chapter6 Flashcards
it is a tool used for planning, scheduling and monitoring project progewss
Project network
an element in the project that consumes time
activity
this is an activity that has more than one activity immediately preceding it
merge activity
these are activities that can take place at the same time
parallel activities
a sequence of connected, dependent activities
path
the path(s) with the longest duration through network, if an activity is delayed the project is delayed the same amount of time
Critical path
represent a point in time when an activity is started or completed
event
this activity has more than one activity immediately following it
burst activity
two approaches to develop project network
- activity-on-node
- activity-on-arrow
If there is a likelihood that the original critical path will change, it
is said to be
sensitive