Condensate Transfer Flashcards
1
Q
What is the basis of the CST volume?
A
- 140k gallons to maintain the plant in hot standby
- 140k gallons to cool the plant to 350F at 75F/Hr for SDC
2
Q
What signals will auto start the Condensate Transfer pumps?
A
LOP
SIAS
CREFAS
CRVIAS
3
Q
What is the limiting condition and the basis for LCO 3.7.6, CST?
A
M1, 2, 3, and 4 when SG is needed for heat removal
> 29.5’ Level
Basis: must have enough water to remove decay heat for four hours after a trip from 102%, and then cooldown to SDC with a LOOP
- 4 hours (and once per 12 hours) to verify RWMT has enough water
- 7 days to restore level