CMMS MPS Role and Expectations Flashcards
What is the Maintenance Planner/Scheduler Role?
The Maintenance Planner/Scheduler role is in support of the CS Asset
Management journey towards a World Class Maintenance organization.
This industry-standard role provides more efficient means of managing facilities maintenance and associated maintenance labor.
Planning and scheduling for all maintenance and operations activities will be conducted using current CMMS system applications and standardized business processes.
How do you optimize maintenance inventory?
Optimizes maintenance inventory by balancing work load to labor availability and location, where possible.
Who sets up Auto Parts ordering? And from what module are parts associated?
MPS Associate parts as requested for PO Auto ordering activities.
Job Plan Module
Who is responsible for training technicians/Ops on the use of Maximo?
MPS trains team members when they are unfamiliar with how to create CMMS work orders.
What type of support does the MPS provide to System Engineers for maintenance optimization?
Provides assistance with preventative, predictive, condition-based maintenance optimization. Provides data to systems engineers to aid them with this activity.
Should the MPS coordinate with Vendors?
Yes. Coordinates scheduling of planned maintenance with contractors/vendors
Name 4 MPS BI indicators that aid in maintenance planning activities?
Key MPS indicators to aid in Planning activities are Maintenance Vitals, Utilization Dashboard (MPS Utilization Dashboard & JP Estimated vs. Actuals) Max Evaluation Tool, Back to the Future, Assignment Change History
Use standardized maintenance indicators to aide in work load adjustments and continually improve our teams asset maintenance program. These indicators are found in MyBI
Name 3 MPS BI indicators that aid in maintenance scheduling activities?
Some additional lagging indicators for Scheduling management: MPS Passdown, Open, Closed, and Aging work orders, PMPAS & Work Order Detail, At-Risk PMWOs.
If an MPS receives a service request to create new data records (asset, pm, job plan, etc) does that MPS have access to do so in Maximo?
No MPS cannot create new data records in Maximo outside of work orders, They can only update data records; assets, pm job plan route etc.
i. conducts work on Maximo Service Request tickets routed to the MPS for which the MOS has CMMS permissions to complete.
ii. Routes any Maximo Service Request Tickets to CMMS Database Administrator for which the MPS does not have CMMS permissions to complete.
How often should an MPS communicate the work schedule?
Communicates the daily maintenance work schedule.
In what module does the MPS assign work orders?
Assignment Manager
Scheduling and Assigns work order is conducted in the Assignment Manager, This ensures appropriate technician availability and utilization management and tracking.
How does the MPS identify unassigned work in Maximo?
Identify open, unscheduled and or unassigned work by running work order queries in Assignment Manager.
An MPS should schedule work based on what factors?
Schedules and assigns work orders based on the work item maintenance window and labor availability.
The MPS should try to schedule planned maintenance within what time frame to ensure optimal flexibility for rescheduling?
For unplanned work orders, attempt to schedule within 3 days of user provided Target Start Date.
How does an MPS update technician availability?
Update technician availability in Assignment Manager - Modify Availability capability. This ensures utulization indicator data is accurately reflected.