Chapter10 Flashcards
PMIS (Project Management Information System)
A framework and methodology for collecting, organizing, storing, processing and disseminating information needed to manage projects
PMIS Objectives
Provide the basis for the strategic direction of the project
Provide the basis to plan, monitor and evaluate projects
Show the interrelationships among cost, schedule and technical performance for the entire project
Help identify project problems before they occur
Enable team to continuously monitor, evaluate, and control project resources
PMIS Provides Info For…I
Project planning – scheduling, budgeting and resource allocation
Integration of cost, schedule and work performance
Integration of activities across functional areas
PMIS Provides Info For II
Filtering information to identify problems and to determine project status
Analysis of variance, performance and forecasting
Controlling changes to system configuration and project plan
Reviewing and updating program status
Good Project Reports I
Isolate significant variances and identify the reasons they occurred
Emphasize the quantitative and specific rather than the subjective and general
Describe risks – anticipated this reporting period, occurred, response success, and anticipated next reporting period
Describe the specific cost, schedule and technology (quality) impacts on project elements
Good Project Reports II
Indicate effects on project baselines
Describe specific corrective actions taken and planned
Assign responsibility for action and give expected dates for improvement
Reference corrective action plans in previous reports
Benefits of Sharing Project Information
Promotes trust, empathy and more mature relationships among project stakeholders
Facilitates solution of problems with the project
Keeps team members working together cohesively and concurrently in the use of project resources
Builds networks with project stakeholders
Value of Project Information
“Information has no real value except as it is used effectively in the management of the project. It does not automatically lead to an effective management process. Information does not ensure success, but lack of information can contribute to project failure.”
Information to Support Project Decisions (Part I)
Progress to Date
- Cost Performance
- Schedule Performance
- Technical
Detailed Plans
- Scope
- Deliverables
- Roles
- Schedules
Information to Support Project Decisions (Part II)
Business Case
- Purpose
- Benefits
Resource Requirements
- People
- Funding
Risks
- Events
- Impacts
- Mitigation Plans
Purpose of Project Review Meetings
communicate and assess project evaluative information
identify and quickly correct deviations from project plan
Project Review Meetings (Informal Review “Peer Reviews”)
Held frequently and regularly
Involve members of the project team
Focus on project status, special problems, emerging issues, and project performance
Participation depends on project phase and issues at hand
Project Review Meetings (Daily Standup Meeting)
Held at the start of each day
Short (15 minutes) and to-the-point
An update on status
-team members give a quick run-though of yesterday’s progress and today’s next steps
Project Review Meetings (Formal Reviews)
Scheduled at milestones or critical project stages; e.g.,
Preliminary review
-Assess how well the functional design specifications fit the basic operational requirements
Critical review
-Check design for conformance to the preliminary design specifications
Project Review Meetings (Action Plan)
Created for each identified problem
Might include
- statement of the problem
- objectives in resolving it
- the required course of action
- target date
- person responsible
Each meeting starts with a status review of items on the action plan
When is time to Terminate Project?
Project now lacks strategic fit
Customer’s needs have changed
Competition threatens project results
A new, superior alternative has emerged
Serious cost and schedule overruns
Technical performance is compromised
Technical risks too great
How to terminate project?
Share the decision - tell all those affected
Revisit the need – how will original purpose be addressed?
Manage resource impacts – account for all resources used, available and requiring disposal.
Tie the loose ends – review all on-going activities for completion or closure.
Capture the experience – a lot can be learned from a termination
Project-Functional Interface
Project Manager vs Functional Manger
Project Manager What is to be done? When will tasks be done? How much money is available for tasks? How well has the total project been done?
Project-Functional Interface
Project Manager vs Functional Manger
Functional Manager How will the task be done? Where will the task be done? Who will do the task? How well has the functional input been integrated into the project?
Advantages of Functional Organizations
Personnel can be used on many projects
Specialists can be grouped to share knowledge and experience
Improved continuity in the functional disciplines, procedures and policies
Communication channels are vertical and understood
Clear career path for professionals
Disadvantages of Functional Organizations
Project orientation is often lacking
Project accountability is often unclear
There is no direct customer focal point or contact
Ideas tend to favor functional perspective
Coordination between functional units is complex and challenging
Where is project team? (Matrix Organization)
Project Manager is assigned to oversee project and interacts on an equal basis with functional managers. This PM and the functional managers jointly direct work flow and approve technical and operational decisions. The PM has some supervisor authority over the project team.
Advantages of Matrix Organizations
Project emphasized by designating a single responsible project manager
More responsive to changes than functional organization
More efficient utilization of project personnel
Increased knowledge transfer between projects
Maintains strong technical base in functional “home” office
Provides career paths and opportunities for functional specialists.
Disadvantages of Matrix Organizations
Dual reporting relationship - balance of power between functional and project groups must be watched
Resource allocation conflicts among project managers may require management intervention
Increased complexity in managing conflict, information flow, performance appraisals
Project assignments may impede career progression for functional experts