Maintaining trust, resolving conflicts, and preventing problems are all parts of:
A. Planning risk responses.
B. Managing stakeholder engagement.
C. Planning human resource management.
D. Controlling communications.
The correct answer is B
You are managing a two-year project involving staff from several departments. The project is on
schedule and within budget. A key team member leaves for a four-week vacation without completing a
highly technical and specialized activity assigned to him (activity A). The project team cannot begin
activity B or activity E (a critical path activity) until activity A is completed. Activity A has three days float
and is not on the critical path. A team member, a seller, and a non-team member work overtime to
complete activity A within its float time. You need to reimburse the non-team member’s department and
pay the seller at an overtime rate. What action should you take?
A. Pay the cost out of your project reserves.
B. Thank the others for filling in, but tell them not to waste time on non-critical path activities.
C. Send a complaint letter to the key team member’s boss and ask him to fund the extra cost
expended.
D. Reevaluate your communications management plan
The correct answer is D.
A stakeholders engagement assessment matrix can be used to identify:
.A Communications gaps.
B. Skill levels of stakeholders.
C. Additional stakeholders.
D. Key relationships between stakeholders
The correct answer is A.
A project team includes five people when the project manager adds two more. How many additional
channels of communication are there?
A. 21
B. 10
C. 7
D. 11
The correct answer is D.
Which of the following statements BEST describes how stakeholders are involved on a project?
A. They approve the project charter, help provide assumptions and create management plans.
B. They help to determine the project constraints and product deliverables.
C. They help to determine the project schedule, deliverables, and requirements.
D. They help to determine the resource needs and resource constraints on the project.
The correct answer is B.
If a project manager wants to examine project results over time to see if performance is improving, she
would use a :
A. Trend report.
B. Variance report.
C. Forecasting report.
D. Status report
The correct answer is A.
A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST
approach a project manager can take at the beginning of the project to manage this situation?
A. Get the stakeholder involved in the project as early as possible.
B. Ask that the stakeholder not be included in the stakeholder listing.
C. Talk to the stakeholder’s boss to find ways of directing the stakeholder’s activities to another
project.
D. Say “No” to the stakeholder a few times to dissuade him from submitting more changes.
The correct answer is A
You have completed project planning and are well into project executing when you discover a manager in
one of the internal clients’ departments is visiting your team members every afternoon for lengthy chats
about the project. What is the BEST thing to do?
A. Ask the manager to formally address his questions to you.
B. Meet with the manager to understand why he feels the need to communicate with your team
members.
C. Ask the manager to formally address project issues as per the communications management plan.
D. Tell your team members not to waste their time talking to the manager.
The correct answer is C.
The project has been going well, except for the number of changes being made. The product of the project is being installed into seven different departments within the company and will greatly improve departmental performance when operational. The team has selected the appropriate processes for use
on the project. The project manager is a technical expert as well as having been trained in communications and managing people. Which of the following is the MOST likely cause of the project problems?
A. The project manager was not trained in understanding the company environment.
B. Some stakeholders were not identified
C. The project should have more management oversight since it will result in such great benefits to the
company.
D. The project should have used more of the project management processes
The correct answer is B.
You are presenting your project status to the company’s management team using
visual aids and multimedia technology. What form of communication is this?
A. lnformal Verbal
B. Formal Verbal
C. Formal Visual
D. lnformal Visual
The correct answer is B.
Visual communication does not exist in the PM Book.
A salience model is used in stakeholder analysis to classify stakeholders based on their:
A. Interest, influence, and legitimacy.
B. Power, urgency, and legitimacy.
C. Impact, interest, and urgency.
D. Urgency, interest, and power
The correct answer is B.
A project manager has a problem with a team member’s performance. What is the BEST form of
communication for addressing this problem?
A. Formal verbal communication
B. Informal verbal communication
C. Formal written communication
D. Informal written communication
The correct answer is B.
When do stakeholders have the MOST influence on a project?
A. At the beginning of the project
B. Throughout the project
C. At the end of the project
D. In the middle of the project
The correct answer is A.
All of the following are true EXCEPT:
A. The stakeholders do not have a role in determining the project management plan unless they are
part of the project team.
B. The project manager needs to determine the skills of the stakeholders.
C. The communications management plan is part of the project management plan.
D. The stakeholders’ impact on the project must be assessed.
The correct answer is A.
All of the following are responsibilities of the project manager EXCEPT:
A. Get stakeholders’ sign-off that the requirements are finalized.
B. Ask stakeholders to let you know about problems in project communications and relationships.
C. Figure out when stakeholders will be involved in the project and how extensively.
D. Carefully select the appropriate stakeholders for the project.
The correct answer is D.