party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the Arbitration Process?

A
  • The appointed Arbitration body must be notified, and they will appoint an Arbitrator.
  • The main hearing will be held,
  • The arbitrator will then base their decision on what they believe to be fair and just
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Under JCT how long does an adjudicator have to make his award?

A

28 days from issue of the referral notice, but this can be extended to 42 if both parties agree.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why can disputes occur?

A
  • Poor performance of parties.
  • Uncontrolled change.
  • Complex contractual relationships / inadequate tender and contract documentation.
  • Inability or reluctance to pay.
  • Inappropriate procurement.
  • Pressure to start on site before design and or contract finalised e.g. Letters of Intent (LOI)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What techniques are available to resolve disputes?

A
  1. Negotiation – problem solving efforts of the parties themselves.
  2. Mediation or conciliation – 3rd party intervention makes a non-binding decision.
  3. An adjudicative process – final outcome determined by a 3rd party who’s decision is binding.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the difference between adjudication and arbitration?

A

• Adjudication is meant to be quicker and cheaper than arbitration or litigation, as adjudicators must reach a decision within 28 days. Adjudication decisions can be appealed and taken to arbitration or litigation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Can you tell me the dispute resolution procedure listed in one of your contracts and who the nominated body is?

A
  • Adjudication as default by JCT

- Adjudicator is the RICS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you explain to me the differences between mediation and conciliation?

A

The main difference between conciliation and Mediation is that a conciliator can recommend an outcome

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you name some key principles to adopt which can help to avoid conflict?

A

Good management
• Clear contract documentation – reduction in ambiguities in contracts
• Partnering and alliancing
• Good project management – proactively managing all aspects of time, money and risk on a project.
• Good client management .
• Good design team management –
• Good payment practice .
• Record keeping – meticulous record keeping on all aspects of work.
• Regular reporting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What happens if a party does not accept the mediators decision?

A
  • Faulting party would still need to pay for the mediator however it can be taken to further dispute (eg adjudication or litigation).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Mediation?

A

Mediation is the name given to a confidential process whereby parties to a dispute invite a neutral individual to facilitate negotiations between them with a view to achieving a resolution of their dispute.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Arbitration?

A

An arbitration is a legal proceeding under the Arbitration Acts and the arbitrator reaches a decision on the basis of evidence put before him or her sometimes at a formal hearing

17
Q

Can you tell me more about JCT adjudication?

A

Section 9 deals with dispute resolution. If either party wants to raise an adjudication, the scheme shall apply subject to:

  • the adjudicator shall be the person nominated in the contract particulars
  • the adjudicator has expert knowledge and experience and if not must appoint an expert witness
18
Q

What do you understand to be the difference between an arbitrator and an independent expert?

A

An arbitration is a legal proceeding and the arbitrator reaches a decision on the basis of evidence

An independent expert’s decision is not enforceable directly by the courts and they are not liable for negligence.

19
Q

What is the process for ADR in the JCT?

A

Mediation
Adjudication
Arbitration

20
Q

Can you remove adjudication from a contract?

A

There would be no point because under the Act, parties have a right to adjudication

21
Q

What is a slip rule?

A

If an adjudicator makes a mistake, they can correct it after a decision is made