CMMS Job Plan Specification Flashcards

1
Q

What are the 3 main foundation tabs in the Maximo Job Plan module?

A

Job Plan

Work Assets

Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the main sections in the Job Plan Module

A
  1. Job Plan title and high-level attributes
  2. Details
  3. Job Plan Tasks
    4.Labor/Materials/Tools
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the naming convention for Corporate Services Job Plans

A

WBS# - MAX - (XX)

Do not duplicate the same job plan number (XX) in the same site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If a site needs to modify an existing job plan for localized use, what should the naming convention be?

A

The Job Plan name will will add the site/fab ID in the Job Plan suffix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If a site needs to use a CS POR or Enterprise level job plan where the tasks are the same but material/parts needed differ, what should the requestor do?

A

If same Job Plan tasks, but for slightly different model assets, create duplicate Job Plans ending with “-Auto” to differentiate material or required parts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If an asset needs a set of job plans against the same WBS what value should be the same?

A

If the same Job Plan comprises a set of Job Plans for an asset such as a pump, Monthly, Quarterly, or Semi-Annual (SET), use the same sequence number, i.e. (1121MAX02-A, 1121MAX02-S, 1121MAX02-Q, 1121MAX02-M)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If a site needs a “site-specific” job plan where there is no existing job plan, what naming convention should be used?

A

SS = Site specific. If a site of campus specific Job Plan is NOT derived from an existing, Non-Process Transfer standard, Jb Plan then use MAXSS in place of MAX and the next available sequence number. [WBS]MAXSS[Site or Campus ID]-F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Name at least five (5) job plan name frequencies?

A

Job Plan name frequency designations:
W = Weekly
3A = Every 3 years
2W = Bi-Weekly
M= Monthly
2M = Bi-Monthly
Q= quarterly
S= Semi-Annual
A= Annual
2A = Bi-Annual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If creating an enterprise level job plan, what should be included in the job plan number?

A

Use the standard naming conventions with the addition of the letter ‘E’ after the word MAX

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The job plan organization defaults to what value?

A

“Intel”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If the job plan is POR and/or Enterprise, should there be an associated siteid?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you add a URL to a job plan record in Maximo?

A

COPY URL -
Goto Job Plan Module paste under Attachments/Add new Attachment/Add new Webpage

Attachment should be lovated under the JP Document Folder
1 Specify URL
2 name of document should match the JP document Name
3 Description should match JP description
4 Print attached document with report if printable type box is checked (default is checked)
5 NON factory sites : Add doc to the document library for others to use and check the box.
6 Factory sites: Leave this boxed unchecked. This associates the linked docunents to the current Job Plan record only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you associate a job plan record into maximo that has no CDOCS URL?

A

No. Job Plan documents in DMS must be entered as a controlled document from the CDOCS documentum site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What templates must be used when writing a new job plan?

A

All new Job Plan documents will be written using the CS standard Job Plan template
(000_MAX_02 or 0000_MAX_03) residing in the CS intel document management system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Where can assets(eg light fixtures, fire sprinklers, etc) which are fixtures associated to a system be listed in a job plan?

A

For assets that are fixtures associated with the system. (sprinklers, safety showers) the Job Plan section 40 can be used to list the associated fixtures that require maintenance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How can you associate an Energy Control Procedure to an asset or PM?

A

Job Plans my contain ECP (Energy Control Procedure) specific to the task being performed in the Job Plan scope of work.

Asset: An SR can be submitted to associate a document to the asset. Any time a work order generates the associated document will be available in attachments.

17
Q

If a job plan is in which two (2) statuses should it not be used aainst work orders or PMs in Maximo?

A

Inactive - An invalid job plan no longer used/ associated to work orders or PMs
Draft - The default status associated to a new Job Plan record. A Job Plan in Draft status cannot be associated to a PM or work order.

18
Q

If a work order is generated while a job plan is in Pending Revision status which document status will be linked to that work order?

A

The Active status version will be used.

19
Q

What does the revised status of a Job Plan tell us?

A

REVISED - Has been modified and there is a later version published in Maximo

20
Q

The template type for a PM Job Plan should always be what?

A

Planned maintenance Job Plans

21
Q

How can we identify job plans that are used for condition monitoring?

A

Template type will be Condition - Job plans associated with a measuring point in condition monitoring to identify work orders generated from a predefined condition.

22
Q

Workplan template types should always have a frequency of what?

A

“AS NEEDED” Job Plans

23
Q

How can we identify job plans that are used for condition monitoring?

A

Template type will be: Condition - Job Plans associated to a measuring point in condition monitoring to identify work orders generated from a predefined condition.

24
Q

The total amount of planned labor hours is called _____ in Maximo?

A

Duration: The total amount of planned estimated job hours.

25
Q

What does the job plan classification tell us an how does that effect work orders?

A

All work orders assigned to a job plan that is classified as regulatory or UPW flow will flag on the work order.

26
Q

Should a PM/PD job plan record include tasks?

A

NO. Id a job plan includes tasks under the “Job Plan Tasks” section; technical procedure work orders will generate

27
Q

How can we determine the number of offset hours before the target start date that job plan scope can begin?

A

Start Constraint Offset: Number of hour the Job Plan scope may commence before the Target Start Date. It is part of what determines the start no earlier than date on a work order.

Daily/Weekly = 0 Hours
Monthly = 24 Hours
Quarterly = 48 hours
Semi-Annual or Greater = 72 hours

28
Q

Name six different job plans frequencies?

A

Annual
Daily
Monthly
Quarterly
Weekly
As-Needed

29
Q

What determines the job plan priority?

A

JP Priority: A Priority assigned to the Job Plan according to the Job Plan frequency.
0 Frequency < 364 days has a priority of “0”
1 frequency >= 365 days has a priority of “1”
Frequency = As Needed or Condition has a priority of “1”

30
Q

Where can we indicate how many laborers and estimated labor hours are needed for a job plan record?

A

Labor - The labor tab is used to track the craft type and estimated labor hours per Technician to perform the Job Plan scope. The fields to populate are:
1 Labor/ Craft - Populate with standard Craft Values
2 Quantity - Number of Craft resources needed to perform the work.
3 Hours - Number of hours needed to complete the work tasks, IE wrench time. Each planned labor line entry. The PM Look ahead report multiplies the quantity of crafts by the estimated labor hours to calculate the total estimated resources hour. (i.e. 2 Mechanical Techs * 2 hours = 4 total estimated labor hours to calculate the total estimated resource hours)
4 Do not calculate the total estimated resource hours per planned labor entry. The PM look ahead report multiplies the number of crafts by the estimated resource hours for all planned labor lines and populates the duration field with this total.
5 calculate the total estimated resource hours for all planned labor lines and populate the duration field with this total.

31
Q

What field would need to be modified in the Job Plan record to extend the end of the window on a PM record?

A

Finish Constraint Offset: Number of hours the Job Plan scope will remain open. This sets the control limit for how far a work order can be pushed out. It is part of what determines the Finish No Later Than date on a work order.
1. No duration = 0 Hours
2. Daily = 23 hours
3. Weekly = 167 hours (7 days)
4. Bi-Weekly = 355 hours (14 days)
Monthly and Bi-MOnthly 503 hours (21 days
Quarterly/Trimester/Semi-Annual = 671 hours (28 days)
Annual or Greater = 839 (35 days)
As needed = 839 hours

32
Q

For PM auto Orders where do you assiociate the parts in the Job Plan record?

A

Materials = Item master part numbers are tracked here to order parts when the PM associated to the Job Plan is generated.

33
Q

Can you associate an asset to a job plan and if so where?

A

Work Assets = This tab is used to associate asset entities to the job plan.

If an asset is associate to a job plan the job plan can be associate to a user Generated WO