Chapter 9 key terms Flashcards
Activities (also called tasks)
Must either precede or follow other tasks from the beginning of the project to its completion.
Activity-on-Arrow (AOA)
Represents the task, or activity, and the node signifies an event marker that suggests the completion of one activity and the potential to start another.
Activity-on-node (AON)
The node represents an activity, and the path arrows demonstrate the logical sequencing from node to node through the network.
Arrow
Represents the task
Backward pass
Calculation of late finish times (dates) for all uncompleted network activities
Beta distribution
Distributions that are asymmetrical
Burst activity
An activity with two or more immediate successor activities (task flowing out from it)
Concurrent
When more than one activity to be accomplished at the same time.
Confidence interval
The highest reasonable probability of being accurate.
Crashing
Speeding up the project
Critical path
The path through the project network with the longest duration. These are identified as having zero float in the project.
Critical Path Method (CPM)
A Network analysis technique used to determine the amount of scheduling flexibility.
Durations
Estimate activity for each step in the project
Early start (ES) date
Earliest possible date on which the uncompleted portions of an activity can start.
Event
A point when an activity is either started or completed
Float (also called slack)
The amount of time an activity may be delayed from its early start without delaying the finish of the project.
Forward pass
Network calculations that determine the earliest start/earliest finish time for an activity.
Hammock activities
Summaries for some subsets of the activities identified in the overall project network.
Laddering
A technique that allows us to redraw the activity network to more closely sequence project subtasks, so the overall network sequence becomes more efficient.
Late start (LS) date
The latest possible date that an activity may begin without delaying a specified milestone
Linked activities
Illustrates the scheduling goal.
Merge activity
Activity with two or more immediate predecessors (tasks flowing into it)
Network diagram
Schematic display of the project’s sequential activities and the logical relationships between them.
Node
A junction point joined to some or all of the others by dependency lines.