Chapter 9 Flashcards
Project Control Steps
Step 1: Monitor performance to determine how the project is coming along.
Step 2: Identify the cause of any cost and schedule problems.
Step 3: Take corrective actions to recover project performance.
Monitor and Control Project Work
the process of tracking, reviewing and reporting the progress to meet the performance objectives defined in the project management plan
How do you: monitoring Performance (Part I)
Use a variety of measures, qualitative and quantitative
Invoices
Time cards
Managers and supervisors assess progress by observation, asking questions, and reviewing reports
Achievement of milestones
Test and demonstration results.
Design reviews—meetings with managers and technical personnel to review progress
Opinions of outside experts.
How do you: monitoring Performance (Part II)
Do not only measure cost and time, which are measures of input.
Need measures of output from each task and work package
Output measures address the deliverables or results defined for each work package.
Project Control Emphasis
Scope Change Control
Quality Control
Schedule Control
Procurement Control
Project Control Emphasis (Scope Control)
- identify where changes have occurred
- ensure the changes are necessary or beneficial
- contain or delimit the changes wherever possible
- the implementation of changes.
Project Control Emphasis (Quality Control)
- manage work to achieve requirements and specifications
- take preventive measures to eliminate errors and mistakes
- identify and eliminate sources of errors and mistakes
- includes technical performance measurement, TPM
Project Control Emphasis (Schedule Control)
- Keep the project on schedule and minimize schedule overruns
- Use Time Buffers
- Fight Tendency to Multitask
- Frequently Report Activity Status
- Publicize Consequences of Delays and Benefits of Early Finish
Project Control Emphasis (Procurement Control)
- Monitor quality, schedule, and cost of all procured items
- Visit and inspect the facilities of subcontractors and suppliers
- Track subcontractors’ and suppliers’ progress and expenses,
- Prepare contingency for all major procured material, equipment, components, and services
Setting the Stage for Earned Value Analysis (5 Steps)
- Define the Work Packages
- Schedule the Work Packages
- Assign the budget to Work Packages
- Determine the Planned Value (PV),
- Establish the Performance Measurement Baseline (PMB)
Planned Value (PV)
the authorized budget assigned to the scheduled work to be accomplished. Also known as Budgeted Cost of Work Scheduled (BCWS)
PV/EV Measurment Techniques
Fixed Formula (e.g. 50/50, 0/100)
Weighted Milestones
Percent Complete
Level of Effort
Fixed Formula (50/50)
Value of work is linked to the start and finish
Fixed Formula (0/100)
Value of work is linked to the start and finish. No funds until project is 100% complete.
Weighted Milestone Method
Value of work is linked to achievement of milestones
The budgeted cost (value) of the work package is distributed and planned to reflect scheduled accomplishment of discrete milestones that occur as part the work package.